Woodward County, Oklahoma Building Permit Guide

Woodward County issues no building permits; its commissioners permit driveway entrances and pipeline or utility crossings on county roads, its Floodplain Board approves floodplain permits, and Woodward, Mooreland and Fort Supply permit construction in town.

Authority: Woodward County Commissioners (road permits) and Floodplain BoardCounty building permits: None (state list)Phone: 580-254-3686
2025 population
19,827
County building permit
Not issued
Home driveway entrance
No permit fee; culvert required
Bored road crossing
$1,000 per line (30 days)

Woodward County does not issue building permits. On rural land the county’s permits are for work that touches county roads and floodplains: the Board of County Commissioners (1600 Main Street, Suite 8, Woodward; 580-254-3686) approves driveway entrances and pipeline or utility crossings, and the county Floodplain Board approves permits for work in mapped floodplains, administered by the Emergency Management director. A driveway entrance for a home or farm has no permit fee, but it must have a drainage culvert. The City of Woodward and the towns of Mooreland and Fort Supply require building permits inside their limits.

What needs a county permit in Woodward County?

Needed outside town limits

  • Floodplain permit for building, excavating, mining, grading, drilling or storing equipment and supplies in a county floodplain
  • Driveway entrance permit for any new access onto a county road
  • Pipeline, utility or public service crossing permit for lines on or across county right-of-way
  • 911 address from Woodward County 911
  • Septic permit from the Oklahoma Department of Environmental Quality (DEQ)

Not issued by the county

  • Building permits or inspections of houses and other buildings
  • Trade permits for wiring, plumbing or heating and cooling
  • Any permit inside Woodward, Mooreland or Fort Supply

Where no local building permit exists, a state rule applies instead. The State Fire Marshal quotes OAC 265:25-1-4(a) as: “In all geographical areas wherein no building permit is required by local authorities such permit shall be obtained from the State Fire Marshal’s Office for all Use and Occupancy Classifications identified in the International Building Code.”

Short on time to read all of this?

Get a free quote →

Who handles permitting in Woodward County?

Woodward County permit contacts
OfficeContact
Board of County Commissioners (driveway and crossing permits)Courthouse, 1600 Main Street, Suite 8, Woodward, OK 73801; 580-254-3686
Emergency Management director, county Floodplain Administrator580-334-5817 (Oklahoma Water Resources Board listing)
Woodward County 911 (addresses)1222 9th Street, Woodward; online address request form

The county has five incorporated places. Two state lists help show which of them permit construction: the State Fire Marshal’s July 14, 2026 list of local plan review authorities, and the building code commission’s jurisdiction list (updated April 17, 2026), which flags places that issue no permits.

Building permits in Woodward County towns
TownWho issues building permits
Woodward (city)City of Woodward Code Enforcement Office, City Hall, 722 Main Street, 580-254-8515. On the State Fire Marshal’s list since June 24, 2025.
Mooreland (town)Town building official. Mooreland’s code (section 10-2-2) requires a permit to build, enlarge, alter or move a building or to place a mobile home, with fees set by Board of Trustees resolution and doubled if work starts first. On the State Fire Marshal’s list since July 22, 2025; 212 S. Main, 580-994-5924.
Fort Supply (town)Town clerk. The town code (September 2025, section 5-105) requires a permit from the town clerk to build, alter or move a building, with the fee set by the Board of Trustees, plus a land use permit with a plot plan drawn to scale; the code still cites the 2009 International Residential, Building and Existing Building Codes. Plumbing, electrical and mechanical work needs town permits, issued to registered or licensed contractors or to an owner-occupant doing the work on their own single-family home, and swimming pools need a permit from the town clerk. The town is not on the State Fire Marshal’s list; town phone on the state commission’s list: 580-766-3211.
Mutual, Sharon (towns)Marked “Does not issue permits” on the state commission’s list; Sharon 580-273-3399.

Not sure this scope needs a permit?

Get a free quote →

Driveway entrances on county roads

The commissioners revised the driveway entrance application in May 2026. Every point of entry onto county right-of-way must have a drainage culvert, and the County Commissioner for the district decides the type and size of culvert case by case.

  • Homes and farms: no entrance permit fee; the owner supplies the culvert and materials.
  • Commercial entrances: $2,000 per entrance, with all materials and labor provided by the business.
  • With the application: a map showing where the drive will be and a drawing of vehicle use, drive dimensions, surface material and drainage.
  • Before building: call the commissioner at least 5 days before construction starts (580-254-3686). Next to a paved or chip seal road, the commissioner may require screenings.
  • Inside a town: the commissioner may build an entrance only where an interlocal agreement is in place.

Building an access drive without a permit means work stops, the owner may have to pay for damage, and no further permits are issued until the problem is put right.

Pipeline and utility crossing permit fees

Pipelines and utility lines on or across county roads need a Public Service/Pipeline Crossing permit (form revised May 2026). The application goes to the County Clerk at least 5 days before a commissioners’ meeting with a check to the County Treasurer, and the permit runs for 30 days; a 60-day permit is available for an additional fee.

Rather talk it over?

Call 1-855-478-4290 →
Woodward County crossing permit fees (May 2026 form)
Crossing30-day fee
Road bored by the applicant$1,000 per line
Road cut or trenched (only if the county approves)$2,500 per line
Overhead line, per crossing$1,500
Line through an existing culvert or under a bridge$1,500
Cut fixed entry in county right-of-way; cut entry for a road or entrance$1,500 each
Over-the-road crossing (7 days)$2,500 per line
Parallel overhead line; parallel above-ground pipeline$1,500 per mile
Parallel water line$500 per mile per line
60-day permit renewalTwice the 30-day fee
Work started before approval$5,000 fine

All crossings must be bored unless trenching is approved, and underground crossings must be at least 4 feet below the road centerline or the ditch flowline, whichever is deeper. Call the commissioners’ office 48 hours before work so an inspector can be on site. Fees are not refunded after final approval. An older version of the form with lower fees is still posted on the county’s forms page; the May 2026 revision is the current one.

Rather not deal with the Woodward County building department?

Get a free quote →

How to get permits for a rural Woodward County build

1. Confirm town or county

Inside Woodward, Mooreland or Fort Supply, apply to the town; the county has no building permit.

2. Check the floodplain

Ask Emergency Management for the floodplain maps; any floodplain work needs a permit approved by the Floodplain Board before it starts.

3. Driveway entrance

Send the May 2026 driveway entrance application, map and drawing to the commissioners, then call the district commissioner 5 days before building.

4. 911 address

Complete Woodward County 911’s online address request and allow 2 to 3 business days.

5. Septic

Apply to DEQ for the onsite sewage permit.

6. Utility lines

Utility companies and contractors crossing county roads file the crossing permit with the County Clerk.

Local Woodward County details

Commissioners’ meetings: the Board meets in the courthouse board room at 10:00 a.m.; individual driveway entrance permits appear on its agendas, such as one on October 13, 2026.

Floodplain regulations: Emergency Management provides the floodplain maps and the Woodward County Floodplain Regulations on request. The crossing permit form notes that development in the county floodplain area needs its own permit.

City floodplain: inside Woodward, the City’s Code Enforcement Office issues development permits for FEMA flood hazard areas, not the county.

Oklahoma building code

Oklahoma sets statewide minimum codes (the 2024 editions since September 14, 2026) that cities enforce and may strengthen; most counties issue no building permits for unincorporated land, though a few do. Oklahoma rules

Want this handled start to finish?

Get a free quote →

Official Woodward County permit resources

Woodward County permit FAQs

Inspections are where schedules slip.

Get a free quote →

Does Woodward County issue building permits?

No. The state building code commission lists Woodward County as issuing no permits. The county permits driveway entrances, road crossings and floodplain work.

Do I need a permit for a driveway onto a county road?

Yes. Every new entrance needs a permit from the Board of County Commissioners and a drainage culvert. There is no fee for a residential or agricultural entrance; a commercial entrance costs $2,000.

How much is a road crossing permit in Woodward County?

A bored crossing is $1,000 per line for 30 days, a cut or trenched crossing $2,500 per line, and work started before approval is fined $5,000.

Who approves building in a floodplain?

The Floodplain Board of Woodward County, through the Emergency Management director, who is the county Floodplain Administrator.

Who issues building permits in Woodward, Mooreland and Fort Supply?

Woodward’s Code Enforcement Office (580-254-8515); Mooreland’s town building official (580-994-5924); and in Fort Supply, the town clerk (580-766-3211).

How long does a 911 address take?

Woodward County 911 asks for 2 to 3 business days after the online request.

Simplify Woodward County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Oklahoma. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Woodward County sooner?

Let Alliance prepare, file, and track your Woodward County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Woodward County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.