Granbury, Texas Building Permit Guide

Granbury’s building department at City Hall on West Bridge Street permits and inspects construction inside the city through OpenGov, and projects filed since July 21, 2026 follow the 2024 I-Codes and 2023 NEC.

Authority: Inspections & PermittingCode: 2024 I-Codes, 2023 NEC (from July 21, 2026)Phone: 682-279-8234
Authority
Building Inspections, Permits & Code EnforcementCity Hall, 116 W. Bridge St.
Apply online
OpenGovPermits, documents & inspections
Code cycle
2024 I-Codes2023 NEC
Inspections
4:30 p.m. cutoffNext business day

Building permits inside Granbury are issued by the City’s Building Inspections, Permits & Code Enforcement department at City Hall, 116 W. Bridge St., and only contractors registered with the City can apply, through the OpenGov portal. The building fee is worked out from the ICC building valuation for the square footage, a new house or addition gets its first review in about two weeks, and inspections requested by 4:30 p.m. are made the next business day.

What requires a permit in Granbury?

A permit is needed for new buildings, additions, remodels and certain repairs or alterations. Cosmetic work such as wallpaper, carpet, paint, cabinets or trim does not need one. The City’s OpenGov list covers these permit types:

Homes and lots

  • New houses, additions and remodels
  • Sheds, garages, carports, patio covers and portable buildings
  • Re-roofing, fences and retaining walls
  • Pools and spas, irrigation systems and solar panels
  • Electrical, plumbing and mechanical work, each on its own permit
  • Driveway approaches, city sidewalks and curb cuts
  • Site grading, demolition and house moving
  • Protected tree removal and water wells

Businesses

  • New commercial buildings, finish-outs and commercial demolition
  • Certificates of Occupancy for every new tenant, owner, name or use
  • Signs, under Article 7 of the Zoning Ordinance
  • Fire alarm, sprinkler, kitchen hood and underground fire line systems
  • Fuel and propane tanks
  • Tents, temporary field offices, construction cargo containers and seasonal sales

Granbury building department: who handles permitting

Building Inspections, Permits & Code Enforcement reviews plans, issues construction permits and inspects residential and commercial work inside Granbury city limits against the approved plans and the building, electrical, mechanical, plumbing and municipal codes. Floodplain development permits inside the city come from the City Engineer and Public Works. Granbury lies in Hood County.

Short on time to read all of this?

Get a free quote →
Granbury permitting contact
DetailInformation
DepartmentBuilding Inspections, Permits & Code Enforcement
Phone682-279-8234 (department); 817-573-1114 (City Hall)
Emailinspections@granbury.org
OfficeFirst floor, City Hall, 116 W. Bridge St., Granbury, TX 76048 (mail: P.O. Box 969)
HoursMonday–Thursday 7:30 a.m.–5:30 p.m.; Friday 8:00 a.m.–5:00 p.m.
PaymentCash, check, credit card or online

OpenGov and contractor registration

Contractors, developers and property owners create an OpenGov account to register, apply, upload documents, pay, request or cancel inspections and track status. Every general contractor and subcontractor on a job must be registered and current and named on the permit before it is issued, and electrical, plumbing and mechanical subcontractors each pull their own permit; sign contractors register and pull individual sign permits too.

Registration costs $100 a year (a lapsed registration adds $50). HVAC contractors, electricians, plumbers and fire alarm, sprinkler and suppression contractors are excluded from that fee.

Granbury permit fees

Fees are set in Article 1.50 of the Code of Ordinances as amended by Ordinance 26-56, passed September 1, 2026. The building permit fee is based on valuation: the structure’s square footage times the ICC Building Valuation Data figure for its occupancy and construction type, priced on this table, plus a $30 permit issuance fee and plan review billed by the hour.

Granbury building permit fee by valuation
ValuationFee
$1–$500$23.50
$501–$2,000$23.50 for the first $500, plus $3.05 per extra $100
$2,001–$25,000$69.25 for the first $2,000, plus $14 per extra $1,000
$25,001–$50,000$391.25 for the first $25,000, plus $10.10 per extra $1,000
$50,001–$100,000$643.75 for the first $50,000, plus $7 per extra $1,000
$100,001–$500,000$993.75 for the first $100,000, plus $5.60 per extra $1,000
$500,001–$1,000,000$3,233.75 for the first $500,000, plus $4.75 per extra $1,000
Over $1,000,000$5,608.75 for the first $1,000,000, plus $3.65 per extra $1,000

Not sure this scope needs a permit?

Get a free quote →
Other Granbury permit fees (September 2026)
ProjectFee
Residential / commercial plan review$50 / $75 per hour
Carport, garage, shed, patio cover or portable building$50 plus $0.03 per sq ft
Residential re-roof: up to 3,000 sq ft / larger$100 / $150
Fence / retaining wall$50 / $100
Residential irrigation system$75
Driveway approach / curb cut$70 / $30
Residential electrical$50 plus $0.04 per sq ft
Residential plumbing, by size$40 (to 500 sq ft) up to $120 (2,501–3,000 sq ft), plus $25 per extra 1,000 sq ft
Residential HVAC / repair or change-out$100 / $75
Water heater, water line or sewer line change-out$75
Floodplain development permit$250
Commercial Certificate of Occupancy / temporary C.O. (180 days)$100 / $200
Re-inspection$50 per hour
After hours, weekends and holidays$100 per hour, 2-hour minimum

Starting work before the permit is issued doubles the fee, and lifting a stop-work order costs $100. Residential pools pay the same as building permits. Utility connections are separate: a 1-inch water tap with meter box is $2,500 ($4,500 with a street cut), a 3/4-inch meter set $600, and a sewer tap of 4 inches or less $1,600 ($3,200 with a street cut). Water and wastewater impact fees depend on meter size and on when the lot’s final plat was recorded in Hood County; for lots platted before February 9, 2019 they total $1,681 for a 3/4-inch meter.

Rather talk it over?

Call 1-855-478-4290 →

Trade, fire and septic permits

Each electrical, plumbing and mechanical subcontractor files a separate permit in OpenGov. Typical residential trade fees after the September 2026 changes: an electrical service change of 200 amps or less $75, a panel replacement $50, solar panels $75, and an annual gas test $100 per building. Fire sprinkler systems are $250 each, kitchen hood suppression $100 and sprinkler underground $100. The fee schedule also charges $500 to install an on-site sewage system, with plan review at $47 an hour.

Gas tests, electrical service changes and reconnects, water and sewer lines and septic systems are treated as emergency inspections and done the same day.

Plans and review for new homes and commercial buildings

New house

  • One set of plans with elevations (36×24 in., or legible 11×17) and an electronic copy
  • Framing, roof framing, electrical, plumbing and mechanical plans
  • Plot plan with dimensions to the property lines
  • Engineered foundation plan, signed, dated and sealed
  • Wind bracing for walls over 60 ft, joist and rafter schedule, and engineering for beams spanning over 14 ft
  • A soil report if more than 2 ft of fill is needed, and the energy code submittal

Commercial

  • OpenGov application with PDF plans plus one paper set
  • Sealed architectural, structural, MEP and plumbing riser drawings
  • Energy compliance report for envelope, lighting and mechanical
  • Asbestos survey or declaration
  • TDLR accessibility registration for work over $50,000
  • Approved plat and a released site plan before the permit is issued

Plan review for a house checks that impervious cover stays within 60% of the lot and enclosed building cover within 40%, that masonry covers at least 80% of the exterior walls, that there is an enclosed two-car garage, and that the house is no taller than 2.5 stories or 35 ft (planned developments may differ). The City aims to finish the first review of a new house or addition in two weeks and revisions in 5 days. The City’s residential guidelines sheet dated September 2025 still names the 2021 codes; projects submitted since July 21, 2026 are reviewed under the 2024 codes.

Rather not deal with the building department?

Get a free quote →

How to get a Granbury building permit

1. Finish platting and zoning

You can apply while a plat or zoning case is pending, but the permit is not issued until both are approved; commercial sites also need a site plan with the 30 elements in Section 11.11 D of the Zoning Ordinance.

2. Register every contractor

The builder and all subcontractors register in OpenGov and are listed on the permit.

3. Apply in OpenGov

Upload the plan set and documents, and pay the issuance fee and plan review.

4. Answer review comments

Expect about two weeks for a house’s first review and 5 days for each revision.

5. Submit the form board survey

After the permit is issued and before the foundation is poured, the form board survey must show the minimum foundation elevation (a 2% rise from the curb flowline plus 12 in.) and fill compacted to 95%, with lab results.

6. Book inspections in OpenGov

Commercial jobs also hold a preconstruction meeting (817-573-1114), and fire lanes must be in place before vertical construction.

Inspections in Granbury

All inspection requests go through OpenGov; those received by 4:30 p.m. are scheduled for the next business day, and results appear in OpenGov or on the job site. A new house typically goes through these inspections:

  • Grade, with vegetation cleared from the footprint and the address posted, and the temporary power pole
  • Plumbing rough, then foundation, after the form board survey is approved
  • Plumbing top-out, mechanical rough and electrical rough
  • Brick ties, sheathing, lath and braced walls, then framing
  • Insulation, with a third-party report uploaded
  • Approach and sidewalk, electrical meter release and gas release
  • Plumbing, mechanical, electrical and irrigation finals (irrigation needs a backflow test report), energy compliance and building final

Want this handled start to finish?

Get a free quote →

At the final, the electrical panel must carry a permanent circuit schedule, the energy certificate and the sprinkler as-builts. The City’s checklist also calls for frost-proof hose bibs, a rain and freeze sensor on irrigation, and at least R-8 flex duct, and a study with a closet is treated as a bedroom for smoke alarms. Commercial foundations need an elevation certificate as well as the form survey, and every new tenant, owner or use needs a Certificate of Occupancy before utilities are released in its name.

Texas building code

Texas has no single statewide building code: state law makes the International Residential Code the base code for homes in cities and the International Building Code the base for commercial buildings, with each city choosing the edition and its own amendments, while the National Electrical Code and the energy code apply statewide. Outside city limits most counties issue no building permits for homes. Texas building code rules

Granbury official resources

Inspections are where schedules slip.

Get a free quote →

Frequently asked questions

How much is a building permit in Granbury?

It depends on valuation: square footage times the ICC Building Valuation Data figure, priced on the City’s table (for example $993.75 for the first $100,000 plus $5.60 per extra $1,000), plus a $30 issuance fee and hourly plan review.

How long does residential plan review take?

About two weeks for the first review of a new house or addition, and 5 days for revisions.

Can a homeowner pull a permit in Granbury?

The City issues permits only to contractors and subcontractors registered with it, and every one working on the job must be listed on the permit.

Do I need a permit for a fence or roof?

Yes. A fence permit is $50 and a residential re-roof $100 up to 3,000 sq ft.

When will my inspection happen?

Requests made in OpenGov by 4:30 p.m. are scheduled for the next business day; gas tests, service changes and utility line inspections are done the same day.

Which codes apply?

The 2024 International Codes and 2023 National Electrical Code with the regional amendments, for projects submitted on or after July 21, 2026.

Simplify Granbury permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Texas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Granbury sooner?

Let Alliance prepare, file, and track your Granbury permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Granbury permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.