To get a building permit in Airway Heights, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The City of Airway Heights Building Department reviews plans, issues building, mechanical and plumbing permits and inspects work inside the city; applications go in by email as PDF files, and electrical permits come from Labor and Industries.

Authority: Airway Heights Building DepartmentFiling: PDF package by emailPhone: 509-244-5514
Authority
Building Department1149 S Garfield Rd, phone and email service
Inspections
509-850-9364Monday to Thursday, 9 a.m. to 4 p.m.
New house deposit
$500 plan reviewInvoiced before review starts
Electrical
Labor and IndustriesNot a City permit

The Building Department of the City of Airway Heights issues building, mechanical and plumbing permits, checks plans and inspects construction inside the city limits. Applications go in as separate PDF files by email to bldgdept@cawh.org, an invoice for the plan review deposit follows, and review starts only once that deposit is paid; a new single-family home needs a $500 deposit. Electrical permits and inspections are handled by the Washington State Department of Labor and Industries (L&I).

The department works from 1149 S Garfield Road, with office hours of 8 a.m. to 4 p.m. on weekdays, but its counter is closed to walk-in traffic until further notice, so permit services run by phone and email. Building code questions go to 509-244-5514 and zoning or subdivision questions to the Planning Department at 509-244-2552. Airway Heights had 11,811 residents in the Census estimate for 2025; land outside the city on the West Plains is under Spokane County.

What requires a building permit in Airway Heights?

The City’s “When is a permit required?” page calls for a permit to replace a water heater, furnace or air conditioner, to install a shower or bathtub even in the same spot, to put in any carport or garage, to replace siding or roofing material, and to install solar collectors, spas, saunas or a pool 24 inches deep or more. Emergency repairs to equipment may go ahead first, but the permit must be taken out on the next working day.

Permit required

  • New homes, additions, garages, carports, and converting a carport or garage
  • Decks over 30 inches above grade at any point, over 200 sq ft, attached to a building or under a roof
  • Re-roofing with new material or new sheathing, siding, and windows or doors where framing changes
  • Water heaters, furnaces, heat pumps, ductwork, gas lines, fireplaces and pellet stoves
  • Retaining walls over 4 feet from the bottom of the footing
  • Fences in commercial and industrial zones, and any temporary fence
  • Fire sprinkler and alarm work (Fire Department permits)

No building permit

  • Sheds, playhouses and similar one-story buildings up to 200 sq ft at a home (120 sq ft on commercial sites), placed to meet zoning setbacks
  • Fences in residential zones, which still follow zoning heights
  • Patios at grade without a roof, unless excavation or fill passes the City’s limits
  • Painting, flooring, cabinets and other finish work
  • Wireless security systems and low-voltage phone or data lines

Residential fences have zoning limits even without a permit: 42 inches inside the front setback, which is the first 25 feet from the front line, and 72 inches elsewhere, measured from existing grade. Electric, barbed and razor wire are allowed only in industrial and agricultural zones as permitted, and a temporary fence needs a permit and may stay up for 180 days.

Short on time to read all of this?

Get a free quote →

What the city decides and what the state holds

Title 15 of the Airway Heights Municipal Code (AHMC) still reads as it was written in 2013 and names the 2012 editions of the building codes, with the 2021 International Fire Code added in 2024. The construction codes in force are the state’s, so the City has not written its own list of exempt work, and the City’s exemption page still carries a 6-foot fence line from an older edition. The local rules that matter are the City Manager’s role as Building Official, design values of 39 pounds per square foot of ground snow with a 30-pound minimum roof snow load and a 24-inch frost depth, the rule that a Washington-licensed designer must prepare plans for commercial buildings, buildings with five or more homes and work over 4,000 sq ft, and fees set by Council resolution.

Washington has a mandatory statewide building code under chapter 19.27 RCW that every city and county enforces and may make stricter; electrical permits come from the Department of Labor and Industries unless the city runs its own program or Tacoma Power serves the site. Building codes in Washington

Airway Heights building department: who handles permitting

The Building Department sits alongside the Planning Department under one director; the City Council agenda for October 26, 2026 lists Zachary Becker as Acting Director of Building and Planning. Public Works handles right-of-way, paving and civil permits, and the Airway Heights Fire Department takes fire sprinkler, alarm and fireworks permit applications. The City posted a notice that reviews are delayed by staff shortages and are handled in the order complete applications arrive, and in August 2026 it asked firms to bid for third-party plan review of commercial and residential projects.

Airway Heights permitting contacts
DetailInformation
OfficeBuilding Department, 1149 S Garfield Road, Airway Heights, WA 99001; open 8 a.m. to 4 p.m. on weekdays, no walk-in service
Building code questions509-244-5514; bldgdept@cawh.org (also the address for submittals)
Zoning and subdivisionPlanning Department, 509-244-2552
Inspection line509-850-9364, or online through Citizen Connect
Electrical permitsL&I Spokane office, 901 N Monroe Street, Suite 100, Spokane; 509-324-2600
Septic systemsSpokane Regional Health District

The City returns business calls within two business days. Payment by credit card carries a 3% charge on the total.

Permit types

Residential permits

For a new house the City’s residential checklist asks for residential building, plumbing and mechanical applications, a public works application where the work touches the street or utilities, building plans at no less than 1/8-inch scale, a site plan, roof truss layouts and specifications, floor joist and beam calculations, footing calculations, the state energy code worksheets and the City’s mechanical ventilation form. Every residential job also needs the Agreement to Pay Fees, and the Landowner Agent Consent Form when the applicant is not the owner. Decks have their own construction guide, and manufactured homes use a placement permit application with a public works form and a foundation report where one applies.

Not sure this scope needs a permit?

Get a free quote →

The Agreement to Pay Fees commits the owner to paying review and inspection fees as the current Council resolution sets them, plus actual costs and a 15% administrative charge. Invoices not paid within 30 days carry a late fee of 1.5% a month and stop further review, and balances left 65 days may go to collection.

Commercial permits

All commercial projects must hold a pre-application conference with the City before applying, and a pre-development review is required before zoning and land use applications and many building permits, including commercial and industrial ones. The commercial package adds the commercial application, the special inspection and testing agreement, the fee agreement and owner consent, and separate mechanical, plumbing and fire safety applications. The City sends notes from each department after a pre-development review and answers follow-up questions by email and phone.

What comes before the building permit

Two airports shape land use here. Airway Heights is mainly affected by Spokane International Airport’s Airport Compatibility Zone 5, where development with more than 180 people per net acre is prohibited along with uses such as schools, hospitals, day cares and residences in commercial or industrial zones. Fairchild Air Force Base’s Accident Potential Zone II, mainly south of Highway 2 and west of Lyons Road, bars all housing and many other uses, and its sound contours limit uses in noisy areas. The full lists are in AHMC chapters 17.15 and 17.16.

The City Council replaced the critical areas title of the code on July 20, 2026 (Ordinance C-1129). Wetlands, critical aquifer recharge areas and fish and wildlife habitat now come under AHMC Title 19, and a project that is not exempt starts with a critical area identification form and a site inspection by the City Planner. Septic systems are permitted by the Spokane Regional Health District. AHMC 15.03.090 states that the city is not within a 100-year floodplain.

Airway Heights permit costs and fees

Building, mechanical and plumbing fees are set by the most recent City fee resolution (AHMC 15.03.070 and chapter 15.08). The City does not post its building fee table online; its building page tells applicants to ask building staff for current fees, and its checklist says fees are based on ICC square-foot valuation rates adopted by resolution. What the City does publish:

Rather talk it over?

Call 1-855-478-4290 →
Airway Heights fees the City publishes
ItemFee or rule
Plan review deposit, new single-family home$500, invoiced after the application is accepted
Building permit feePer Council resolution, based on ICC square-foot valuation rates
Work started without a permitInvestigation fee equal to the permit fee, on top of it
After-hours inspectionsMinimum charge of 2 hours
Re-inspections; plan revisionsMinimum charge of 1 hour each
RefundsUp to 80% of an unused permit or plan review fee, on written request within 180 days of payment
Pre-application review (2026 planning fees)$500
Site plan review (2026)$69 residential; $138 commercial or industrial; $570 with landscaping review
Fence (2026 planning fees)$103.50
SEPA environmental checklist (2026)$500
Credit card payments3% added to the total charged
Transportation impact feeSet by Council resolution; last amended by Resolution 2026-007, approved May 18, 2026 (rates not published with the agenda)

The state building code fee set by RCW 19.27.085 applies to building permits here as everywhere in Washington; Airway Heights posts no fee table that shows it.

Trade permits and who may pull them

Mechanical and plumbing permits are City permits with their own application forms; a new house submits them with the building application. L&I issues and inspects every electrical permit in Airway Heights, which is not on L&I’s list of cities with their own electrical program, and the City’s sign rules point sign wiring to L&I’s standards. Gas lines for barbecues, cooktops, dryers and water heaters need a mechanical permit, and a lawn sprinkler system needs a permit for its backflow device.

Rather not deal with the building department?

Get a free quote →

Who issues what

  • Building, mechanical, plumbing: Airway Heights Building Department
  • Fire sprinklers, alarms, fireworks: Airway Heights Fire Department
  • Driveways, right-of-way and utility connections: Public Works
  • Electrical: L&I
  • Septic: Spokane Regional Health District

Contractors in the city

  • Contractors working in the city need a City business license as well as state registration
  • Licenses come as 48-hour, 30-day or annual licenses; an annual license runs January 1 to December 31
  • The residential application asks for the contractor’s license number and UBI, and for the plumbing contractor’s
  • How L&I registration and electrician and plumber certificates work is set out in our Washington licensing overview

How to apply for an Airway Heights building permit

1. Check the site

Use the City’s GIS maps and the aviation zone maps, and email the Planning Department about zoning; book a pre-development review for commercial, industrial or land use projects.

2. Prepare the package

Fill in the application, checklist, Agreement to Pay Fees and, if needed, the owner consent form, with drawn plans and a site plan; phone photos and Google Maps site plans are refused.

3. Email the PDFs

Send separate PDF files for the plans, applications, site plan and supporting documents to bldgdept@cawh.org; ask the department first if paper copies are needed.

4. Pay the deposit

The City emails an invoice once the submission is accepted; review starts after the deposit is paid, by card over the phone if you wish.

5. Answer the review

Send corrections as requested; unpaid invoices stop the review after 30 days.

6. Pay and pick up

Pay the remaining fees, keep the approved plans on site, and buy the electrical permit from L&I.

Review, corrections and what causes delay

The City’s own notice warns of review delays from staff shortages, with applications handled in the order complete materials arrive. An application is treated as abandoned 180 days after filing unless it has been pursued in good faith, and extensions must be asked for in writing. The residential checklist warns that an application missing any of its minimum items may not be accepted or processed, and unpaid invoices stop review. Building official decisions can be appealed to the hearing examiner within 14 calendar days.

Inspections in Airway Heights

Call the inspection line at 509-850-9364 at least 24 hours ahead, or log in to the Citizen Connect portal to request an inspection online. Inspectors work Monday to Thursday from 9 a.m. to 4 p.m.; there are no Friday inspections, so a Friday request is booked into the next week. The inspection types for each job are listed on the Progress Inspection Record issued with the permit, and the City runs one-hour Citizen Connect demonstrations every Friday, with Zoom sessions on request.

Want this handled start to finish?

Get a free quote →

A permit expires if work does not start within 180 days, if work stops for 180 days, or two years after it was issued whether or not the work is done; only an inspection the building official approves counts as work. An expired job needs a new permit priced on the value of the work left. A demolition must take out floors, footings and walls to at least 18 inches below grade, fill and grade the site, and pass a final site inspection.

Airway Heights permit search and official resources

Once logged in to Citizen Connect, people tied to a permit can see its status, total fees and balance due, inspection comments and reviews. For older permits or plans, file a request through the City Clerk’s public records page. FEMA’s Community Status Book for Washington does not list Airway Heights in either its participating or its non-participating section.

Inspections are where schedules slip.

Get a free quote →

Airway Heights building permit FAQ

Who issues building permits in Airway Heights?

The City’s Building Department at 1149 S Garfield Road, reached at 509-244-5514 or bldgdept@cawh.org. Electrical permits come from L&I.

Can I drop off plans in person?

Not at present. The counter is closed to walk-in traffic until further notice; plans go in by email as separate PDF files, and the department arranges paper submittals only where they are needed.

How much is a building permit in Airway Heights?

Fees follow the City’s fee resolution and ICC valuation rates, which are not posted online, so ask building staff for a figure. A new single-family home needs a $500 plan review deposit before review begins.

Do I need a permit for a fence?

Not in a residential zone, though the fence must stay within 42 inches in the front setback and 72 inches elsewhere. Commercial and industrial fences and temporary fences need a permit.

Do I need a permit to replace a water heater or furnace?

Yes. The City requires a permit to replace a water heater, furnace or air conditioner, and to extend or replace ductwork.

Are there inspections on Fridays?

No. Inspections run Monday to Thursday, 9 a.m. to 4 p.m., and need 24 hours’ notice by phone or through Citizen Connect.

Can I build near the airport or Fairchild?

Housing is barred in Fairchild’s Accident Potential Zone II, and Airport Compatibility Zone 5 limits density and certain uses, so check the zone before you design.

Simplify Airway Heights permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Washington. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Airway Heights sooner?

Let Alliance prepare, file, and track your Airway Heights permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Airway Heights permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.