In Bedford Heights, the city’s Building Department at City Hall, 5661 Perkins Road (440-786-3237), issues and tracks permits for new construction, additions, alterations, repairs and demolition, and inspections are scheduled with SAFEbuilt at 440-399-0850. Every contractor and subcontractor must be registered and bonded with the city before a permit is issued. Under Chapter 1329 of the city code, a new single-family house costs $200 plus $8 per 100 square feet of floor area, and the city holds a $1,000 deposit until the final inspection.
What requires a building permit in Bedford Heights?
The Building Department’s remit is broad: permits for all new construction, alterations, additions, repairs and demolition, each inspected for compliance with the Bedford Heights Building Code. The fee chapter shows how far that reaches into ordinary house projects.
Building permits
- New houses, apartments and commercial buildings, and additions to them
- Interior alterations and fire restoration
- Windows, siding, roofing, gutters and downspouts
- Patio enclosures and three-season rooms, decks, garages and sheds
- Foundations, greenhouses and moving or demolishing a building
- Curb cuts and driveway aprons
Separate trade permits
- Electrical work, including pool wiring
- Plumbing, sewers, drain tile and waterproofing
- Furnaces, boilers, air conditioning, ductwork and gas piping
- Hot water tanks and heaters
- Fire sprinklers and landscape sprinkler systems (with a backflow device)
- Water storage tanks and water connections to air conditioning units
The general interior permit does not cover the trades: the fee chapter says electrical, plumbing, mechanical and fire restoration each need their own permit. A building on a flood hazard area needs a separate permit application, which the building permit form asks you to flag.
What Bedford Heights decides and what the state holds
Ohio sets the building codes and certifies the departments that enforce them. Bedford Heights sets its own permit fees and deposits (Chapter 1329), requires contractor registration (Chapter 1333), runs zoning through its Planning Commission, Zoning Board of Appeals and Architectural Board of Review, and requires an occupancy permit and point-of-sale inspection before anyone moves into a house that changes hands. Inspections are scheduled through SAFEbuilt, whose deck and porch guidelines the city posts, and the city engineering role is held by Chagrin Valley Engineering. FEMA lists Bedford Heights as a participating flood insurance community, with maps dated December 3, 2010.
Bedford Heights building department: who handles permitting
The Bedford Heights Building Department handles permits and keeps the records; SAFEbuilt takes the inspection calls. The department sits in City Hall: on arrival, use the phone in the vestibule, choose the Building Department, and someone comes to the door. Fees can be paid by credit card in person or by phone, including permits, contractor registration, point-of-sale and occupancy inspections, and board application fees. The city of Bedford, a separate municipality next door, has its own Building Department, so check the parcel’s city before filing.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Department, Bedford Heights City Hall, 5661 Perkins Road, Bedford Heights, OH 44146 |
| Phone / fax | 440-786-3237 / 440-786-3277 |
| Counter hours | Opens 9:00 a.m., closed for lunch noon to 1:00 p.m., closes 4:30 p.m. |
| Inspections | SAFEbuilt, 440-399-0850, Monday to Friday 9:00 a.m. to noon and 1:00 to 4:00 p.m.; 24 hours’ notice minimum |
| City engineer | Chagrin Valley Engineering, Ltd., 22999 Forbes Road, Bedford |
| City Hall main line | 440-786-3200, Monday to Friday 8:30 a.m. to 5:00 p.m. |
Bedford Heights permit types
The city’s forms page carries fillable applications for a building permit, electrical, mechanical installation, plumbing and sewer installation, fence and sign permits, a driveway apron form, occupancy permits, and the three board applications. The building permit form covers residential and commercial work and asks for the lot dimensions, wall and roof construction, floor areas, heating, cooling and fire protection systems, the estimated cost, and the Ohio registration numbers of the designer and the general contractor.
Residential permits
- New houses pay a $75 plan filing fee, a $500 deposit toward the city’s professional review costs, and the permit fee by floor area, which counts every floor, the basement and half of any attic.
- Fences need a survey with the pins visible; residential fences top out at 6 feet with no pointed tops, run along the rear and side lines only up to the rear building line, and face their good side out.
- Sheds need a drawing and a plot plan. One accessory building besides a garage is allowed per lot, up to 120 square feet, 8 feet tall with a flat roof or 11 feet with a pitched one.
- Decks and porches follow SAFEbuilt’s posted guidelines.
Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
Apartments, motels, hotels and business, commercial or industrial buildings pay a $250 plan filing fee with a $750 plan review deposit, plus a $2,000 deposit for the city’s architectural, engineering and legal review. No commercial permit is issued until those consultant fees are paid, and the chapter provides for unused sums to be refunded within 60 days of the permit. Commercial occupancy permits and inspections have their own application form.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Zoning Board of Appeals. Hears appeals of a zoning inspector’s permit denial, variances and conditional use permits on the second Tuesday; file at least 20 days ahead with a $100 fee.
- Planning Commission. Chaired by the Mayor and meeting on the second Tuesday at 5:00 p.m.; file three weeks ahead with 13 sets of drawings and supporting material and a $100 fee.
- Architectural Board of Review. Meets on the second Tuesday at 2:00 p.m.; the deadline is noon on the Monday 21 days before. Bring five sets of plans and site plans, landscape designs for commercial work, material and color samples, photos of the neighboring properties and $150. City-owned lots sold for new homes require ABR review of the plans, a house of at least 1,600 square feet and construction within a year.
- Floodplain. Work in a flood hazard area takes its own permit application.
Bedford Heights permit costs and fees
Bedford Heights posts its fee chapter, Chapter 1329 “Permits and Fees”, under the notice that some application fees have changed; the file is labelled as the 2019 legislation, and the posted copy stops partway through the electrical section. Deposits sit on top of the permit fees: $1,000 for a new house, $500 for a residential addition or alteration (waived for work under $1,000) and $4,000 for apartments and commercial or industrial buildings. After the final inspection the city keeps $200 of a single-family deposit, or $500 on other work, as a final inspection fee and refunds the rest. A Board of Building Standards assessment of 1% of residential and 3% of nonresidential fees is added under state law.
| Work | Fee |
|---|---|
| New one-family house | $200 + $8 per 100 sq ft of floor area; occupancy permit $100 |
| Plan filing fee | $75 per house; $250 per commercial building plus $750 plan review deposit |
| General interior alteration (1–2 family) | $175 |
| Fire restoration | $300 |
| Roofing, windows, siding, patio enclosure | $100 each |
| Gutters and downspouts | $25 |
| Private garage; deck; tool shed | $100; $100; $50 |
| New commercial building or commercial alteration | $300 per floor + $10 per 100 sq ft |
| Commercial roof | $200 + $5 per 100 sq ft |
| Furnace replacement (single-family); new heating system | $50; $75 |
| Hot water tank replacement; residential A/C up to 3 tons | $75; $100 |
| Plumbing alteration | $50 base ($100 commercial) + $5 per fixture |
| Waterproofing | $100 + $1 per foot of drain tile + $15 per sump pump |
| Electrical, 1–2 family base; residential pool wiring | $75; $200 |
| Curb cut; driveway apron | $50; $50 |
| Demolishing a primary building | $10,000 cash surety bond, $150 kept as the inspection fee |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the chapter: a new house with 2,400 square feet of floor area, counting the basement, pays $200 plus 24 × $8, or $392, for the building permit, plus the $75 filing fee and the $100 occupancy permit, for $567 before trade permits and the state assessment. The $1,000 deposit and the $500 professional review deposit are paid as well and are partly or fully refundable.
Trade permits and who may pull them
Electrical, plumbing and sewer, and mechanical work each take their own application. Chapter 1333 of the city code says contractors in building and allied trades must be registered with the city, and the registration packet adds that every contractor and subcontractor must be registered and bonded before a permit is issued. The packet lists the classifications, from carpentry, concrete and masonry to electrical, plumbing and heating, roofing, siding and windows, sewer, signs, pools and fire alarms, and a firm working in more than one needs a registration for each.
- Fee: $100 for the calendar year or any part of it; registrations expire on December 31.
- Bond: a $10,000 performance bond on the city’s form, or a $50,000 cash deposit instead.
- Insurance: public liability of at least $500,000 for personal injury and $300,000 for property damage, with the city named as additional insured.
- Paperwork: the application signed by a company officer, a photo ID and the city income tax forms. No permit is issued until everything is in.
Commercial electrical, HVAC, hydronics, plumbing and refrigeration contractors also need their state license from the Ohio Construction Industry Licensing Board. The city posts its list of registered contractors (the current list is dated May 5, 2026) so owners can check a firm before hiring it. An owner planning to do their own work should ask the department at 440-786-3237 how a homeowner permit is handled.
Rather not deal with the building department?
Get a free quote →How to apply for a Bedford Heights building permit
Confirm the address is in Bedford Heights and find its district on the 2021 zoning map.
File with the Architectural Board of Review, Planning Commission or Zoning Board of Appeals by their deadlines if the project needs them.
Each firm on the job registers and posts its bond before any permit can be issued.
Use the fillable building, electrical, mechanical, plumbing and sewer or fence application, with drawings and the estimated cost.
Bring the forms to the Building Department at 5661 Perkins Road and pay the filing fee, deposits and permit fees; cards are accepted.
Call 440-399-0850 at least 24 hours before each stage.
Review, corrections and what causes delay
Commercial plans wait until the city’s professional review costs are paid, and if a deposit runs low the applicant must top it back up to the original amount. Revised plans after a permit is issued carry a new filing fee of $20 plus $2 per 100 square feet, up to $75. Board cases run on their own clocks: the ABR packet is due 21 days before its meeting, and the Planning Commission needs 13 sets three weeks ahead.
Inspections and certificates in Bedford Heights
Call SAFEbuilt at 440-399-0850 on weekdays between 9:00 a.m. and noon or 1:00 and 4:00 p.m.; the office closes for lunch, and every inspection needs at least 24 hours’ notice. Fences have two required inspections: the post holes, before any posts are set, with a string line pulled between the property pins, and a final with the string still in place. Wood fence posts go 36 inches deep and chain-link posts 24 inches, set in concrete.
When the work is done, ask the department for the final inspection and the return of the construction deposit. If the work is incomplete, property was damaged or the site was left dirty, the city holds the deposit until it is fixed, and can make the repairs itself and deduct the cost.
Selling or renting a house. Nobody may move into a single-family or two-family home or a duplex suite until the Building Commissioner issues an occupancy permit, unless one was issued in the last six months. The point-of-sale inspection costs $100, with $50 more for a sewer dye test if none was done in the past year. Violations not fixed before the title transfers must be covered by an escrow of 100% of the approved repair estimate (at least $100), released only on the city’s written approval. Breaking the chapter is a first-degree misdemeanor with a minimum fine of $250.
Ohio building code in Bedford Heights
The Building Department applies the Bedford Heights Building Code and the state codes; the city’s building page links the Residential Code of Ohio and the Ohio Administrative Code rules on certificates of occupancy. To confirm which department holds residential and commercial authority over a particular address, use the Board of Building Standards look-up map.
Want this handled start to finish?
Get a free quote →Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Bedford Heights building permit FAQs
Who do I call to book an inspection in Bedford Heights?
SAFEbuilt, at 440-399-0850, at least 24 hours ahead, on weekdays between 9:00 a.m. and 4:00 p.m. outside the noon hour.
How much does a building permit cost for a new house?
$200 plus $8 per 100 square feet of floor area, plus a $75 filing fee, a $100 occupancy permit and a $1,000 deposit, most of which is refunded after the final.
Do I need a permit for a new roof or windows?
Yes. Roofing, windows and siding are $100 each, and gutters and downspouts $25.
What does contractor registration cost?
$100 a year per classification, with a $10,000 performance bond or $50,000 cash deposit and proof of insurance.
How big can a shed be?
Up to 120 square feet, and 8 or 11 feet tall depending on the roof; only one accessory building besides a garage is allowed.
Is an inspection needed when I sell my house?
Yes. A $100 point-of-sale inspection and an occupancy permit come first; unfinished repairs need an escrow of 100% of the estimate.
When does the Architectural Board of Review meet?
The second Tuesday of the month at 2:00 p.m.; plans are due by noon on the Monday 21 days before, with a $150 fee.
Bedford Heights permit search and official resources
The Building Department keeps the city’s permit records. To ask about a permit, an inspection or a property’s file, call 440-786-3237 or visit City Hall during counter hours; point-of-sale and occupancy questions go to the same office.
Inspections are where schedules slip.
Get a free quote →- Bedford Heights Building Department
- Forms and permits
- Chapter 1329, permits and fees (2019 legislation)
- Building permit application
- Contractor registration packet
- Point-of-sale inspections
- Fence installation requirements
- Shed installation requirements
- Deck and porch guidelines (SAFEbuilt)
- Planning Commission application
- Zoning Board of Appeals application
- Architectural Board of Review application
- Zoning map (2021)
- BBS building department look-up
- Ohio Board of Building Standards
Simplify Bedford Heights permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Bedford Heights sooner?
Let Alliance prepare, file, and track your Bedford Heights permits while your crew stays on the job.
More Ohio permitting guides
Cuyahoga County
Read guide →Berea
Read guide →Brecksville
Read guide →Belmont County Building Permit Guide
Read guide →Bexley Building Permit Guide
Read guide →Blue Ash Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Bedford Heights permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.