Orangeburg, South Carolina Building Permit Guide

Inside Orangeburg city limits, building, trade and sign permits come from the Building Inspection Division of Public Works at 1099 Russell Street, which also reviews plans and issues certificates of occupancy.

Authority: City of Orangeburg Building Inspection DivisionCode: 2021 South Carolina Building CodesPhone: 803-533-6052
Authority
City of Orangeburg Building Inspection DivisionPublic Works Department
Filing
Paper applicationDrop off at 1099 Russell Street
Plan review fee
Half the permit feeFY2026-2027 schedule
Inspections
24-hour noticeCall 803-533-6052

The City of Orangeburg’s Building Inspection Division issues building permits for property inside city limits; you file a paper application, which can be dropped off at City Hall, 1099 Russell Street, at any time. Under the Master Fee Schedule in effect from October 1, 2026, a permit for work valued over $1,000 costs $27 plus $5 per $1,000, plan review adds half the permit fee, and the City asks you to allow 48 hours for action on an application.

What requires a permit in Orangeburg?

The City’s permit application covers four kinds of building work: new construction, renovation or repair, demolition and relocation. The fee schedule and forms add separate permits for trade work and signs.

Building

  • New homes, additions and attached garages, which must be drawn to the current International Residential Code
  • New commercial buildings and alterations
  • Renovations and repairs
  • Decks (the City posts a prescriptive wood deck construction guide)
  • Demolition
  • Moving a house or a mobile home
  • Manufactured home setup

Trades and other

  • Electrical, plumbing, gas and heating and air work (subtrade permits)
  • Temporary power and service upgrades, which also need a Utilities Connection Order
  • Signs, including temporary signs
  • Zoning compliance verification for a new use
  • Work on the exterior of a building in a historic conservation district

Starting construction before the permit is issued doubles the permit fee. An issued permit becomes void if work has not started within 60 days.

Orangeburg building department: who handles permitting

Building Inspection sits within the City’s Public Works Department and also runs code enforcement for building and property maintenance. It reviews residential and commercial plans, approves building permits, inspects construction and issues certificates of occupancy, but only inside Orangeburg city limits; unincorporated land around the city is permitted by Orangeburg County. David Epting is the Building Official and also serves as Zoning Administrator. To meet an inspector in person, call ahead for an appointment.

Short on time to read all of this?

Get a free quote →
Orangeburg permitting contact
DetailInformation
DepartmentCity of Orangeburg Building Inspection Division (Public Works)
Address1099 Russell Street, Orangeburg, SC 29115 (mail: P.O. Drawer 387, Orangeburg, SC 29116-0387)
Phone803-533-6052
HoursMonday to Friday, 8:00 a.m. to 5:00 p.m.
Building OfficialDavid Epting, david.epting@orangeburg.sc.us
Fire Marshal803-533-4105, firemarshal@orangeburgdps.org

Orangeburg permit applications and forms

There is no online permit portal on the City’s site. Applications are paper forms posted on the Building Inspection page and can be left at the office at any time.

  • Application for Building Permit: location, tax map number, owner, contractor with state and City licence numbers, a list of sub-contractors by trade, heated area, stories, room count, type of construction and heat, and the total estimated cost of materials and labor. It also asks whether a recorded covenant on the parcel conflicts with or prohibits the work.
  • Application for Plan Review: the same project details, filed for plan review.
  • Requirements for Owner/Builders: an owner who holds title and plans to do the construction initials each statement and signs with the Building Official. Anyone the owner pays must hold a City business licence, and the owner cannot do electrical, plumbing or heating and air work without the proper licences and permits or a licensed contractor.
  • HVAC Design Form, Application for Sign Permit and Request for Verification of Zoning Compliance ($10 residential, $20 commercial, normally 3–5 business days).

Every contractor and sub-contractor on the application must be licensed by both the City of Orangeburg and the State of South Carolina.

Orangeburg permit cost

Fees are set in the City’s Master Fee Schedule for FY 2026-2027, effective October 1, 2026. The building permit is priced on the value of the work, which the City works out from the latest ICC Building Valuation Data with the South Carolina multiplier rather than from the contract price alone.

Not sure this scope needs a permit?

Get a free quote →
Orangeburg building permit fees (effective October 1, 2026)
ProjectFee
Building permit, value under $500$25
Building permit, $501–$1,000$27
Building permit, $1,001 and up$27 plus $5 per $1,000
Plan reviewHalf of the permit fee
Demolition, under $500No fee
Demolition, $501–$1,000$27
Demolition, over $1,000$27 plus $5 per $1,000
Re-inspection, any type$55 each
Moving a house$50
Moving a mobile home (new, used or de-title)$75
Mobile home setup$85
Temporary sign$30
Appeal of a building codes decision$50

Building, demolition, subtrade and sign permit fees are doubled when construction begins before the permit is obtained. The City’s older Application for Plan Review form still prints a permit fee of $25 for the first $1,000 plus $5 per additional $1,000; the October 2026 schedule is the newer adopted figure, so budget from it.

Orangeburg trade permits

Electrical, plumbing, gas and heating and air work is permitted by Building Inspection as subtrade permits. The building permit application asks for each sub-contractor’s name and licence number, from electrician and plumber to HVAC and roofer.

Orangeburg subtrade permit fees (effective October 1, 2026)
Value of workFee
Less than $1,000$27
More than $1,000$27 plus $5 per $1,000

Residential plans must include Manual J and Manual D calculations; hand-computed Manual J forms are refused. Gas piping is pressure-tested at rough-in: 10 psi for natural gas and 20 psi for LP gas. Fire inspections and fire prevention are handled by the Fire Marshal in the Orangeburg Department of Public Safety.

Rather talk it over?

Call 1-855-478-4290 →

Application documents and plan review

1 and 2 family dwellings

  • Two copies of the site plan and two copies of the building plans, drawn to engineer’s scale (a draftsman or engineer must draw them if you cannot)
  • Site plan dimensioned from each exterior wall to every property line
  • Elevations with roof height and floodplain where it applies
  • Foundation or stem wall plan with rebar, bond beams and hold-downs
  • Floor, wall and roof framing details, braced wall lines and window schedule
  • Electrical and plumbing layouts, which may be shown on the floor plan
  • Manual J and Manual D with duct sizes and room-by-room CFM
  • Energy details: R-values, U-factors and SHGCs, equipment efficiencies and air sealing
  • SC DHEC notification form for sites disturbing less than one acre

Commercial

  • Two paper sets at 24 x 36 inches plus one PDF
  • Cover sheet naming the design professional in charge, with occupancy group, construction type, area, occupant load, sprinkler needs, code edition and special inspections
  • Site plan with utility connection points, parking, drainage and grading; utility locations need Department of Public Utilities approval
  • Landscape and buffer plan
  • Foundation, framing, floor, elevation and wall section drawings
  • Energy, HVAC, plumbing and electrical plans
  • Specifications on the drawings or in a booklet

Commercial plan review is charged at 50% of the permit cost, worked out from the ICC valuation data. During construction, the prime design professional must tell the Building Official about any change that alters the scope or affects code compliance.

Rather not deal with the building department?

Get a free quote →

Orangeburg permit application: how to apply step by step

1. Confirm the parcel is in the city

Only addresses inside Orangeburg city limits are permitted at Russell Street. Ask zoning for a compliance verification if the use is new.

2. Check for a historic district

Exterior work in a historic conservation overlay district needs a certificate of appropriateness before any permit is issued.

3. Assemble plans and forms

Fill in the Application for Building Permit and, for plan review, the Application for Plan Review, with two sets of plans; owner-builders add the signed Owner/Builder form.

4. Drop off the application

Leave it at Building Inspection, 1099 Russell Street, and allow 48 hours for action; call 803-533-6052 if you need to meet an inspector.

5. Pay and request utilities

Pay the permit and plan review fees. Apply to the Department of Public Utilities for service points; Building Inspection then issues the Utilities Connection Order.

6. Start within 60 days and call in inspections

Give 24 hours’ notice for each inspection, through to the final C.O. inspection.

Inspections in Orangeburg

Inspections need 24 hours’ notice; an emergency inspection with less notice is possible when circumstances allow. When you call 803-533-6052, give the address, permit number, inspection type, contractor name and a contact phone number. Post the permit where it can be seen and keep a set of approved plans on site.

The City’s residential inspection sequence is footing (rebar and Ufer ground in place), slab (vapor barrier, termite treatment and any under-slab trade inspections first), piers or CMU walls for crawl spaces, then the rough-ins for framing, electrical, plumbing, gas and mechanical, done together where possible. Insulation is checked against R-19 floors, R-13 walls and R-30 ceilings, followed by temporary power and the final, which the City calls the C.O. inspection. Paint, carpet and vinyl flooring may be unfinished at the final; everything else must be complete. Every re-inspection costs $55.

Local Orangeburg details that matter

Utility connections: the Department of Public Utilities (1016 Russell Street, 803-268-4050) sets the service points for gas, water, sewer and electric. Saw poles, temporary power, permanent power and service upgrades each need a Utilities Connection Order from Building Inspection; the meter can is tagged with a release number after the inspection passes, and permanent power is released only after the final inspection.

Historic conservation districts: applications for a certificate of appropriateness go through the Zoning Administrator to the historic conservation commission, which acts within 30 days. Without one, no permit is issued for building, altering, demolishing or moving a structure in the district.

Want this handled start to finish?

Get a free quote →

Stormwater: for a single-family site under one acre, the residential requirements call for the SC DHEC notification form, which the City posts on the Building Inspection page.

Owner-builders: the owner-builder form makes the owner responsible for business licences of anyone paid on the job and warns about workers’ compensation liability.

South Carolina building code

Every South Carolina county and municipality enforces the 2021 South Carolina Building Codes, in force since 1 January 2023; the 2024 editions take effect statewide on 1 January 2027, and the energy code stays the 2009 International Energy Conservation Code. South Carolina building codes

Orangeburg permit search and official resources

Inspections are where schedules slip.

Get a free quote →

Frequently asked questions

Who issues building permits in Orangeburg?

The City’s Building Inspection Division, part of Public Works, for property inside city limits. Unincorporated land outside the city goes to Orangeburg County.

How much is a building permit in Orangeburg?

From October 1, 2026, $25 for work under $500, $27 for $501–$1,000, and $27 plus $5 per $1,000 above that, valued with ICC data and the South Carolina multiplier. Plan review adds half of the permit fee.

How long does a permit take?

The City asks applicants to allow 48 hours for action on a permit application. Plans that need correction take longer.

Can a homeowner pull a permit in Orangeburg?

Yes, an owner who holds title and does the construction signs the City’s Owner/Builder form. Electrical, plumbing and heating and air work still needs the proper licences and permits or a licensed contractor.

How do I schedule an inspection?

Call Building Inspection at 803-533-6052 at least 24 hours ahead with the address, permit number, inspection type, contractor name and your phone number.

What happens if I start work without a permit?

The permit fee is doubled when construction begins before the permit is obtained.

How much is a re-inspection?

$55 for each re-inspection of any type.

Simplify Orangeburg permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in South Carolina. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Orangeburg sooner?

Let Alliance prepare, file, and track your Orangeburg permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Orangeburg permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.