Gray County, Texas Building Permit Guide

Gray County publishes no building permit for rural homes; the Commissioners Court rules on subdivision plats and pipeline or utility crossings under county roads, while Pampa’s Building Department permits construction inside that city.

Authority: Commissioners Court (plats, road crossings); City of Pampa Building Department inside PampaCode: No county building codePhone: 806-669-8008 (County Judge)
County permits
Plats and road crossingsNo county building permit
Plat application
$1,000Recording fees extra
Road crossing
$500 inspection feeAgreement of April 15, 2024
2025 population
20,919

Gray County does not publish a building permit or inspection program, so a house built outside Pampa, McLean or Lefors gets no county building permit. What the county does regulate is land division and its roads: the Commissioners Court approves residential subdivisions under rules in force since October 1, 2022 (a $1,000 application fee) and signs road crossing agreements for lines bored under county roads ($500 on-site inspection fee). Inside Pampa, the City’s Building Department permits new construction, repairs and remodels.

What needs county approval in Gray County?

County approvals

  • A preliminary and final plat for any division outside a city that creates two or more lots of 10 acres or less meant for homes
  • A Commissioners Court road crossing agreement before a pipeline, water line, flow line or cable goes under or along a county road right-of-way
  • Court acceptance before the county takes over maintenance of a new road
  • Court approval to amend, replat or vacate a recorded plat

Not a county permit

  • Building, electrical, plumbing or mechanical permits for houses and businesses in the unincorporated county: the county publishes none
  • Construction inside Pampa, which the City permits
  • Divisions for agricultural, wildlife management or timber use, gifts or sales to a relative, or lots over 10 acres where no land is set aside for public use
  • Lots sold through the Veterans Land Board, state-owned land, and transfers among owners who already held an undivided interest

Lots of 10 acres or less are presumed to be residential unless the plat and every deed restrict them to other uses. No lot may be sold until the preliminary plat is approved, and knowingly breaking the subdivision rules is a Class B misdemeanor.

Short on time to read all of this?

Get a free quote →

Who issues permits in each part of Gray County?

The Census lists three incorporated places in Gray County: Pampa, the county seat (about 16,400 residents), McLean (about 630) and Lefors (about 430). Everything else is unincorporated and falls to the county offices below.

Gray County permit offices by area
AreaWho issues permits
City of PampaCity Building Department (Public Works, Code Enforcement), City Hall, 200 W. Foster Ave., Room 204; 806-669-5740; Monday–Friday 8 a.m.–4 p.m. It permits new construction and the repair or remodeling of existing buildings, and plumbing, electrical and mechanical work needs a state licence. Floodplain questions go to the Assistant Public Works Director (806-669-5750).
LeforsThe published sources do not say who issues building permits; ask City Hall. The state floodplain directory lists the City Secretary, 806-835-2200, as the town’s floodplain contact.
McLeanThe published sources do not say who issues building permits in McLean; City Hall is on 806-779-2481.
Unincorporated county: plats, road crossings, road acceptanceCommissioners Court, through the County Judge’s office, Gray County Courthouse, 205 N. Russell, Pampa, TX 79065; 806-669-8008
Septic systemsTCEQ Region 1, 5809 S. Western St., Suite 260, Amarillo, TX 79110; 806-353-9251 (TCEQ lists no local authorized agent for Gray County)
Unincorporated county: floodplainEmergency Management Coordinator, 806-669-8007, listed as the county’s floodplain administrator in the Texas Water Development Board directory
Plat recordingCounty Clerk, P.O. Box 1902, Pampa, TX 79066; 806-669-8004

Inside the extraterritorial jurisdiction of Pampa, Lefors or McLean, the county may sign an interlocal agreement with that city deciding whether a new subdivision follows the city’s development rules or the county’s. Precinct commissioners can be reached directly: Precinct 1 806-662-6957, Precinct 2 806-773-4224, Precinct 3 806-662-6222 and Precinct 4 806-662-7331.

Not sure this scope needs a permit?

Get a free quote →

Gray County fees

Gray County fees
ItemFee
Application to create a subdivision (preliminary plat)$1,000, covering county inspections and staff time
Plat filing and recordingCharged separately by the County Clerk
Road crossing agreement$500 on-site inspection fee
Road crossing for agricultural useNo fee, if a majority of the Commissioners Court approves

The subdivision rules refer amending plats, replats and plat vacations to the county’s adopted fee schedule, which is not posted on the county website. The court will not accept or review a plat from anyone who owes the county delinquent taxes or fees until they are paid or a payment arrangement is made.

How to get a subdivision plat approved in Gray County

1. Tell the county

Notify the County Judge or the commissioner for your precinct that you intend to create a subdivision.

2. Attend the pre-application meeting

The precinct commissioner sets up an informal meeting with county staff, hands over the rules and the application, which doubles as the preliminary plat checklist, and goes over the fee.

3. Present the preliminary plat

Ask for a place on a Commissioners Court agenda and present the plat, the application and the $1,000 fee. The plat shows every lot’s size, the roads, easements, contours, a drainage plan and any housing size limits in the deeds.

4. Wait for the decision

Once the plat passes the completeness check the court must act within 30 days, or the plat is deemed approved; where groundwater certification is needed the 30 days start when it is filed. A denial comes within 10 days with a list of deficiencies.

5. Build the infrastructure and file the final plat

Preliminary approval lasts 2 years, with one 1-year extension. The final plat adds the water and wastewater arrangements, utility providers’ written agreement and road names and 9-1-1 numbers set with the Panhandle Regional Planning Commission. A developer can instead skip the preliminary stage by posting a bond for the roads and drainage.

6. Record it

Give the court 5 copies; once approved, the final plat on 4 mil mylar, signed by every utility provider, is recorded with the County Clerk. It lapses after 2 years if construction has not started.

Rather talk it over?

Call 1-855-478-4290 →

Road, water and septic rules in the county

Water and septic: a subdivision needs a 30-year water supply, either from a utility or from groundwater certified by a licensed engineer or hydrologist. Lots with their own well and septic system must meet Panhandle Groundwater Conservation District and state requirements, wells must be drilled by a Texas-licensed driller and septic systems installed by a Texas-licensed installer. Pit privies and portable toilets are not accepted on platted lots. No local authorized agent runs septic permitting in Gray County, so permits for individual systems come from the TCEQ Region 1 office in Amarillo.

Floodplain: development in a special flood hazard area is not allowed on a subdivision plat, and the county may set flood standards stricter than FEMA’s minimum.

Rather not deal with the Gray County building department?

Get a free quote →

Roads: new county roads need at least 80 ft of right-of-way and a 24-ft roadbed with 6 inches of compacted caliche and a 3% crown, culverts of at least 24 inches, and cul-de-sacs no longer than 600 ft with a 40-ft turnaround radius. Lots with 90 ft or more of frontage may have two driveways at least 20 ft apart; narrower lots get one. The court does not have to accept a road for maintenance and may have it inspected by an engineer at the developer’s cost.

Setbacks and easements: where there is no adopted fire code and no water lines sized for firefighting, buildings sit at least 10 ft from roads and 5 ft from adjacent property lines, and utility easements are at least 15 ft wide.

Road crossings: under the agreement approved April 15, 2024, lines are bored under the full width of the road and cased from one right-of-way line to the other, at least 36 inches below the ditch, never within 50 ft of a bridge end or 20 ft of a culvert. Give the County Judge’s office and the commissioner at least 2 days’ notice before work starts, backfill the top 24 inches with crushed lime rock, add a copper tracer wire to non-metallic pipe and mark each crossing above ground; every crossing must appear on the county road map.

Texas building code

Texas has no single statewide building code: state law makes the International Residential Code the base code for homes in cities and the International Building Code the base for commercial buildings, with each city choosing the edition and its own amendments, while the National Electrical Code and the energy code apply statewide. Outside city limits most counties issue no building permits for homes. Texas building code rules

Want this handled start to finish?

Get a free quote →

Gray County official resources

Gray County permit FAQs

Do I need a county building permit to build a house in rural Gray County?

No. The county publishes no building permit or inspection program for the unincorporated area. A new lot of 10 acres or less still has to be on an approved plat, and a subdivision’s lots need a 30-year water supply and a licensed septic installation or a sewer connection.

Inspections are where schedules slip.

Get a free quote →

Who issues building permits in Pampa?

The City of Pampa Building Department at City Hall, 200 W. Foster Ave., Room 204 (806-669-5740), for new construction, repairs and remodels inside the city.

How much does a subdivision plat cost in Gray County?

The application fee is $1,000, plus the County Clerk’s recording fees.

How long does plat approval take?

The Commissioners Court must act within 30 days of a complete plat being presented, or it is deemed approved.

Do I need permission to run a line under a county road?

Yes. Sign the county road crossing agreement and pay the $500 on-site inspection fee; agricultural crossings can be exempted from the fee by court vote.

Who is the floodplain contact for unincorporated Gray County?

The county Emergency Management Coordinator, 806-669-8007, according to the state floodplain administrator directory.

Simplify Gray County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Texas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Gray County sooner?

Let Alliance prepare, file, and track your Gray County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Gray County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.