Blanco County issues no building permit for a house in the unincorporated county. What it does permit is septic systems (through the County Inspector, from $300 for a home), driveways onto county roads, 911 addresses and, under its fire code, new or substantially improved commercial, public and larger multi-family buildings. The City of Blanco and Johnson City issue their own building permits inside their limits.
What needs a county permit in Blanco County?
County permit or approval
- Septic system (OSSF): new, repair or expansion
- Driveway entering a county road
- 911 address for a new home site
- Commercial buildings, public buildings and multi-family buildings of 4 or more units: Fire Code permit
- Fire alarm, sprinkler, hood and other fire systems; fuel tanks
- Subdivision plats and replats
No county permit
- Building permit for a house, addition or barn outside city limits
- Electrical, plumbing or mechanical permits outside city limits
The county’s own pages list no building or trade permit for homes. Wells are permitted by the Blanco-Pedernales Groundwater Conservation District, not the county.
Short on time to read all of this?
Get a free quote →Who issues permits in Blanco County?
| Area or work | Who issues permits |
|---|---|
| City of Blanco | The City: construction, fire and sign permits; City Hall, 300 Pecan Street, 830-833-4525 |
| Johnson City | The City’s Development Services; Bureau Veritas reviews plans and inspects; City Hall, 303 E. Pecan Dr., 830-868-7111 ext. 8 |
| Round Mountain | The published sources do not say; ask the town |
| Septic systems, whole county except Johnson City and Round Mountain | County OSSF Inspector, 830-868-2117 (TCEQ’s agent, the City of Blanco included) |
| Septic systems in Johnson City and Round Mountain | Johnson City is TCEQ’s agent inside its own limits; TCEQ names no local agent for Round Mountain, which leaves its Region 11 office in Austin |
| Fire Code permits, unincorporated county | Blanco County Fire Marshal, 830-868-8223 |
| Driveways on county roads | The County Commissioner’s office for the precinct |
| 911 addresses | Rural Addressing, County Courthouse, Johnson City, 830-868-2008 |
Development Services uses a temporary office at 200 North Ave. G in Johnson City (mail: P.O. Box 471, Johnson City, TX 78636). The courthouse is at 101 E. Pecan in Johnson City.
Trade permits and inspections inside the cities
Outside city limits there is no county electrical, plumbing or mechanical permit. Inside the cities:
- City of Blanco: lists electrical, plumbing, irrigation, roofing, fence, pool, driveway and demolition permits among its construction permits, with fire plan review handled by the City as well.
- Johnson City: Development Services receives all building and trade applications and books inspections, which Bureau Veritas carries out. Requests made by 4 p.m. are inspected the next business day. Johnson City builds to the 2015 International codes and the 2015 National Electrical Code.
Not sure this scope needs a permit?
Get a free quote →County applications and how they are filed
- Septic (OSSF) application: filed in the owner’s name with the current tax receipt or signed deed, the 911 address, the site evaluation and construction plan with setbacks, a professional design where required, an aerobic maintenance contract where it applies, and a power of attorney if someone else files. Systems that spray effluent need an Affidavit to the Public recorded with the County Clerk ($21) first.
- Fire Code applications: the Fire Code Building Permit, Fire Suppression, System/Special Construction, Business Operational and Mass Gathering forms are posted on the county’s iWorQ portal. Email the completed form and plans to FireMarshal@co.blanco.tx.us; processing takes about 30 days, and the office calls or emails when the permit is ready.
- 911 Address Application: also on the iWorQ portal. The GIS office needs a copy of the driveway access permit before it issues the address.
- Plats and replats: filed with Development Services on the dates in the county’s 2026 drop-off calendar for new development.
Blanco County permit fees
| Permit | Fee |
|---|---|
| Single-family home | $300 |
| Single-family home with professional design | $375 |
| Home repair or expansion (drain field or tank only) | $150 |
| Commercial or recreational | $450 |
| Mobile home or RV park | $60 per unit, $500 minimum |
| Commercial or park repair or expansion | $225 |
| Filing fee (County Clerk) | $40 home; $60 designed system |
| Re-inspection | $150 |
| Variance / replat site review | $50 each |
Rather talk it over?
Call 1-855-478-4290 →Fire Code permits are priced on project value: $50 up to $1,000; $50 plus $7 per additional $1,000 up to $50,000; $393 plus $6 per $1,000 up to $100,000; $687 plus $5 per $1,000 up to $350,000; and $1,888 plus $4 per $1,000 up to $700,000. Other Fire Marshal fees include $125 for a preliminary plan review, $150 for a change-of-occupancy inspection, $250 plus $0.50 per device over 10 for a fire alarm, $250 plus $0.50 per head over 35 for a sprinkler system, $150 for a kitchen hood system and $300 per aboveground fuel tank. Work started without a required permit is charged double. RV and tiny home parks pay a $2,500 filing fee and $175 per pad.
Inspections and project closeout
Septic: the County Inspector will not enter a property unless the blue 911 address plate is visible from the road. Septic permits are valid for one year, and a failed inspection costs $150 to repeat.
Fire Code buildings: post the permit and the street number where they can be seen from the road. The Fire Marshal may inspect as often as needed. When the building is ready, submit a Request for Final Inspection signed and sealed by a Texas engineer or architect or an ICC-certified building official; buildings with fire protection systems also need the State Fire Marshal’s Form 009. After a passing final, the Fire Marshal issues a Certificate of Compliance and releases utilities, and the building may not be occupied without it.
Permit life: Fire Code work must start within 180 days of issue; the Fire Marshal can grant two 6-month extensions on written request.
Rather not deal with the Blanco County building department?
Get a free quote →Blanco County development rules
Lot size: lots served by a private well and septic need at least 5 acres and 250 feet of road frontage. The septic checklist applies the same 5-acre minimum to land platted after 1998, sets a 1,000-gallon minimum tank, and keeps drain fields 50 feet from property lines in subdivisions platted after 1998.
Setbacks: building sites on state highways and county roads need a 50-foot front setback, with at least 10 feet at the sides and rear. Gates and entrances sit at least 40 feet back from the county right-of-way.
Driveways: private driveways are 10 to 24 feet wide at the right-of-way, with a culvert of at least 15 inches where they cross a ditch. Post the address within 10 feet of the driveway entrance in reflective letters at least 4 inches tall.
Floodplain: any structure in the regulatory floodplain must follow the county’s floodplain regulations, and the septic application asks whether floodplain verification is needed.
Texas building code
Texas has no single statewide building code: state law makes the International Residential Code the base code for homes in cities and the International Building Code the base for commercial buildings, with each city choosing the edition and its own amendments, while the National Electrical Code and the energy code apply statewide. Outside city limits most counties issue no building permits for homes. Texas building code rules
Blanco County permit search and official resources
County, Fire Marshal and city pages:
Want this handled start to finish?
Get a free quote →- Texas TCEQ OSSF Permits
- Blanco County OSSF Application and Checklist
- Blanco County Development Rules
- Blanco County Government
- Blanco County Development Services
- Blanco County Fire Code and applications
- Blanco County iWorQ permit portal
- Johnson City Development Services
- City of Blanco permits
Blanco County permit FAQs
Do I need a building permit to build a house in unincorporated Blanco County?
No county building permit exists for a house. You will still need a septic permit, a 911 address and, on a county road, a driveway permit.
How much is a septic permit in Blanco County?
$300 for a single-family home, or $375 if the system needs a professional design, plus a $40 or $60 filing fee paid to the County Clerk.
Inspections are where schedules slip.
Get a free quote →Who needs a Blanco County Fire Code permit?
New or substantially improved commercial buildings, public buildings and multi-family buildings with 4 or more units outside city limits.
How long does a Fire Code permit take?
The county portal says about 30 days, and the code requires the Fire Marshal to issue or deny a complete application within 30 days.
Who issues permits in Johnson City and Blanco?
Each city issues its own. Johnson City’s Development Services uses Bureau Veritas for plan review and inspections; the City of Blanco issues construction, fire and sign permits through City Hall.
Simplify Blanco County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Texas. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Blanco County sooner?
Let Alliance prepare, file, and track your Blanco County permits while your crew stays on the job.
More Texas permitting guides
This guide is provided by Alliance Permitting for general information about Blanco County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.