In the City of Solon, building permits are issued by the Building Department on the first floor of City Hall, 34200 Bainbridge Road (440-349-6737), whose staff the Ohio Board of Building Standards certifies for residential and commercial code enforcement. Applications go in person or by email, Building, Planning and Engineering (and Fire, for commercial work) review them in about 7 to 10 business days, and the permit is invoiced once every contractor is registered. A new house is charged $200 plus $15 per 100 square feet for the building permit, plus the trade permits and the 1% state fee.
What requires a building permit in Solon?
Solon’s “Residential Permits – When Required” guide, updated October 15, 2024, is broad: it lists as permit work nearly every change to a house’s structure, systems or exterior, and some site work besides.
Permit required (examples)
- Any electrical installation, including replacing or adding a fixture, outlet or switch, and car chargers
- Furnace, air conditioner and water heater replacements; new gas piping
- Kitchen or bath remodels that move or alter electrical, plumbing or HVAC lines
- Roofing and siding, including repairs; replacement exterior windows or doors
- Decks, patios, garages, sheds, fences, greenhouses and gazebos
- Basement finishing, wall removal or addition, and framing
- Pools deeper than 24 inches, generators, solar panels and fireplaces
- Gutters and downspouts, masonry and chimney restoration, antennas and satellite dishes
- Topsoil removal, grading and tree clearing on undeveloped land
No permit on the guide
- Interior or exterior painting and wallpapering
- Carpeting, vinyl flooring and refinishing wood floors
- Replacing an interior, non-glass door of the same size
- Swapping laundry or kitchen appliances without moving gas, plumbing, electrical or HVAC lines
- Replacing plumbing fixtures and adding a refrigerator water line
Retaining walls more than 4 feet from the bottom of the footing may need a design professional. Driveways, aprons, sidewalks and curb cuts are handled by the Engineering Department at 440-349-6745, not the Building Department.
What Solon decides and what the state holds
The Building Department enforces every code the Ohio Board of Building Standards adopts, so the construction standards are the state’s. Solon sets its own fees, registers contractors under its codified ordinances, runs zoning through the Planning & Community Development Department, requires land use approval for new businesses, inspects amusement devices yearly, and has its own flood hazard area, downspout disconnection and stormwater rules. The 1% residential and 3% commercial state fees go to the state.
Short on time to read all of this?
Get a free quote →Solon building department: who handles permitting
The Building Department handles most building-related permits in the city, working with the Planning & Community Development, Engineering and Fire departments, which review the same applications. Russ Rodic is the Chief Building Official, who also issues contractor registration certificates.
| Detail | Information |
|---|---|
| Office | Building Department, City Hall, 1st floor, 34200 Bainbridge Road, Solon, OH 44139 |
| Phone / fax | 440-349-6737 / 440-349-6322 |
| Permit@Solonohio.org | |
| Hours | Monday to Friday, 8 a.m. to 4:30 p.m. |
| Chief Building Official | Russ Rodic |
| Related offices | Planning and signs 440-349-6327; Engineering 440-349-6745; Fire Prevention 440-349-6333 ext. 1821 or 1822 |
Solon permit types
Every permit starts with the city’s residential or commercial application, or one of its miscellaneous forms, plus two sets of construction drawings or one digital copy, a site plan and elevations where they apply. Separate forms cover reroofing with metal, furnace, air-conditioner, water heater or electrical panel work, solar panels, driveways, downspout disconnections, fire alarms and fire suppression, tents and the flood hazard area development permit.
Residential permits
- Review. The Building, Planning and Engineering departments all review residential applications, and the applicant is emailed if more information is needed.
- Homeowners. An owner doing their own work files the Homeowner Affidavit instead of a contractor registration.
- Site plans. Additions, air conditioners, car chargers, generators, sheds, decks, gazebos, greenhouses and fences all need a site plan showing distances to the property lines and nearby structures. Hand-drawn plans are accepted, but the city recommends a topographic drawing where one exists because it shows easements and swales with their own setbacks; the Building or Engineering Department may have one on file.
- Technical sheets. Additions and alterations add construction drawings and electrical, HVAC and plumbing diagrams; car chargers and generators add the maker’s specifications; fences add the specifications or the city’s fence form; and solar panels follow their own checklist.
- Rentals. Rental properties fall under the city’s residential rental registration program.
- Garage sales. Each sale needs a $5 permit from the Building Department or online, and signs may go only on the sale property.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial applications add the Fire Department to the review. Additions and accessory structures need a site plan with full construction and technical drawings, alterations need drawings and a detailed scope of work, roof replacements need a site plan of the area and the roofing specifications, rooftop units need the units marked on a site plan with the new equipment’s specifications, and parking lot or driveway replacements need a site plan and scope. Any new tenant or business needs a land use application, which can be filed ahead of the building permit for new buildings or tenant remodels, or on its own where no remodeling is planned. Signs go to the Planning & Community Development Department, and amusement or game devices used by customers must be inspected every year.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning pre-application meeting. The city posts a request form for a pre-application meeting with Planning.
- Planning Commission. It reviews lot splits and consolidations and zoning variances, meeting at 7:30 p.m. on the Tuesday after the second and fourth Mondays; applications are due by noon on the Monday two weeks before.
- Site work first. Engineering review with a grade set ($200), grading and clearing, and utility, sewer and drain installation ($100 each) are charged as work required before the building permit issues; driveway, apron, sidewalk and curb work goes to the Engineering Department.
- Flood hazard areas. Work in a mapped flood hazard area uses the flood hazard area development permit; FEMA lists Solon (community 390130) as participating, with its current map dated December 3, 2010.
Solon permit costs and fees
The Building Department posts a list of building-related fees; it carries no date or ordinance number, and the codified ordinances behind it are the governing text. Residential new construction and remodeling fees add the 1% state fee, and plans-examiner time on commercial work carries a 3% surcharge.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| New house, building permit | $200 plus $15 per 100 sq ft |
| New house, each trade (HVAC, electric, plumbing) | $50 plus $10 per 100 sq ft, per trade |
| Residential remodel: building, electric or mechanical (incl. waterproofing) | $50 per trade |
| Decks and patios / detached garage / fireplace or furnace | $50 each |
| Air-conditioner replacement / hot water tank / re-roofing / re-siding | $40 each |
| Sheds, greenhouses, gazebos and similar | $30 |
| Above-ground pool / in-ground pool | $50 / $75 |
| Fence / retaining wall / satellite dish | $40 / $100 / $50 |
| Demolition: accessory / principal structure | $50 / $200 |
| New non-residential building | $175 plus $20 per 100 sq ft; electrical and mechanical $150 plus $25 per 1,000 sq ft each; plumbing $150 plus $15 per fixture |
| Non-residential alteration | $125 up to $10,000 of value; $175 from $10,001 to $20,000; $175 plus $20 per $1,000 above that |
| Plans examiner | $95 an hour plus 3% |
| Plan revisions | $50 residential; $200 non-residential |
| Re-inspection / contractor registration | $100 / $100 |
Worked example from the list: a new 3,000-square-foot house has a building permit of $200 plus 30 × $15, or $650, and three trade permits of $50 plus 30 × $10, or $350 each ($1,050), for $1,700; the 1% state fee brings it to $1,717. Moving a house or accessory structure costs $100, as does disconnecting downspouts from the sewer. Fees are invoiced by the department after review, and the list notes that fire prevention and wireless tower fees are set in the codified ordinances.
Trade permits and who may pull them
HVAC, electrical and plumbing permits are priced per trade, and fire alarm and fire suppression systems have their own permit applications and joint inspections with the Solon Fire Prevention Bureau.
- Registration. No contractor may work in Solon without a certificate of registration from the Chief Building Official, valid for the calendar year and renewed annually; every contractor and subcontractor must be listed and registered before a permit issues. The fee is $100.
- Insurance and bond. General liability of $1,000,000 per occurrence and $2,000,000 aggregate, naming the city as additional insured, plus a signed and sealed City of Solon contractor registration bond. The city’s FAQ puts that bond at $25,000 and explains that it protects code compliance for the city, not a homeowner’s price, schedule or contract.
- State licenses. Electrical, HVAC, refrigeration, hydronics and plumbing contractors show their Ohio Construction Industry Licensing Board license; fire suppression and fire alarm contractors show their license from the State Fire Marshal’s office.
- Filing. Registrations can be emailed to Permit@Solonohio.org, with the fee paid by card online or by phone after the department sends an invoice.
- Homeowners. Owners doing their own work sign the Homeowner Affidavit.
Rather not deal with the building department?
Get a free quote →How to apply for a Solon building permit
Use the residential permit guide, and call Engineering first for driveway, apron, sidewalk or curb work.
Request a pre-application meeting or file with the Planning Commission if the job needs a variance or a lot change.
Use the residential or commercial form, with two drawing sets or one digital copy, a site plan and elevations.
Every contractor and subcontractor registers; an owner doing the work signs the Homeowner Affidavit.
File at the Building Department window or email Permit@Solonohio.org; the departments review it in about 7 to 10 business days.
Pay online, by phone or in person, then collect the permit and job documents by email or at the window.
Review, corrections and what causes delay
The invoice is not sent until every contractor’s registration is complete, so an unregistered subcontractor holds up the permit. Each reviewing department may email for more information, and any change to submitted or approved documents goes back through review with a revision fee of $50 for a house or $200 for non-residential work. The city notes that state rules allow 30 calendar days for plan review and approval, against its usual 7 to 10 business days.
Inspections in Solon
Each permit lists its required inspections. Book them by phone at 440-349-6737, Monday to Friday from 8 a.m. to 4:30 p.m., or by email to permit@solonohio.org; voicemail and email requests need at least 24 hours’ notice. Calls between 8 and 9 a.m. may get a same-day inspection if inspectors are free, while requests made from 9 a.m. to 4:30 p.m. go to the next available business day, and plumbing inspections are not offered every day. Have the address, permit number, inspection type, a contact name and number, and an a.m. or p.m. preference ready. A re-inspection costs $100.
Life safety finals, kitchen hoods, fire suppression and fire alarm systems are joint inspections by the Fire Prevention Bureau and the Building Department, booked the same way; fire questions can also go directly to the Fire Department.
Ohio building code in Solon
Solon’s certified staff enforce the codes adopted by the Ohio Board of Building Standards for houses and commercial buildings, and the department links the state’s online code library from its pages.
Want this handled start to finish?
Get a free quote →Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Solon permit search and official resources
Permit invoices are paid and applications started on the city’s online permitting portal, and the Building Department posts a list of registered contractors. For permit records or plans on a Solon address, ask the Building Department at 440-349-6737 or Permit@Solonohio.org; the city also posts open records request forms on its Permits & Forms page.
- Solon Building Department
- Building permits and the review process
- Residential permits: when required guide
- Building-related fees
- Residential permit application
- Non-residential permit application
- Homeowner affidavit
- Contractor registration
- Inspection scheduling
- Planning Commission
- Flood hazard area development permit
- City permits and forms
- Online permitting portal
- FEMA Community Status Book, Ohio
Inspections are where schedules slip.
Get a free quote →Solon building permit FAQs
How long does a building permit take in Solon?
The city says review currently takes 7 to 10 business days once the application and all required documents are in, and the invoice follows once every contractor is registered.
How much is a permit for a new house?
$200 plus $15 per 100 square feet for the building permit, plus $50 and $10 per 100 square feet for each of the HVAC, electrical and plumbing permits, and the 1% state fee.
Do I need a permit to replace a light fixture or outlet?
Yes. Solon’s guide lists replacing or adding any fixture, outlet or switch as permit work.
Can I pull a permit as a homeowner?
Yes, by signing the Homeowner Affidavit for work you do yourself; any contractor on the job must be registered.
What does contractor registration require?
A $100 fee, $1 million per occurrence and $2 million aggregate liability insurance naming the city, a city bond form, and state licenses for the licensed trades.
Who handles driveways and curb cuts?
The Engineering Department, at 440-349-6745.
When should I make the final payment to my contractor?
The Building Department’s advice is to get at least three bids, use a written contract, confirm the contractor is registered with Solon, and make sure the final inspection has passed before the last payment or sign-off.
Can I get a same-day inspection?
Possibly, if you call between 8 and 9 a.m. and an inspector is available; later requests are scheduled for the next business day.
Simplify Solon permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Solon sooner?
Let Alliance prepare, file, and track your Solon permits while your crew stays on the job.
More Ohio permitting guides
Cuyahoga County
Read guide →South Euclid
Read guide →Strongsville
Read guide →Springboro Building Permit Guide
Read guide →Springdale Building Permit Guide
Read guide →Springfield Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Solon permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.