Tillamook County, Oregon Building Permit Guide

To get a building permit in Tillamook County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Tillamook County’s Department of Community Development issues building and trade permits for rural land and six of the county’s seven cities; applications go in by appointment or by mail, not through ePermitting.

Authority: Tillamook County Community Development, Building DivisionCode: 2026 ORSC, 2025 OSSCPhone: 503-842-3407
Authority
DCD Building Division1510-B Third Street, Tillamook
Hours
Mon–Thu, 8 a.m.–4 p.m.Four-day, 10-hour staff week
Filing
In person or by mailAppointment required; no emailed submittals
Inspections
503-842-1815Call before 7 a.m. the same day

The Tillamook County Department of Community Development issues structural, plumbing, mechanical and electrical permits for the unincorporated county and for Bay City, Garibaldi, Nehalem, Rockaway Beach, Tillamook and Wheeler; Manzanita issues its own building permits but buys electrical permits from the county. Plans go in on paper, by appointment or by mail. Under the fee schedule in force since July 15, 2023, $150,000 of work carries a $1,200.02 permit fee before plan review, the 5 percent technology fee and the state surcharge.

What requires a building permit in Tillamook County?

The county’s consolidated building and zoning application covers new houses and replacements, additions, accessory buildings such as garages and sheds, alterations, demolition and “other” work it names as decks, pools, retaining walls, solar and driveways; each type of work needs its own permit. The 2023 fee schedule adds manufactured home placement, residential fire sprinkler systems and a separate review charge for work in geologic, dune or flood hazard areas.

Permit required

  • New or replacement houses and additions that add square footage
  • Accessory buildings beyond the state exemption, and alterations with no change in floor area
  • Retaining walls, decks and fences where the state code calls for a structural permit
  • Manufactured home placement, from $328 for a single-wide
  • Residential fire sprinkler systems, priced by the area covered
  • Electrical, plumbing and mechanical work, each on its own application

No building permit (2026 ORSC)

  • A one-story nonhabitable accessory building of 200 sq ft or less and no more than 15 ft tall from grade plane; 400 sq ft on 2 acres or more
  • Decks and porches no more than 30 inches above grade
  • Nonhabitable membrane-covered frame structures up to 500 sq ft, one story, 3 ft or more from a lot line
  • Reroofing adding 4 psf or less of dead load, unless the house is a townhouse, the roof is a solar covering or local wildfire rules applied
  • Siding replacement that needs no fire rating, gutters, retrofitted insulation and masonry repair

Those exemptions are the 2026 Oregon Residential Specialty Code’s, in force since October 1, 2026; the county’s Building page still links the 2023 edition. Its section R101.2.2 adds fixed docks with no superstructure and in-ground pools at houses, which need no building permit unless a local ordinance requires one; a pool-barrier fence always does. In this county the zoning check matters as much as the building code: an exempt shed still needs a zoning approval, and building in a mapped special flood hazard area needs a floodplain development permit after a required pre-application meeting.

What the county decides and what the state holds

The Board of Commissioners sets the fees by board order and the department sets its own procedures: appointments for submittals, paper plans, a five-day pickup window for issued permits and a 5 percent technology fee. The department also says the county has chosen to enforce stricter flood construction standards than the federal minimum to earn Community Rating System discounts on flood insurance. The building codes, licensing and the valuation table come from the state.

Short on time to read all of this?

Get a free quote →

Tillamook County building department: who handles permitting

One county office covers almost the whole county. The state’s Local Building Department Directory lists Tillamook County for “all building permits” in six cities and in the unincorporated communities, including Beaver, Cloverdale, Hebo, Neskowin, Netarts, Oceanside and Pacific City. Manzanita is the exception.

Who issues permits in each city
CityBuilding, plumbing, mechanicalElectricalZoning approval
TillamookTillamook CountyTillamook CountyCity of Tillamook (city limits and UGB)
Bay CityTillamook CountyTillamook CountyCity of Bay City (city limits and UGB)
GaribaldiTillamook CountyTillamook CountyCity of Garibaldi (city limits and UGB)
Rockaway BeachTillamook CountyTillamook CountyCity of Rockaway Beach (city limits and UGB)
WheelerTillamook CountyTillamook CountyCity of Wheeler (city limits and UGB)
NehalemTillamook CountyTillamook CountyCity of Nehalem (city limits)
ManzanitaCity of Manzanita, 543 Laneda Ave., 503-368-5343Tillamook CountyCity of Manzanita (inside its UGB)
Unincorporated countyTillamook CountyTillamook CountyTillamook County Planning

The zoning column follows the county’s own rule: a copy of the city’s approved zoning permit must come with the building application for land inside those city limits or growth boundaries.

Department of Community Development
ItemDetails
Address1510-B Third Street, Tillamook, OR 97141, inside the TLC Fibre Credit Union building
PhonesBuilding 503-842-3407; main office and planning 503-842-3408; on-site sanitation 503-842-3409; inspection hotline 503-842-1815
HoursMonday to Thursday, 8 a.m. to 4 p.m.; staff work a four-day, 10-hour week
Director and Building OfficialSarah Absher

Permit types and approvals before filing

Not sure this scope needs a permit?

Get a free quote →

Residential permits

Houses start on the consolidated building and zoning application, which records the zone and setbacks, the road access, the water supply and whether waste goes to a sewer district or a septic tank, with the valuation and the wind exposure category. The trade work needs its own electrical, plumbing and mechanical applications, and the forms page adds the residential energy code form, the moisture content acknowledgement and the county design criteria. Those criteria set seismic design category D2, a 120 mph special wind region, a minimum ground snow load of 36 psf for prescriptive design (25 psf engineered) and footings at least 12 inches below finished grade, and they require a design professional for any lateral bracing that does not follow the prescriptive path.

Commercial permits

Commercial work adds a fire and life safety review at 50 percent of the structural permit fee, a 1 percent seismic review for essential structures, and fees for deferred submittals (65 percent of the fee on the deferred part, at least $100) and phased projects ($326 plus 10 percent of the total permit fee, up to $1,500 a phase). Commercial fire sprinkler systems are priced on the valuation table. A temporary certificate of occupancy for a commercial building is $450.

What comes before the building permit

  • Zoning: outside the cities’ areas the county Planning Division gives the zoning approval on the same consolidated form; inside them, the city’s approved zoning permit is attached.
  • Floodplain: a pre-application meeting is required before a floodplain development permit application, and the fee schedule charges $300 for geologic hazard, dune or flood hazard review.
  • Septic: the department’s onsite wastewater program, DEQ’s contract agent for the county, issues site evaluations and system permits; it does not take septic applications through ePermitting.
  • Wetlands: the application warns that a site in a jurisdictional wetland needs any state or federal permits before work starts.
  • School excise tax: collected at submittal by check to the district: $1.45 per sq ft for a house in the Tillamook School District, $1.63 in Nestucca Valley and $1 in Neah-Kah-Nie, with lower rates for nonresidential space.

Building permit fees

Building Division fees were raised by Board Order 23-030, adopted June 7, 2023 and effective July 15, 2023; the order notes the schedule had not been revised since orders of 2011 and 2013. The Building Forms page still posts that 2023 Fee Schedule. Structural fees use the ICC valuation table in force on April 1 each year.

Rather talk it over?

Call 1-855-478-4290 →
Tillamook County structural permit fees (effective July 15, 2023)
Valuation or itemFee
$1 to $2,000$86.50
$2,001 to $25,000$86.50 for the first $2,000, plus $12.49 per additional $1,000 or fraction
$25,001 to $50,000$373.77 for the first $25,000, plus $9.57 per additional $1,000 or fraction
$50,001 to $300,000$613.02 for the first $50,000, plus $5.87 per additional $1,000 or fraction
$300,001 and up$2,080.52 plus $7.00 per additional $1,000 or fraction (the schedule prints “for the first $100,000”; $2,080.52 is the fee at $300,000)
Structural plan review65% of the permit fee
Fire and life safety review50% of the permit fee
Additional plan review$100 an hour, one-hour minimum
Re-inspection$100
Residential fire sprinkler, standalone (includes review)$195 to 2,000 sq ft; $247.50, $320 or $400 above
Prescriptive solar (includes review)$230
New house electrical$192.50 for the first 1,000 sq ft, $37.50 per additional 500 sq ft
Complete demolition$100, not subject to the state surcharge
Temporary certificate of occupancy, residential$275

State surcharge, in the county’s words: the schedule prints no rate; it marks fees that “incur State Surcharge,” such as structural alterations and reinstatements, and those “not subject to State Surcharge,” such as demolitions, extensions ($50) and the refund processing fee ($50), and the application carries a separate “State Surcharge” line. The county’s own “Tech Fee” is “5% of all fees, besides surcharges.”

Worked example: $150,000 of work is in the $50,001 to $300,000 band: $613.02 plus 100 × $5.87 = $1,200.02. Plan review adds $780.01 and the technology fee 5 percent of both, $99.00, for $2,079.03 before the state surcharge and any school excise tax.

Trade permits and who may pull them

Electrical work anywhere in the county, Manzanita included, is permitted by the county; Tillamook People’s Utility District also requires a county electrical permit before it connects a new service. Plumbing and mechanical permits come from the county everywhere except Manzanita. Electrical inspections are limited: the inspection page books north county electrical stops on Monday, Wednesday and Friday and south county ones on Tuesday and Thursday.

Rather not deal with the Tillamook County building department?

Get a free quote →
  • Licensed work: a contractor paid for the job needs a Construction Contractors Board license, and the application asks for the CCB number, or the installer number for a manufactured home. Electricians and plumbers working for hire also need Building Codes Division licenses.
  • Owners wiring their own property: ORS 479.540 lets an owner do electrical work without a license on residential or farm property owned by them or an immediate family member, if it is not intended for sale, exchange, lease or rent; the permit is still required.
  • Owners doing their own plumbing: unpaid plumbing work is outside the plumbing licensing law (ORS 447.060), but it is not outside the permit and inspection.
  • Owner-builders: ORS 701.325 has an owner who is exempt from CCB licensing state the reason for the exemption when applying.

How to apply

1. Check the zoning authority

Inside Tillamook, Bay City, Garibaldi, Rockaway Beach, Wheeler or Nehalem, or Manzanita’s growth boundary, get the city’s zoning permit first.

2. Book a submittal appointment

Use the department’s online booking calendar and choose the zoning, building and sanitation submittal slot.

3. Assemble a complete package

The consolidated application, plans drawn to the county design criteria, energy and moisture forms, trade applications and the school excise tax check.

4. Deliver it

In person at the appointment or by mail to 1510-B Third Street; the green and red bins by the office door take drop-offs.

5. Collect the permit

Pick up the issued permit packet within five business days or it is mailed.

6. Keep it active

Pass a first inspection within 180 days; each approved inspection adds another 180.

Review, corrections and what causes delay

The department turns away incomplete applications rather than holding them, and it does not take emailed or digital structural submittals unless staff agree in advance. Changes after approval go through the addendum form at $100 an hour. A permit close to expiring can be extended only by a written request with a justifiable reason, which the building official approves or denies; the extension fee is $50.

Inspections

Call the inspection hotline, 503-842-1815, before 7 a.m. on the day you want the visit, and choose 1 for structural or manufactured dwelling, 2 for mechanical, 3 for plumbing or 4 for electrical. Structural and related trade inspections can also be booked on Oregon ePermitting or its phone app. The daily routes are posted by 9 a.m.; the order is up to the inspector and no arrival times are given, and in summer inspections can run until 6 p.m.

Results, with any correction notes, appear on ePermitting under the permit’s inspection record. A re-inspection, or any inspection beyond the number allowed, costs $100, and inspections outside business hours are $150 an hour with a two-hour minimum.

Want this handled start to finish?

Get a free quote →

Code editions and flood maps

The state codes in force are the 2025 Oregon Structural Specialty Code and the 2026 residential, electrical and plumbing codes; the residential construction chapters may follow the 2023 edition until April 1, 2027, which is also the edition the county design criteria cite. The unincorporated county and all seven cities take part in the National Flood Insurance Program, each carried as a participant in FEMA’s Community Status Book. The county runs tsunami hazard overlay zones for Barview, Twin Rocks and Watseco, Cape Meares, Oceanside, Neskowin, Pacific City and Woods, and Tierra del Mar.

Oregon’s building code and its exemptions are the same in Tillamook County as everywhere in the state, and an exemption from the building permit is not an exemption from zoning, land use or a trade permit. Site snow, wind and seismic values come from the state’s Oregon Design Criteria Hub. How Oregon’s statewide code works

Tillamook County building permit FAQ

Can I apply on Oregon ePermitting?

Not for structural plans: the county says it lacks the setup for online structural submittals, so applications go in person by appointment or by mail.

What does a permit cost?

$1,200.02 on $150,000 of work, plus 65 percent plan review, the 5 percent technology fee and the state surcharge.

Does the City of Tillamook issue building permits?

No. The county does, after the city approves the zoning.

Who permits work in Manzanita?

The City of Manzanita issues building, plumbing and mechanical permits; electrical permits come from the county.

Is the office open on Fridays?

No. The department is open Monday to Thursday, 8 a.m. to 4 p.m.

What school tax will I pay on a new house?

$1.45, $1.63 or $1 per sq ft, depending on the school district, by check to the district at submittal.

Who issues septic permits?

The department’s onsite wastewater program, as DEQ’s agent; call 503-842-3409.

Permit search and official resources

County permits carry numbers beginning 851 and can be looked up on Oregon ePermitting under the Building tab, where inspection results are also posted. For older property files and public record copies, ask the department and allow five business days; research and copy fees apply. Land use applications under review are listed on the Planning pages.

Inspections are where schedules slip.

Get a free quote →

Simplify Tillamook County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oregon. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Tillamook County sooner?

Let Alliance prepare, file, and track your Tillamook County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Tillamook County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.