To get a building permit in Addison County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Addison County has no county permit office: its 22 towns and the City of Vergennes issue their own zoning permits, and the state handles public buildings, septic systems and Act 250.

Authority: Town zoning administratorsCode: Vermont Fire and Building Safety Code (public buildings)Public buildings: 802-786-5867
Local permits
22 towns + VergennesZoning administrator in each
No zoning
Granville, HancockFlood hazard rules only
Public buildings
DFS Rutland office802-786-5867
Act 250
District 9District 3 for Granville, Hancock

In Addison County the permit for a house, garage or addition is a town zoning permit from the zoning administrator of the town where the land lies, or from the City of Vergennes; it checks use and setbacks, not construction. Rentals and commercial buildings also need a construction permit from the Division of Fire Safety’s Rutland Regional Office (802-786-5867). Middlebury charges $230 per new dwelling unit, and Granville and Hancock have no zoning at all, only flood hazard rules.

What needs a permit in Addison County?

Each town’s bylaw sets its own trigger, and most catch any new building, addition, change of use or subdivision. A few examples from the town rules:

  • Goshen: no building, construction, conversion, relocation or enlargement may start without a zoning permit; structures under 100 square feet that are not for human occupancy are exempt but must meet setbacks.
  • Bridport: under interim bylaws in force since July 18, 2025, sheds and similar structures up to 120 square feet and 10 feet high may sit within a yard if they stay at least 10 feet from any property line.
  • Middlebury: the town calls its permit a “zoning (building) permit”; it must be posted where the public can see it for 15 days before work starts, and it lasts 2 years.
  • Granville and Hancock: no zoning permit, but building in a mapped flood hazard area needs the town’s flood hazard approval.

State permits

  • Construction permit for public buildings, which in Vermont include rental housing and commercial premises
  • Wastewater system and potable water supply permit for a new septic, well or added bedrooms
  • Act 250 land use permit above the district thresholds
  • Residential energy certificate (RBES) for new homes and for additions, alterations and repairs to homes of three stories or less

Exempt locally

  • Farm structures under the state’s agricultural practices (Goshen and Monkton ask for written notice first)
  • Small sheds below each town’s size limit
  • Repairs that do not enlarge the footprint or change the use (Goshen’s wording)

Addison County building department: who handles permitting

Vermont counties have no general government, so nothing is filed with “Addison County”. Every town has its own zoning or land use bylaw except Granville and Hancock, which regulate only flood hazard areas. Vergennes is the county’s only city and has its own Development Review Board; there are no incorporated villages. Most towns use a Development Review Board for conditional uses, variances and subdivisions, while Ferrisburgh, Ripton and Weybridge still use a Zoning Board of Adjustment.

Short on time to read all of this?

Get a free quote →
Addison County municipalities and their land use rules
MunicipalityLocal rulesOffice phone
AddisonZoning and Subdivision Regulations, adopted November 2024802-759-2020
BridportZoning Regulations (2006) plus interim bylaws effective July 18, 2025 for two years802-758-2483
BristolUnified Development Regulations, voter-approved November 5, 2024802-453-3648 (zoning); town office 802-453-2410
CornwallZoning By-Laws and Regulations; Subdivision Regulations (2008)802-462-2775 (zoning 802-349-9772)
FerrisburghLand Use Regulations effective June 23, 2026; Zoning Board of Adjustment802-877-3429
GoshenZoning Bylaws adopted April 11, 2008802-247-6455
LeicesterUnified Zoning Bylaws (2017)802-247-5961
LincolnZoning Bylaws approved December 5, 2023802-453-2980
MiddleburyZoning and Subdivision Regulations effective September 13, 2022802-388-8100
MonktonUnified Planning Document adopted by voters March 7, 2023802-453-3800
New HavenZoning and Subdivision Regulations adopted April 2024802-453-3516
OrwellLand Use Regulations (2019)802-948-2032
PantonZoning and Subdivision Regulations adopted July 11, 2017802-475-2333
RiptonUnified Development Bylaw adopted October 8, 2018; Historic District Commission802-388-2266
SalisburyUnified Regulations effective March 31, 2026802-352-4228
ShorehamUnified Development Regulations, last amended January 31, 2024802-897-5841
StarksboroLand Use and Development Regulations effective January 28, 2020; interim flood hazard and river corridor bylaw effective September 15, 2026802-453-2639
Vergennes (city)Zoning and Subdivision Regulations, amended effective November 18, 2025802-877-1232
WalthamZoning, Subdivision and Floodplain Regulations (September 9, 2019)802-877-3641
WeybridgeZoning Regulations adopted January 3, 2017802-545-2450
WhitingZoning Regulations and Subdivision Regulations802-623-7813
GranvilleNo zoning; Flood Hazard Area Regulations (2009, update adopted December 8, 2025)802-767-4403
HancockNo zoning; Inundation Hazard Area Regulations adopted April 21, 2009802-767-3660

Not sure this scope needs a permit?

Get a free quote →

Several zoning administrators work part time and see applicants by appointment: the Vergennes office is open Monday 12:30 to 4:30 pm and Tuesday 8 am to noon, Ferrisburgh’s Monday to Wednesday 1 to 4 pm, and Bristol’s walk-in hours run Monday to Wednesday 10 am to 4 pm.

State permits for Addison County projects

The state offices for this county are split along its eastern edge. Granville and Hancock, in the mountains on Route 100, are served from Springfield and Montpelier for wastewater and Act 250, while every other town looks to Rutland and Essex Junction.

State offices serving Addison County
PermitOfficeContact
Construction permit for a public building; electrical and plumbing work noticesDivision of Fire Safety, Rutland Regional Office, 56 Howe Street, Building A, Suite 200, Rutland (all Addison County towns)802-786-5867
Wastewater system and potable water supply permitDEC Rutland regional office, 271 North Main Street, Suite 215, Rutland; Granville and Hancock: Springfield office, 100 Mineral Street802-786-5900; Springfield 802-522-2220
Act 250 land use permitDistrict 9 Environmental Commission, 111 West Street, Essex Junction; Granville and Hancock: District 3, 10 Baldwin Street, Montpelier802-261-1945; District 3 802-261-1947
Residential energy certificate (RBES)Copies to the Department of Public Service and the town clerk–

The wastewater application fee is $306.25 for a design flow of 560 gallons a day or less from July 1, 2026, and applications go through ANR Online. On the Land Use Review Board’s list updated September 24, 2026, Shoreham, Granville and Hancock are 1-acre towns, where Act 250 applies to development on tracts of more than one acre instead of ten; the rest of the county is 10-acre. Since July 14, 2026 a new home may follow either the 2020 or the 2024 residential energy standards.

Rather talk it over?

Call 1-855-478-4290 →

Zoning permit fees in Addison County towns

Each town sets its own fees, usually by Selectboard order, and most add the state’s $15 per page recording fee. These are the posted schedules for a new house or a smaller project:

Posted zoning permit fees
TownNew houseSmaller projects
Middlebury (updated July 2, 2026)$230 per dwelling unit + $15 per page recordingGarage, shed, addition or pool $70; double fee if work started first
Bristol (effective February 1, 2025)$0.10 per sq ft + $50 per unitAccessory structure $75; 4 times the fee without a permit
Addison (effective January 1, 2020)$300Accessory outbuilding $125; addition $200 or $125
Bridport$345Addition, garage, deck or shed $170
Monkton (adopted February 11, 2025)$0.30 per sq ft of first and second floors + $50–
Lincoln (effective July 1, 2019)Greater of $0.15 per sq ft of living space or $150Outbuilding 100–499 sq ft $50
Starksboro (approved September 16, 2025)$150 per unit + $0.15 per sq ft + $15After-the-fact permit 3 times the fee
Panton (October 2025)$150 to $350 by size, including a $100 certificate of occupancySame size bands
Goshen (July 7, 2023)$115Footprint 400 sq ft or less $60
Ripton$115 including recordingAddition or renovation $65

Panton’s bands make a simple example: a 1,500-square-foot addition falls in the 1,001 to 2,000 square foot band and costs $200, of which $100 is the certificate of occupancy. Middlebury also charges $300 per equivalent residential unit to connect to town water and $400 to connect to town sewer.

Rather not deal with the Addison County building department?

Get a free quote →

Electrical, plumbing and fire safety work

No Addison County municipality holds a Division of Fire Safety inspection agreement, so state construction permits, electrical and plumbing work notices and fire alarm or sprinkler permits for public buildings all go to the Rutland Regional Office. The Division requires a work notice or permit before any covered work starts, and it has a shorter construction permit application for renovations under $200,000. Electricians and plumbers working on those buildings hold state licences.

How to get a permit in Addison County

1. Find the town

Use the table above; a Vergennes parcel goes to City Hall, not to Ferrisburgh, Panton or Waltham.

2. Talk to the zoning administrator

Many work part time, so call or email for an appointment and ask whether the project also needs the Development Review Board.

3. File the town application

Attach a site sketch with setbacks, pay the town fee and wait out the 15-day appeal period before starting.

4. Add the state permits

New bedrooms, wells and septic systems need the DEC permit; rentals and commercial space need the Rutland fire safety office.

5. Check Act 250

Call the District 9 coordinator, or District 3 for Granville and Hancock, before buying land for a larger project.

6. Close out

Ask the town for its certificate of occupancy or compliance and file the energy certificate with the town clerk.

Inspections and close-out

Town zoning offices check setbacks and use rather than construction, and several issue a certificate of occupancy or compliance at the end: Addison includes it in the permit fee, Bridport asks to be told when work is finished so it can issue one, and Panton’s fees build in $100 for it. Construction inspections on public buildings come from the Rutland Regional Office. On an owner-occupied house no town or state office inspects the structure, so the RBES certificate, posted near the electrical panel or heating equipment, is often the main record of the work.

⚠️ Two Addison towns are outside the flood insurance program. FEMA lists Waltham and Whiting among communities not in the National Flood Insurance Program; the other 21 municipalities participate.

Want this handled start to finish?

Get a free quote →

Vermont building code

Vermont has no statewide building code for an owner-occupied single-family home. The state code covers public buildings, including rented homes, and each town decides whether it runs a building department or only issues zoning permits. Vermont rules

Addison County permit FAQ

Does Addison County issue building permits?

No. Vermont counties have no permit office; the 22 towns and the City of Vergennes issue zoning permits, and the state permits public buildings, septic systems and Act 250 projects.

Which Addison County towns have no zoning?

Granville and Hancock. Both regulate building in flood hazard areas only, and both are 1-acre towns for Act 250 in District 3.

How much is a permit for a new house in Middlebury?

$230 per dwelling unit under the schedule updated July 2, 2026, plus $15 per page to record the permit.

When can I start work after the permit is issued?

Middlebury permits must be posted for 15 days before work starts, and Bridport says not to start until the permit has been issued for 15 days. That window is the appeal period.

Where do I apply for a septic or well permit?

The DEC Rutland regional office (802-786-5900) for most of the county and the Springfield office (802-522-2220) for Granville and Hancock; the fee is $306.25 for a design flow of 560 gallons a day or less.

Which Act 250 district covers Addison County?

District 9 in Essex Junction (802-261-1945) for all towns except Granville and Hancock, which are in District 3 in Montpelier.

Addison County permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Inspections are where schedules slip.

Get a free quote →

Simplify Addison County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Vermont. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Addison County sooner?

Let Alliance prepare, file, and track your Addison County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Addison County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.