Building permits in Logan County are handled by the Logan County Building Authority, 1365 County Road 32 North, Suite 2, Bellefontaine (937-592-7473), where Joseph Kipp is the Chief Building Official. It issues separate building, electrical and HVAC permits, reviews residential and commercial plans and makes the inspections, and its forms send owners in Bellefontaine and the villages to it as well as owners in the townships. Every application needs a zoning permit, Health Department approval and a floodplain determination first, and since July 1, 2026 new home applications are accepted only through the online portal. Plumbing permits are issued by the Logan County Health District.
What requires a building permit in Logan County?
The Building Authority’s one-page “Will I need a permit?” sheet lists the work it permits and the work it does not. A permit is needed to erect, build, enlarge, repair, improve, alter, cover or extend any building or structure, to move one, and for electrical wiring, gas supply piping, boilers and heating apparatus, signs, air-conditioning and refrigeration, pool bonding and grounding, solar panels, cell towers, and fire suppression or alarm systems.
Permit needed
- New buildings, additions, alterations and moved buildings
- Electrical wiring and equipment; gas piping
- Furnaces, boilers, air-conditioning and refrigeration
- Signs, solar panels and cell towers
- Swimming pool bonding and grounding
- Fire suppression and fire alarm systems
No permit, per the sheet
- General maintenance and repairs
- Re-roofing a house with no structural repairs
- Fences 6 feet or less
- One-story sheds under 200 square feet
- Residential retaining walls under 4 feet
- Freestanding residential decks under 200 square feet and under 30 inches tall
- Sidewalks, driveways and interior finish work
Manufactured homes are handled differently: the sheet sends anyone placing one to the state Division of Industrial Compliance at 614-644-2223. Work that needs no building permit can still need zoning, a floodplain determination or a health department review.
What the county decides and what the state holds
The building codes are the state’s, and the Building Authority enforces them. Locally it sets the fee schedule and its own procedures, including a policy since January 2026 that every new single-family and multi-family home must have an air leakage (blower door) test, with the results at the final inspection; the code limit it quotes is five air changes per hour. Zoning belongs to the townships, villages and city, the county regulates floodplains in unincorporated areas under Resolution 212-23, and the health district runs plumbing, septic and well permits.
Logan County building department: who handles permitting
The Building Authority’s guidance tells owners that even where no zoning permit is issued they must still apply to it for construction approval, and that any special requirements from the city or a village go to it with the plans. Its floodplain determination form, which goes with every building permit application, covers projects inside Bellefontaine and the villages as well as the townships. Confirm the department for a specific address on the Board of Building Standards look-up.
Short on time to read all of this?
Get a free quote →| Community | Zoning and floodplain |
|---|---|
| Bellefontaine (city, county seat) | City zoning officer; the city floodplain administrator signs the determination |
| DeGraff, Lakeview, Quincy, Russells Point, Valley Hi, West Liberty (villages) | Village zoning officer; the village floodplain administrator signs the determination |
| Belle Center, Huntsville, Ridgeway (part), Rushsylvania, West Mansfield, Zanesfield (villages) | Village zoning officer; floodplain determination from the Logan Soil and Water Conservation District |
| Townships | Township zoning officer (none in Bloomfield Township and parts of Stokes Township); floodplain determination from the Soil and Water Conservation District |
| Office | Contact |
|---|---|
| Building Authority | 1365 County Road 32 N, Suite 2, Bellefontaine, OH 43311; 937-592-7473; Monday to Friday 7:30 a.m. to 4:00 p.m. |
| Logan County Health District (plumbing, septic, wells) | 310 South Main Street, Bellefontaine; 937-592-9040 |
| Logan Soil and Water Conservation District (soils, drainage, floodplain) | 324 County Road 11, Bellefontaine; 937-404-3150 |
| Logan County Sewer District (Indian Lake area) | 1015 State Route 708, Russells Point; 937-550-3505 |
| Logan-Union-Champaign Regional Planning Commission | 10820 State Route 347, East Liberty; 937-666-3431 |
| County Engineer (addresses, county-road driveways) | 1991 County Road 13, Bellefontaine; 937-592-2791 |
Logan County permit types
The Building Authority uses one residential and one commercial application covering all trades, but it issues separate permits for each trade: building, electrical and HVAC. New home applications must go through its iWorQ permit portal, and commercial plans may be submitted through the portal or by email. Detailed construction drawings are required for every building project.
Residential permits
- New homes. Since July 1, 2026 every new home build application must be filed through the portal; email or paper submissions are returned unprocessed.
- Additions, alterations and accessory buildings use the same residential application, listing living, non-living and garage square footage, the estimated cost and each contractor (general, electrical, HVAC and gas line).
- Electrical and HVAC details go on the form, with a system description or sketch; the office will not separate them from the plans for you.
- Furnace and air conditioner swaps have their own like-for-like replacement form.
- Plumbing is permitted by the Logan County Health District, not the Building Authority.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial work needs stamped drawings and, for new buildings, a zoning permit, health district review or sanitary sewer approval, and site plans. The submittal checklist asks for a title page with the code editions, fire jurisdiction, occupancy classification, construction type, occupant load and flood hazard classification, then site, demolition, structural, elevation, foundation, floor, wall-section, envelope and mechanical drawings. Commercial plumbing and food service plans go to the health district. The page also posts the state statement of special inspections, a map of fire departments and districts, and the state appeals form for commercial decisions.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning permit. From the township, village or city zoning officer; the Logan-Union-Champaign Regional Planning Commission keeps the list of township zoning officers.
- Health approval. The health district’s building site review for well and septic clearances, or a sanitary sewer review where county sewer serves the lot. Work around Indian Lake needs the Sewer District’s review.
- Floodplain determination. Signed by the floodplain administrator for the location; a structure in a flood zone also needs a Special Flood Hazard Area permit.
- Address and driveway. The County Engineer or municipality assigns addresses; on a state highway, the ODOT driveway permit comes first.
Logan County permit costs and fees
The Building Authority posts a three-part residential fee schedule (building, HVAC and electrical); the scanned sheets do not name an adopting resolution or date. Fees are additive, so each applicable line is paid, and every fee carries the 1% state surcharge. No commercial fee schedule is posted; ask the office.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Valuation basis | Living area $45 per sq ft; garages, sheds and decks $25 per sq ft |
| Application fee (each trade, non-refundable) | $40 |
| Plan review: new house / other projects / revisions | $100 / $50 / $25 |
| Building inspection fee | 0.045% of building valuation, as printed |
| Energy code review / certificate of occupancy / fireplace | $15 / $50 / $30 |
| Minimum fee: building / HVAC / electrical | $115 / $85 / $85 |
| HVAC: replacement system / new system | $45 (1 inspection) / $90 (2 inspections) |
| HVAC: gas piping, ductless, refrigeration, solid fuel | $45 each |
| Electrical: temporary, permanent or reconnected service | $45 each, plus $5 to $10 by service size |
| Electrical: rough-in and final combined | $90 |
| Re-inspection or requested inspection | $45 (per trade for re-inspections) |
| Permit extension | Half the original permit fee |
| Residential Appeals Board application | $200 |
Work started without a required permit is subject to double the applicable fee, capped at $200 on the schedule; the HVAC and electrical sheets exempt emergency work. Permits are valid for 12 months, and an approved plan lapses if work has not started within 12 months. The schedule prints the building inspection fee as 0.045% of valuation and does not show how it combines with the $115 minimum, so ask the office to price your plan. Plumbing, septic and well permits are charged separately on the Logan County Health District’s 2026 fee schedule.
Trade permits and who may pull them
Electrical and HVAC permits come from the Building Authority, each with its own application fee and minimum; plumbing permits come from the health district. Only the permit holder may request a scheduled inspection, and work must not be covered until the electrical or mechanical inspector approves it.
- Contractor registration. All contractors working within the Building Authority’s jurisdiction are encouraged to register. Specialty contractors pay $100 a year (the fee is waived for general contractors), for a calendar-year registration that is not prorated, with liability insurance of $100,000/$300,000 naming the Building Authority as certificate holder and workers’ compensation if they have employees. Subcontractors register separately.
- Commercial trades. Specialty contractors on commercial work must show a state license from the Ohio Construction Industry Licensing Board or the State Fire Marshal’s Bureau of Testing and Registration.
- Plumbing. Applications are dropped off or mailed to the health district at 310 South Main Street or emailed to its plumbing address, paid in full (card by phone adds 3%). A registered commercial plumbing contractor must do any work at a commercial property; check the property class on the County Auditor’s site.
- Plumbing inspections run Monday to Thursday, 8:00 a.m. to 3:30 p.m., and the health district must approve rough plumbing before the Building Authority’s framing inspection and final plumbing before the final.
Rather not deal with the Logan County building department?
Get a free quote →The Building Authority’s pages do not describe a homeowner rule for building, electrical or HVAC permits; ask the office before applying without a contractor.
How to apply for a Logan County building permit
Apply to the township, village or city zoning officer; keep a copy for the Building Authority.
File the health district’s building site review, or the Sewer District review near Indian Lake.
Have the municipal floodplain administrator or the Soil and Water Conservation District sign the form.
Detailed construction drawings, plus electrical and HVAC descriptions; stamped drawings for commercial work.
Upload the application and attachments in iWorQ; new homes must use the portal.
Pay the fees, then call 937-592-7473 for the first inspection.
Review, corrections and what causes delay
The Building Authority will not release a permit until it has the zoning permit, the health approval or sewer connection review and the floodplain determination. Plans must be clear and complete, signed on the first sheet by the person who prepared them, and each revision costs $25 to review. A new home submitted by email or paper after July 1, 2026 is returned. For a lot outside a recorded subdivision, the county’s brochure suggests checking zoning, floodplain, soils, sewage and driveway location before buying.
Inspections and certificates in Logan County
Inspections are scheduled only by phone at 937-592-7473; emailed requests are not processed. Inspectors work Monday to Friday from 8:00 a.m. to 3:00 p.m., need at least 24 hours’ notice, and take calls until 2:30 p.m. for the next day. A time preference is considered only for concrete pours.
The published inspection list covers footings (including post-hole footings), wall reinforcing, foundation before backfill, slabs, rough electric, rough HVAC, gas line pressure tests, rough fire suppression (200 pounds for 2 hours) and fire alarm, framing, insulation, electric service, fireplaces, pools (one inspection above ground, three in ground) and the finals. The final structure inspection comes before occupancy, after the trade finals and the health district’s final plumbing approval, and for a new home the blower door results must be on hand. A certificate of occupancy costs $50 on the residential schedule.
Want this handled start to finish?
Get a free quote →Ohio building code in Logan County
FEMA’s Community Status Book lists unincorporated Logan County (community 390772) as participating in the National Flood Insurance Program, with a current flood map dated November 30, 2023; the county’s floodplain regulations for unincorporated areas are Resolution 212-23.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Logan County permit search and official resources
The Building Authority runs its permit portal and a separate code portal on iWorQ; for an older permit or inspection record, call the office at 937-592-7473. Parcel numbers, needed on the floodplain form, come from the County Auditor’s real estate site. Plumbing, septic and well records are with the health district.
- Logan County Building Authority
- New home portal requirement, July 1, 2026
- Residential permit information
- Residential building, HVAC and electrical fees
- Will I need a permit?
- Required inspections
- Air leakage test policy
- Commercial permit information
- Contractor registration 2026
- Guidelines and contacts for building
- Floodplain determination form
- County floodplain administrator and Resolution 212-23
- Logan County Health District plumbing permits
- LUC Regional Planning, township zoning officers
- Ohio Board of Building Standards building department look-up
- FEMA Community Status Book, Ohio
Inspections are where schedules slip.
Get a free quote →Logan County building permit FAQs
Who issues building permits in Logan County?
The Logan County Building Authority, 1365 County Road 32 North, Bellefontaine (937-592-7473); plumbing permits come from the Logan County Health District.
Do I need a permit for a shed or fence?
Not for a one-story shed under 200 square feet or a fence of 6 feet or less, per the Building Authority’s sheet, but zoning rules may still apply.
Do I need a permit to replace my roof?
Not for a house re-roof with no structural repairs.
What must I have before applying?
A zoning permit, Health Department approval (or sewer review) and a floodplain determination.
Can I submit a new home application by email?
No. Since July 1, 2026 new home applications are accepted only through the online portal.
How do I schedule an inspection?
Call 937-592-7473 by 2:30 p.m. for the next day, with at least 24 hours’ notice; emailed requests are not processed.
Is a blower door test required?
Yes, for all new single-family and multi-family homes since January 2026, with results at the final inspection.
Simplify Logan County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Logan County sooner?
Let Alliance prepare, file, and track your Logan County permits while your crew stays on the job.
More Ohio permitting guides
Union County
Read guide →Shelby County
Read guide →Auglaize County
Read guide →Lorain Building Permit Guide
Read guide →Lorain County Building Permit Guide
Read guide →Loveland Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Logan County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.