Hardeeville, South Carolina Building Permit Guide

Hardeeville’s Building Safety Department takes every building permit application, document upload and inspection request through the City’s online Permit & License Portal.

Authority: City of Hardeeville Building Safety DepartmentCode: 2021 South Carolina Building CodesPhone: 843-784-2231
Authority
City of Hardeeville Building Safety DepartmentLocal building authority
Portal
Permit & License PortalPublished filing path
Business license
Required for every contractorAny work on a structure in the city
Inspections
Requested in the portalCancel by 3:00 p.m.

Inside Hardeeville city limits, the City’s Building Safety Department (843-784-2231) issues building and trade permits, and every application goes through the online Permit & License Portal. Under the City’s fee schedule a permit starts at $69 for work valued up to $2,000, and plan review, when the Building Official requires it, adds half the permit fee.

What requires a permit in Hardeeville?

The City publishes its own list of work that does and does not need a permit. Even where no permit is needed, any contractor working on a structure in the city must hold a current City business license.

Permit required

  • New roofing, replacement windows and new siding or trim
  • New interior walls, new openings, porches, lanais, gazebos and screened enclosures
  • Any structural work, including load-bearing walls
  • Replacing sewer or water lines or water heaters, and adding plumbing to a room
  • Wiring, outlets, breakers, solar panels, generators, hot tub disconnects and whole-house surge protectors
  • New or replacement heating and air units, ductwork and mini-splits
  • Gas lines for anything other than portable appliances
  • Pools over 24 in deep or 3,500 gallons, or with permanent equipment
  • Sheds, garages, carports and decks over 200 sq ft or attached to the house, and fences over 7 ft

No permit

  • Painting, wallpaper, tile, flooring and carpet
  • Cabinets, countertops, plumbing fixtures and appliances
  • Rotted wood and other routine maintenance on a single-family home
  • Gutters, swings and play equipment
  • With zoning approval only: detached accessory buildings under 200 sq ft, fences up to 7 ft, retaining walls up to 4 ft, and sidewalks, driveways and patio slabs

Short on time to read all of this?

Get a free quote →

Who issues building permits in Hardeeville?

The City of Hardeeville Building Safety Department reviews applications, issues permits and inspects work inside city limits. Hardeeville lies mostly in Jasper County with a part in Beaufort County; property outside the city is permitted by the county it sits in.

Hardeeville permitting contacts
DetailInformation
DepartmentCity of Hardeeville Building Safety Department
Office3345 Argent Blvd, Unit 102, Ridgeland, SC 29936
Phone843-784-2231
Emailpermits@hardeevillesc.gov (business licenses: businesslicensing@hardeevillesc.gov)
PortalPermit & License Portal (CitizenServe)
City Hall205 Main Street, Hardeeville, SC 29927 (PO Box 609)

Applying through the Permit & License Portal

The portal handles new building permits, existing permit records, inspection requests, document uploads and business license applications and renewals. Forms the City lists for portal submittals include:

  • Homeowner Builder Disclosure Form, for owners building under the state owner-builder exemption.
  • Homeowner’s Consent Affidavit, which names the owner’s agent, lets City staff enter the property for review, and acknowledges the City’s flood zone construction rules.
  • B-3 Sub Contractor Roster.
  • Revision Form, emailed to permits@hardeevillesc.gov to change an application already submitted.
  • Special Inspections (IBC chapter 17) and High Piled Storage (IFC chapter 32) requirements for commercial projects.

Land work has its own planning forms: Form C for clearing, Form D for development, Form SF for site features, Form Z for zoning and Form E for signs.

Hardeeville permit fees

Appendix B of the City code, last amended in June 2024, sets building permit fees on total valuation, and the City’s FAQ says valuations follow the ICC Building Valuation Data for residential and commercial permits.

Not sure this scope needs a permit?

Get a free quote →
Hardeeville building permit fees
ValuationFee
Up to $2,000$69
$2,001–$40,000$69 for the first $2,000, plus $11 per extra $1,000
$40,001–$100,000$487 for the first $40,000, plus $9 per extra $1,000
$100,001–$500,000$1,027 for the first $100,000, plus $7 per extra $1,000
$500,001–$1,000,000$3,827 for the first $500,000, plus $5 per extra $1,000
$1,000,001–$5,000,000$6,327 for the first $1,000,000, plus $3 per extra $1,000
Over $5,000,000$18,327 for the first $5,000,000, plus $1 per extra $1,000

For a $300,000 valuation the permit fee is $1,027 plus 200 × $7, or $2,427. If the Building Official requires plan review, half that ($1,213.50) is paid when the plans are submitted. Online payments carry a 3% convenience fee.

Other Hardeeville building fees
ItemFee
Change of occupancy classification$100
Manufactured home$200
Moving a structure$150
Demolition$100
Plan revision$100 per page for up to 3 pages, then $20 per page
Re-stamping plans$50
Construction trailer$100
Weekend or after-hours inspection$240, plus $80 an hour over 3 hours
Flood zone determination letter$50
Temporary Certificate of Occupancy$200 up to 20,000 sq ft, plus $0.01 per sq ft above, up to $2,000

Rather talk it over?

Call 1-855-478-4290 →

Refunds are limited: 75% of the plan review fee before review starts, 50% of the permit fee if no work has started, and nothing on a permit that has expired after 180 days or where work has begun.

Electrical, plumbing, mechanical and gas permits

Building Safety also issues the trade permits. The fee schedule prices electrical work above 200 amps, gas, mechanical and plumbing work, and change-outs of electrical services, residential HVAC units and water heaters, on the job valuation using the same table as building permits.

Fire protection work on commercial and multi-family buildings has its own inspection fees in the schedule, for example $150 plus $1.50 per head for a new 13 or 13R sprinkler system, $75 plus $1.50 per head for a 13D system in a detached house, and $150 plus $1.50 per device for a new fire alarm system.

How to apply in Hardeeville

1. Check the list and the city limits

Use the City’s permit list to see whether the job needs a building permit, zoning approval or neither, and confirm the parcel is inside Hardeeville.

2. Get a City business license

Every contractor on the job needs one; apply or renew in the same portal.

3. Check the flood zone

If any part of the lot is in a Special Flood Hazard Area, plan for elevation certificates at the drawing, construction and finished stages.

4. Apply in the portal

Create an account, complete the permit application and upload plans, the subcontractor roster and any affidavits.

5. Pay and answer comments

Pay the plan review fee at submittal and the permit fee at issue; send changes with the Revision Form.

6. Request inspections online

Book each inspection in the portal; results are emailed to the site contact.

Rather not deal with the building department?

Get a free quote →

Inspections in Hardeeville

All inspection requests are made in the portal. To move an inspection, cancel the scheduled request before 3:00 p.m. and book a new date. Results are emailed to the site contact on the permit and appear in the portal as soon as the inspector enters them.

Re-inspections cost $75 the first time, $150 the second and $300 the third, and each later re-inspection doubles. Weekend or after-hours inspections cost $240 plus $80 an hour beyond 3 hours.

Flood zone rules in Hardeeville

The City’s elevation certificate chart sets when one is needed. If the lot or the structure is in a Special Flood Hazard Area, certificates are required with the construction drawings, while the building is under construction and when it is finished. If the flood zone only crosses the building setback, certificates are needed at the drawing and finished stages. The City can require an elevation certificate on any project.

The Homeowner’s Consent Affidavit restates the City’s flood rules: enclosed space below base flood elevation may be used only for parking, limited storage or access, must be built of flood-resistant materials and must have flood openings on at least two walls, and all mechanical, electrical and plumbing equipment must sit above base flood elevation.

South Carolina building code

Every South Carolina county and municipality enforces the 2021 South Carolina Building Codes, in force since 1 January 2023; the 2024 editions take effect statewide on 1 January 2027, and the energy code stays the 2009 International Energy Conservation Code. South Carolina building codes

Want this handled start to finish?

Get a free quote →

Hardeeville permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Hardeeville permit FAQs

Who issues building permits in Hardeeville?

The City of Hardeeville Building Safety Department (843-784-2231, permits@hardeevillesc.gov), for property inside city limits.

Inspections are where schedules slip.

Get a free quote →

How much is a building permit in Hardeeville?

$69 for work valued up to $2,000, then a sliding scale; a $300,000 project pays $2,427, plus $1,213.50 if plan review is required.

Do I need a permit to replace my roof or windows?

Yes. New roofing, replacement windows and new siding all need a permit in Hardeeville.

Do I need a permit for a shed or fence?

A detached shed under 200 sq ft or a fence up to 7 ft needs zoning approval but no building permit. Larger or attached structures, and fences over 7 ft, need a permit.

How do I schedule or cancel an inspection?

In the Permit & License Portal. Cancellations must be made by 3:00 p.m.; to reschedule, cancel and request a new date.

What does a failed inspection cost?

$75 for the first re-inspection, $150 for the second and $300 for the third, doubling after that.

Simplify Hardeeville permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in South Carolina. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Hardeeville sooner?

Let Alliance prepare, file, and track your Hardeeville permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Hardeeville permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.