Aiken County Building Permit — Filed & Tracked For You

Everything contractors, builders, and developers need to pull an Aiken County building permit โ€” the Development Services Online Portal, the two sets of drawings a residential application needs, the manufactured home registration and moving rules, and the three routes to scheduling an inspection.

Authority: Aiken County Planning and DevelopmentCode: 2021 South Carolina Building CodesSubmission: Development Services Online Portal
Authority
Planning & DevelopmentCodes and Planning
Portal
Development ServicesPermits and site plans
Drawings
Two setsWith the application
Inspections
Three routesPortal, phone, or email

The Aiken County Planning and Development Department permits unincorporated Aiken County through its Codes and Planning divisions, with everything filed on the Development Services Online Portal.

This Aiken County building permit guide covers what requires a permit, the two sets of drawings a residential application needs, the three ways to book an inspection, the county flood maps, and the tax rules that gate a manufactured home move.

Scope: unincorporated Aiken County. The City of Aiken runs its own Building Inspection Division.

๐Ÿ“ž

Three ways to book an inspection. The online portal, 803-642-1518, or an email to the Codes division all reach the queue. Keep all three, because portal outages happen and concrete trucks do not reschedule themselves.

What requires a permit in Aiken County?

The Aiken County Planning and Development Department is responsible for issuing building permits for all new construction and renovations in unincorporated Aiken County. It works through two divisions โ€” Codes and Planning โ€” and the split matters when you are trying to reach the right person: permitting and portal questions go one way, inspections the other.

All permits and development approvals are available digitally through the Development Services Online Portal. The portal covers residential and commercial building permits, commercial site development plans and subdivision approvals, and it also publishes the application and submission requirements โ€” so the requirements list and the application live in the same place.

Aiken sits on the Georgia line across from Augusta-Richmond County, and the cross-border question comes up constantly on projects in the corridor. The Savannah River Site also sits partly in the county. Neither Georgia's code adoption nor federal site rules govern an Aiken County permit โ€” South Carolina's adopted codes do, administered by this department.

The enforced code is the South Carolina Building Codes โ€” the International Codes as adopted with South Carolina modifications by the South Carolina Building Codes Council under S.C. Code Ann. ยง 6-9-50, then administered and enforced locally. South Carolina is mid-changeover. The codes in force today are the 2021 South Carolina Building Codes, effective 1 January 2023. On 26 August 2025 the Building Codes Council adopted the next cycle โ€” the 2024 editions of the International Building, Residential, Fire, Plumbing, Mechanical and Fuel Gas Codes, together with the 2023 National Electrical Code โ€” and set the implementation date for every municipality and county as 1 January 2027. Design to the 2021 codes for a permit pulled now; design to the 2024 codes for anything that will be applied for after the turn.

Permit required

  • New construction and renovations, residential and commercial
  • Structural alteration and demolition
  • Electrical, mechanical, and plumbing work
  • Manufactured home registration and set-up
  • Manufactured home moving, within or out of the county
  • Commercial site development plans and subdivisions
  • Change of use or occupancy

Typically exempt

  • Painting, flooring, and cosmetic finishes
  • Routine maintenance not altering structure or a regulated system
  • Work inside the City of Aiken and other municipalities that permit their own
  • Like-for-like replacements not modifying a regulated system
⚠️ Manufactured home moves are gated on tax status. To move a home within Aiken County, all current taxes must be paid and the new owner must hold title in the new name or a form 400. To move one out of Aiken County, the previous year's taxes as well as the current year's must be paid, along with title or form 400 and the destination location. Start the tax check early.

Aiken County building department: who handles permitting

Planning and Development handles both halves of the process, but they answer on different lines. Portal and user account questions go to the department on 803-642-1520. Inspections are scheduled three ways โ€” on the online portal, by calling 803-642-1518, or by emailing the Codes division. Having all three routes matters on a job where the portal is down and the pour is booked.

For a residential building permit the department asks for a completed building permit application submitted with two sets of drawings. Aggregator sites describing a single-set submission are describing something else. The site plan showing the structure's location can be a recorded plat, a scaled drawing on graph paper, or a scaled aerial photo from the county's GeoServices.

The department also publishes and maintains the county flood maps and profiles. Where a parcel is anywhere near mapped floodplain, pull the map before drawing rather than after, because elevation decisions made late are the expensive kind.

Aiken County permitting contact
DetailInformation
AuthorityAiken County Planning and Development Department
DivisionsCodes and Planning
PortalDevelopment Services Online Portal
Portal and accounts803-642-1520
InspectionsPortal, 803-642-1518, or email the Codes division
Residential submittalApplication plus two sets of drawings
Site plan optionsRecorded plat, scaled graph-paper drawing, or scaled aerial from GeoServices
FloodCounty flood maps and profiles published by the department
💻

๐Ÿ“ž|Three ways to book an inspection, and you should know all three. Residential and commercial inspections can be scheduled on the online portal, by calling 803-642-1518, or by emailing the Codes department. Portal outages happen; concrete trucks do not reschedule themselves.

Aiken County permits: record types and what each covers

Aiken County's Development Services portal issues building, development and subdivision records, alongside the manufactured home permits:

Residential permit types

Residential permit types in Aiken County
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures above the local size thresholdFull plan review against the adopted South Carolina Residential Code, plus zoningValuation-based
Renovation / alterationStructural changes, layout changes, or added plumbing, mechanical, or electricalPlan review scaled to scope; the property maintenance and existing-building provisions apply only where locally adopted by ordinanceValuation-based
ReroofRoof covering replacement, recover, and structural deck repairDry-in and deck inspection; plan review rarely requiredValuation or squares
Solar photovoltaicRooftop or ground-mount arrays, with or without battery storageElectrical review led, with structural review of the attachmentFlat or system-size based
Battery energy storageWall or floor-mounted storage added to a dwellingElectrical review plus fire separation and location checkFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, EV chargers, and rewiringTrade review; filed under a mechanical contractor holding the Electrical subclassificationPer-permit minimum or per-device
PlumbingNew piping, repipes, fixtures, gas piping, and water heater replacementTrade review under a mechanical contractor holding PlumbingPer-permit minimum or per-fixture
Mechanical / HVACChangeouts, new ductwork, and refrigerationTrade review under Air Conditioning, Heating, or Refrigeration subclassificationsPer-permit minimum or per-unit
Deck and porchNew decks, screened porches, and structural rebuildsStructural review of footings, ledger attachment, and guardsValuation or flat
Swimming poolIn-ground and above-ground pools, including residential poolsBarrier, bonding, and electrical review; residential pool work now requires a Swimming Pools subclassification or a Residential Builder licenceValuation or flat
Manufactured home set-upPlacing or re-siting a manufactured homeZoning, floodplain, and anchoring review; filed by an LLR-licensed contractorFlat or per-unit
DemolitionFull or partial demolition of a dwelling or accessory structureUtility disconnect confirmation and site restoration checkFlat

Commercial permit types

Commercial permit types in Aiken County
Permit typeWhat triggers itReview pathFee basis
New commercial constructionGround-up commercial, industrial, and institutional buildingsConcurrent review against the adopted South Carolina Building Code, fire, and zoningValuation-based
Tenant improvement / upfitInterior fit-out of an existing tenant spaceBuilding, trade, and life-safety review; accessibility attaches on change of useValuation-based
Change of occupancyConverting a building or space to a different use groupOccupancy classification, egress, and accessibility reviewValuation or flat
Commercial electricalService, distribution, and branch circuit workTrade review under a mechanical contractor holding ElectricalPer-permit or valuation
Commercial plumbingProcess piping, fixtures, backflow, and grease wasteTrade review; backflow and grease interceptor sign-off where applicablePer-fixture or valuation
Commercial mechanicalRooftop units, kitchen exhaust and hood systems, and refrigerationTrade review; kitchen exhaust and hood systems sit under Packaged EquipmentPer-unit or valuation
Commercial reroofRoof covering replacement on a commercial structureDeck, dry-in, and attachment inspectionValuation or squares
SignageWall, ground, and illuminated signsZoning review for size and placement, plus electrical where illuminatedFlat or per-sign
Land disturbanceClearing, grading, and stormwater-triggering site workErosion and sediment control review, separate from the building permitAcreage-based
Commercial demolitionFull or partial demolition of a commercial structureUtility disconnect, asbestos notification, and site restorationFlat or valuation

Residential

  • Single-discipline review in most cases
  • Trade records filed separately under Title 40 Chapter 11 licences regardless of job value
  • Residential builder licence required above the statutory threshold; residential specialty above a much lower one
  • Septic properties need SCDES approval before the county can issue

Commercial — multi-discipline

  • Concurrent review across building, trades, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Licence group caps the value of a single bid or job, separately from the permit
  • Accessibility and life-safety review attach to any change of occupancy

Records you will actually see in Aiken County

Aiken County record catalog
RecordWhat it covers
Residential building permitApplication plus two sets of drawings
Commercial building permitCommercial construction and tenant work
Commercial site development planSite development review through the portal
Subdivision approvalFiled and tracked in the same system
Manufactured home registrationTitle or form 400 plus septic approval
Manufactured home moving permitTax status gates the move
Trade permitsElectrical, mechanical, and plumbing

Solar permits in Aiken County

Solar is reviewed on two tracks at once across South Carolina: the electrical side (conductors, overcurrent protection, rapid shutdown, labelling, and the service or supply-side connection, against the adopted National Electrical Code) and the structural side (attachment detail, rail spacing, and whether the existing framing carries the added dead load).

Aiken County files solar through the Development Services portal with the electrical scope, and inspections can be booked on the portal, by phone, or by email to the Codes division. Confirm which classifications your installer actually holds before the application is filed, because a single rooftop array can cross the general contractor Miscellaneous Metals subclassification for the panels, Roofing or Building for the mounting, and a mechanical contractor holding Electrical for the wiring and connections.

The licensing split is the part that catches installers. South Carolina puts solar panel installation under the general contractor Miscellaneous Metals subclassification, but roof mounting may only be performed by a general contractor holding Roofing or Building, and wiring and connections may only be performed by a mechanical contractor holding Electrical. Structural upgrading of the roof to carry the array goes to a general contractor with Building or Structural Framing. One array, potentially three licences.

Utility interconnection runs on its own clock alongside the permit. Dominion Energy South Carolina, Duke Energy Carolinas and Duke Energy Progress, Santee Cooper and the state's electric cooperatives each set their own application, meter, and witness-test sequence. Permission to operate is not something the building department controls, so plan for the two tracks to finish at different times.

Roofing permits in Aiken County

A roof covering replacement needs a permit across most of South Carolina. The permit is usually quick, but it is not optional, and the inspection that matters happens before the covering goes on rather than after.

Because South Carolina enforces a statewide adopted code, there is no state product-approval database to search and no approval number to cite on the application. The assembly has to comply with the adopted code and the manufacturer's listed installation instructions, and that pairing is what the inspector checks โ€” which makes the manufacturer's instructions a document worth having on site.

A reroof in unincorporated Aiken County is permitted through the Development Services portal. Note that inside the City of Aiken a roofing contractor needs a current city business licence as well as the state licence, and historic or overlay districts may require planning approval. Roofing is its own general contractor subclassification in South Carolina, and it absorbed the former General Roofing and Specialty Roofing classifications, so an older pocket card can read differently from the current licence record โ€” check the LLR verification lookup rather than the card alone.

Sequencing is where reroofs go wrong. The deck and dry-in condition has to be visible when the inspector arrives, so covering it first means opening it back up. Where a previous layer has been torn off, expect attention to deck fastening and to any sheathing replaced along the eaves.

Record types, document sets, and fee structures are set by local ordinance and change without notice. Confirm the current catalog against the official portal before you file.

Aiken County permit cost

Aiken County permit fees follow the county's published schedule and scale with the type and valuation of the work, with trade permits charged separately and fees payable before the permit is issued. Manufactured home development permits carry their own smaller fee.

Card payments attract a transaction fee, so on a large commercial permit the payment method is worth a moment's thought. Confirm current amounts and accepted methods against the county schedule before budgeting.

How Aiken County fees are structured
Fee componentHow it works
Building permitPer county fee schedule, by type and valuation
Trade permitsElectrical, mechanical, plumbing charged separately
Manufactured home developmentIts own permit and fee
When payableBefore the permit is issued
Card paymentsA transaction fee applies to card payment
Septic propertiesSCDES approval required before the county can issue
🧮

Want a precise number for a specific Aiken County project? Send us the scope and we will price the permit path before you file.

Aiken County trade permits

Electrical, mechanical and plumbing work each need their own permit and a South Carolina licensed contractor. Four Aiken County practicalities:

Bring two sets of drawings

A residential building permit application is submitted with two sets of drawings. Turning up with one is a return trip.

Book inspections whichever way works

The portal, 803-642-1518, or an email to the Codes division all reach the inspection queue. Use whichever is up.

Site plan can be simple, but must be scaled

A recorded plat, a scaled drawing on graph paper, or a scaled aerial photograph from Aiken County GeoServices are all acceptable ways of showing the structure's location.

Check the flood map first

The department publishes county flood maps and profiles. Elevation and foundation decisions made before design are far cheaper than the same decisions made at plan review.

🧢 South Carolina licenses through two separate boards, both inside the Department of Labor, Licensing and Regulation. The Contractor's Licensing Board covers general and mechanical construction under Title 40, Chapter 11: a licence is required once the total cost of construction is greater than $10,000 (S.C. Code Ann. ยง 40-11-30). That figure rose from $5,000 under H.4115 in 2023 โ€” guides still quoting $5,000 for commercial or mechanical work are three years out of date. The Residential Builders Commission covers residential builders, residential specialty contractors and home inspectors under Title 40, Chapter 59, and its thresholds did not change: $5,000 for residential building and $500 for residential specialty work. The licence must exist before the bid, not before the work. An awarding authority, owner, contractor or agent may not consider a bid, sign a contract, or let work begin unless the contractor already holds the required licence โ€” and a bid submitted without one may not be reconsidered even if the contractor is licensed later. A South Carolina commercial licence is not open-ended. Each licensee sits in one of five groups, and the group caps the value of a single bid or job. Group placement is set by working capital or net worth, or by a surety bond in the same amount. A Group 2 general contractor cannot take a $500,000 job, and the bid limits differ sharply between the general and mechanical tracks โ€” an unlimited mechanical contractor and an unlimited general contractor are not the same credential.

Aiken County permit application: how to apply step by step

Here is how to get a building permit in Aiken County, from confirming the requirement through to close-out. Each step below corresponds to a real decision point where projects commonly stall.

1. Confirm the parcel is unincorporated

The City of Aiken and the county's other municipalities permit their own work. Aiken County Planning and Development covers the unincorporated county.

2. Check the flood maps

Pull the county flood maps and profiles published by the department before design is fixed, particularly on parcels near mapped floodplain.

3. Prepare the application and two drawing sets

A completed building permit application plus two sets of drawings, with a site plan showing the structure's location as a recorded plat, a scaled graph-paper drawing, or a scaled GeoServices aerial.

4. Apply through the Development Services portal

Residential and commercial building permits, commercial site development plans and subdivision approvals all run through the portal, which also publishes the submission requirements.

5. Pay before issuance

Fees are payable before the permit is issued. Card payments attract a transaction fee, so choose the payment method deliberately on larger permits.

6. Schedule inspections through to final

Book on the portal, by phone on 803-642-1518, or by emailing the Codes division, and keep the permit and approved plans on site to Certificate of Occupancy.

Inspections in Aiken County

Residential and commercial inspections in unincorporated Aiken County are scheduled through the Codes division, and the department deliberately keeps three routes open โ€” the online portal, the phone line on 803-642-1518, and email. Typical checkpoints follow the adopted code: footing and foundation, trade rough-ins, framing, insulation, and final.

Manufactured homes carry their own document trail. To register a manufactured home the county needs a copy of the state title in your name or a form 400, together with septic approval. Check the agency name on any older handout. Septic approval now comes from the SC Department of Environmental Services (SCDES); the combined health and environment agency that previously issued these approvals was dissolved on 1 July 2024 and its onsite wastewater programme moved to SCDES.

Moving a manufactured home is gated on tax status rather than on construction. Within the county, all current taxes must be paid and the new owner must have title in the new name or a form 400. Moving out of the county requires the previous year's taxes as well as the current year's, plus the destination.

Keep the permit and approved plans on site throughout, and read any older environmental reference on a county form as SCDES for anything issued since July 2024.

Aiken County permit search and official resources

Aiken County publishes its permitting, flood mapping and manufactured home guidance through Planning and Development, with the City of Aiken publishing separately for city parcels.

Frequently asked questions

Who issues building permits in Aiken County, SC?

The Aiken County Planning and Development Department, through its Codes and Planning divisions, for unincorporated Aiken County. The City of Aiken runs its own Building Inspection Division.

How do I apply for an Aiken County building permit?

Through the Development Services Online Portal, which handles residential and commercial building permits, commercial site development plans and subdivision approvals, and publishes the application and submission requirements.

How many sets of drawings does Aiken County need?

Two. A residential building permit is obtained by completing the building permit application and submitting it with two sets of drawings.

How do I schedule an inspection in Aiken County?

Three ways: on the online portal, by calling 803-642-1518, or by emailing the Codes department. Having all three is useful when the portal is unavailable.

What can I use as a site plan?

A recorded plat, a scaled drawing on graph paper, or a scaled aerial photograph from Aiken County GeoServices. It needs to show where the structure sits on the parcel.

What do I need to register a manufactured home?

A copy of the state title in your name or a form 400, together with septic approval. Septic approval comes from the SC Department of Environmental Services. Older county handouts may still name the predecessor agency, which was dissolved on 1 July 2024 when its onsite wastewater programme moved to SCDES.

How do I move a manufactured home within Aiken County?

All current taxes must be paid, and the new owner must have title in the new name or a form 400.

What if I am moving a manufactured home out of Aiken County?

The previous year's taxes as well as the current year's must be paid, the new owner must have title in the new name or a form 400, and the destination location is required.

Where do I get Aiken County flood maps?

The Planning and Development Department publishes county flood maps and profiles for viewing and download. Check them before design is fixed rather than at plan review.

When are permit fees payable?

Before the permit is issued. Card payments attract a transaction fee, which is worth factoring in on a large commercial permit.

Does Georgia's building code apply near the Augusta line?

No. An Aiken County permit is governed by South Carolina's adopted codes as administered by Aiken County Planning and Development, regardless of how close the parcel sits to the Georgia line.

Which building code does Aiken County enforce?

The South Carolina Building Codes โ€” the I-Codes as adopted with South Carolina modifications. The 2021 editions apply now, with the 2024 editions adopted in August 2025 and implementation set for 1 January 2027.

Simplify Aiken County permitting with Alliance Permitting

Aiken's requirements are not complicated, but they are specific โ€” two drawing sets, a scaled site plan, tax clearance on manufactured homes, and a flood map worth reading early.

250K+Permits approved
All 50States covered
21 YearsJurisdictional depth
Done-for-youWe file, you build

Trusted by leading builders, developers, and national contractors — 21 years of filing in the jurisdictions we write about.

Contractors and builders choose Alliance for Aiken County because the work is done by people who have stood at the counter:

  • Right authority โ€” unincorporated county or the City of Aiken, resolved from the parcel rather than the postal address.
  • Complete first submission โ€” application, two drawing sets and a properly scaled site plan.
  • Flood checked early โ€” county flood maps and profiles read before design is fixed.
  • Complete oversight โ€” every Aiken permit and inspection tracked across your jobs in one place.

Alliance Permitting is a permit documentation and expediting service in South Carolina. We are not a law firm and do not provide legal advice, and we are not the permitting authority.

Ready to break ground in Aiken County sooner?

Let Alliance prepare, file, and track your Aiken County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Aiken County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.