Bedford, Ohio Building Permit Guide

To get a building permit in Bedford, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Bedford’s Building Department at City Hall, 165 Center Road, issues building, electrical, plumbing and mechanical permits for the whole city, in person or through its Citizenserve portal, where every plan review must be filed.

Authority: Bedford Building DepartmentFees: Section 1305.16 schedulePhone: 440-735-6530
Authority
City Building DepartmentResidential and commercial
New house
$250 + $20 per 100 sq ftBuilding permit, plus 1%
Contractors
City registration$15,000 bond on city form
Hours
Mon–Fri 8–4440-735-6530

In the City of Bedford, permits come from the Building Department at Bedford City Hall, 165 Center Road (440-735-6530), led by Building Department Commissioner Michael Greer. The city says it is a state-certified department for both residential and commercial work. You can apply at the counter from 8 a.m. to 4 p.m. on weekdays or online through Citizenserve, and all plan reviews go through the portal. A new house pays a building permit of $250 plus $20 per 100 square feet under the Section 1305.16 fee schedule, with separate trade permits and plan review on top.

What requires a building permit in Bedford?

Bedford’s own permit list reaches well past new buildings, and the city says it is not a complete list, so call before starting anything close to it.

Structures and site

  • New construction, alterations, structural changes and repairs
  • Demolition of any residential or commercial structure
  • Decks, porches, patios, sheds and fences
  • New or replacement concrete and pavers: patios, driveways, sidewalks, parking lots and driveway aprons
  • Roof replacements, waterproofing inside or out, retaining walls and grade changes
  • Swimming pools, spas and hot tubs; tents (call first); every sign, including temporary banners

Trades and systems

  • Electrical work, including new or replacement panels, new conductors and new or upgraded services
  • Interior plumbing, including new or replacement water and sewer piping and fixtures
  • Hot water tank installation or replacement
  • Exterior water, sewer and gas lines from the building to the street
  • Heating, cooling and refrigeration
  • Fire alarms and fire suppression systems

Solar and wind systems count too: Bedford says every one, even a small residential system, needs Building Department approval. Public sidewalk work carries no permit charge but still needs a city inspection.

What Bedford decides and what the state holds

The state writes the building codes and certifies departments to enforce them. Bedford decides everything around that: its Building Code (Chapters 1301 to 1399) and Zoning Code (Chapters 1901 to 1999), its fee schedule, contractor registration, rental licensing and the Bedford Dwelling House Code it applies to homes, which takes in the Residential Code of Ohio and the property maintenance code. The Building Department, run under the general direction of the City Manager’s Office, enforces building, housing and zoning rules together, so one counter answers most questions. Flood questions start on the residential plan review form, which asks whether the lot is in a floodplain and whether the floodplain administrator has been contacted; FEMA lists Bedford as a participating community with maps dated December 3, 2010.

Bedford building department: who handles permitting

The city’s Building Department issues every building and trade permit inside Bedford. Its permits page says it is a State of Ohio certified department for residential and commercial work, enforcing the Residential Code of Ohio for one-, two- and three-family homes and the Ohio Building Code for commercial buildings. Bedford Heights, next door, is a separate city with its own office, so check which city the parcel sits in before filing. Cuyahoga County’s new Division of Building Standards says it will serve partner communities still to be announced; Bedford issues its own permits today.

Short on time to read all of this?

Get a free quote →
Bedford Building Department contacts
DetailInformation
OfficeBedford City Hall, Building Department, 165 Center Road, Bedford, OH 44146
Phone / fax440-735-6530 / 440-232-1558
EmailBuilding@bedfordoh.gov
HoursMonday to Friday, 8:00 a.m. to 4:00 p.m.
Building Department CommissionerMichael Greer, 440-735-6531
Online portalCitizenserve (citizenserve.com/bedford): permits, contractor registration, rental registration and plan approval
Board contactThe Commissioner is the listed contact for the Planning Commission, Board of Zoning Appeals, Board of Building Standards and Appeals and Historical Preservation Board

Bedford permit types

Bedford keeps a separate application for each trade: residential building, electric, mechanical, plumbing and roof permits, plus residential and commercial plan review applications. The residential building form lets you tick new construction, a garage, major additions or alterations of 500 square feet or more, minor work under 500 square feet, decks, sheds, siding, porches, interior renovations, fences, pools and waterproofing, and it asks for the contractor and the estimated cost.

Residential permits

  • New houses and additions need a residential plan review application filed through Citizenserve. The form notes that drawings for houses must show who prepared them but need no professional seal, citing the state law on residential plans.
  • Sheds cost $75 and need a site plan showing distances to the property lines and other buildings, a material list and construction documents. A shed sits in the rear yard at least 3 feet from the side line, 6 feet from the rear line and 10 feet from any other structure, may cover no more than 30% of the rear yard, and is capped at 15 feet tall.
  • Fences, sidewalks, driveways and pools have their own handouts: a 2025 fence permit worksheet, sidewalk and driveway requirements, and swimming pool requirements. Concrete slabs must be at least 4 inches thick, and a residential apron and the sidewalk across it 6 inches.
  • Doing your own work: an owner may pull permits under a notarized Homeowner’s Affidavit (see trades below).

Commercial permits

Commercial projects start with the commercial plan review application in the portal, and fire alarm and sprinkler drawings must be approved before installation. A new tenant or new use needs a certificate of occupancy: the application, revised March 2026, quotes the Ohio Building Code rule that no building may be used until the building official issues one, asks for the prior use, staff and customer numbers and any new plumbing or electrical work, requires a floor plan showing exits, room uses and occupant load, and lists a $25 application fee.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. The Building Department also enforces the Zoning Code, so zoning questions go to the same counter; check the parcel’s district on the city zoning map first.
  • Planning Commission. Site plans and development proposals go to the commission, which meets on the first and third Tuesdays as needed at 6:30 p.m.; file at least two weeks ahead with a $50 fee. The commission recommends and City Council makes the final decision.
  • Board of Zoning Appeals. Variances, administrative appeals and nonconforming-use questions are heard on fourth Tuesdays as needed at 6 p.m. for a $75 fee, and the filing deadline is seven weeks before the meeting.
  • Water, sewer and streets. Water and sewer taps must be installed by a registered contractor and inspected by the city; when the City Manager, City Engineer or Building Commissioner requires it, public or private site improvements need a completion bond of 125% of the work.

Bedford permit costs and fees

Bedford’s permit fees come from Section 1305.16 of its Building Code. The posted schedule says it took effect on January 1, 2024. Plan review and outside consultant fees are not included in the permit fee and are billed to the owner separately under Section 1305.6. The schedule adds 1% for the state on residential fees and says to add 5% on commercial fees for the “State/City surcharge”; the Board of Building Standards assessment itself is 1% of residential and 3% of nonresidential fees.

Bedford permit fees (Section 1305.16, effective January 1, 2024)
WorkFee
New 1–3 family dwelling, building permit$250 + $20 per 100 sq ft
New dwelling: electrical, mechanical or plumbing permit$150 + $12 per 100 sq ft each
Garage (any size)$100 building; $75 electrical
Residential major addition or alteration (over 500 sq ft)$250 building; $125 each trade, per dwelling unit
Residential minor work under 500 sq ft (roofs, siding, sheds, decks, porches, interior alterations)$75
Residential furnace or A/C, minor electrical or plumbing, demolition$75 each
New or replacement electrical service; pool with its wiring$100 each
New commercial building$300 + $7.50 per 100 sq ft; trades and sprinklers $175 + $4.50 per 100 sq ft
Commercial minor building work, including roofs$175
Commercial sign / temporary sign (30 days)$75 / $35 each
Fence; driveway or apron$50; $50 residential, $75 commercial
Water connection; residential sewer connection$1,450; $1,000 per unit
Street opening$500 each
Re-inspection; permit extension$50; $15 per 6 months
Work started without a permitTwice the normal fee

Rather talk it over?

Call 1-855-478-4290 →

Worked example from the schedule: a new 2,000-square-foot house pays a building permit of $250 plus 20 × $20, or $650, and each of the electrical, mechanical and plumbing permits is $150 plus 20 × $12, or $390. Those four permits total $1,820 before the 1% state charge and before the separate plan review bill.

Trade permits and who may pull them

Electrical, plumbing and mechanical work each takes its own Bedford permit, separate from the building permit. Every contractor who works in the city must register first, by trade classification, either at the counter or in Citizenserve. The registration package is the same for every trade:

  • a registration for each classification you work in;
  • a copy of the current State of Ohio certificate for plumbing, electrical and HVAC contractors;
  • insurance of $100,000/$300,000 for bodily injury and $100,000 for property damage, naming the City of Bedford as additional insured;
  • an original $15,000 bond on the city’s own form (copies are refused unless you apply online).

Registration runs for the calendar year and expires on December 31, and the fee is not refundable. Starting work before registering costs triple the registration fee for a first offense, $300 for a second and $500 for each one after that.

Homeowners. Bedford’s Homeowner’s Affidavit lets an owner pull building, electric, HVAC or plumbing permits for work they do themselves, but only on an owner-occupied primary residence, never a rented or leased home. The owner swears before a notary to live there for at least one year after the final inspection, accepts the same inspection schedule as a registered contractor, and must hire only registered firms for any part of the job they do not do personally.

Rather not deal with the building department?

Get a free quote →

How to apply for a Bedford building permit

1. Confirm the city and the zoning

Make sure the parcel is in Bedford, not Bedford Heights, and check its district on the city zoning map.

2. Line up registered contractors

Every contractor on the job registers with Bedford before work starts; an owner doing the work signs the Homeowner’s Affidavit.

3. Clear any board approvals

Book the Planning Commission (two weeks’ notice) or the Board of Zoning Appeals (seven weeks) if the project needs them.

4. File the plan review in Citizenserve

Upload drawings for new buildings, additions and commercial work; Bedford takes plan reviews only through the portal.

5. Apply for each permit

Use the residential building, electric, mechanical, plumbing or roof form, online or at City Hall between 8 a.m. and 4 p.m.

6. Pay and post the permit

Pay the permit fees and the separate plan review bill, then post the permit and the address where they can be seen.

Review, corrections and what causes delay

The residential plan review form quotes the state rule that a failure to approve construction documents within 30 days of filing counts as a denial the applicant can appeal, and that every denial must state its reasons. The forms ask for the floodplain status, the person who prepared the drawings and the contractor, so leave none of them blank, and file board cases before their deadlines. Ask about an extension before a permit runs out; each six-month extension costs $15.

Inspections and certificates in Bedford

Call the Building Department at least 24 hours before work is ready. Approved drawings, including any truss shop drawings, must be on site for every inspection, and the permit must be posted where it can be seen; the handout warns that an unposted permit counts as no permit. Bedford charges nothing extra for a legitimately scheduled inspection, pass or fail, but a visit for work that was not ready or was cancelled, or where nobody met the inspector, may be charged; the schedule sets re-inspections at $50.

  • Before concrete: location and setback (corners staked, address posted, site plan on hand), footers before any concrete, waterproofing and drain tile, underground piping, and slabs, including driveways and aprons.
  • Rough stage: plumbing, electrical and mechanical rough-ins, then framing, then insulation and vapor barrier. The electrician and plumber must attend their rough inspections.
  • Single items: panel replacements with the cover off, roofs during installation (ice and water shield checked; no more than two layers), deck post holes, fence locations with property pins showing, water heaters and furnaces.
  • Finals: electrical, plumbing, mechanical and building finals, with patching to match existing finishes under Section 1913.07.

Bedford froze point-of-sale inspections on May 13, 2016. A sale still needs a free Certificate of Transfer from the Building Department after a $40 special assessment search by the Finance Department. Rentals need an annual Certificate of Rental License ($150 for a one-, two- or three-family home, $50 per suite in larger buildings, doubled if unpaid by March 1) and a rental inspection every two years or at each change of tenant.

Want this handled start to finish?

Get a free quote →

Ohio building code in Bedford

Bedford describes itself as a State of Ohio certified building department for residential and commercial work, enforcing the state codes through its own Building Code and the Bedford Dwelling House Code. The Board of Building Standards look-up map shows which department has authority over an address.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Bedford building permit FAQs

Do I need a permit to replace my roof in Bedford?

Yes. A residential roof replacement is minor work at $75, and the roof is inspected during installation; Bedford allows no more than two layers.

How much is a shed permit?

$75, with a site plan, material list and drawings. The shed must stay 3 feet from the side line and 6 feet from the rear line.

Can a homeowner do their own electrical or plumbing work?

Yes, on an owner-occupied primary residence, by signing the notarized Homeowner’s Affidavit and agreeing to live there at least a year after the final. It cannot be used for a rental.

Does Bedford still do point-of-sale inspections?

No. They have been frozen since May 13, 2016, but a Certificate of Transfer is still needed, after a $40 special assessment search.

How do I schedule an inspection?

Call 440-735-6530 at least 24 hours ahead, and keep the approved drawings and posted permit on site.

Is plan review included in the permit fee?

No. Plan review and consultant fees are billed separately under Section 1305.6.

What does it cost to start work without a permit?

Twice the normal permit fee. A contractor caught working unregistered is also fined triple the registration fee for a first offense.

Bedford permit search and official resources

Permit holders can check applications, plan approvals and inspections in the Citizenserve portal. For older permits or a property’s file, email the Building Department at Building@bedfordoh.gov or call 440-735-6530; title companies get Certificates of Transfer by fax or email from the same office.

Inspections are where schedules slip.

Get a free quote →

Simplify Bedford permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Bedford sooner?

Let Alliance prepare, file, and track your Bedford permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Bedford permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.