Building work in Piqua needs two approvals from two governments. The city’s Planning and Zoning Division, part of the Community Services Department at 201 West Water Street (937-778-2049), issues the development (zoning) permit, and Piqua’s own Development Code sends every building, electrical and mechanical permit to the Miami County Department of Development, whose Building Regulations division is at 1506 One Stop Court in Troy (937-440-8121). A city zoning permit for a new house costs $150; the county then charges its building fee, for example $0.34 per square foot for a complete dwelling over 1,500 square feet.
What requires a building permit in Piqua?
Ohio law bars an owner from going ahead with the construction, erection, alteration or equipment of a building until the plans have been approved as the law requires. In Piqua that approval comes from Miami County Building Regulations, and the county’s own checklist says a permit is needed to build, enlarge, repair, alter, move or extend any building or structure; to add a deck any part of which is 30 inches or more above grade, or a roof over a deck at any height; for electrical wiring, plumbing, water or gas lines, furnaces and air conditioning; for signs and awnings; and for swimming pools. The same sheet lists general maintenance, roofs on structures under 200 square feet and telephone utility work as permit-free.
City development permit needed
- Building, rebuilding, extending or altering any building or structure
- Permanent fences and temporary or permanent pools
- Grading, excavation or fill, tree removal, clearing more than 2,500 square feet, or any work within 100 feet of a riparian area
- Adding 1,000 square feet or more of hard surface, or changing parking, access or circulation
- A change of use or occupancy in a non-residential building, and temporary uses
No city development permit
- Painting, and replacing shingles, siding or windows to match what is there, when the appearance does not change
- Certain temporary uses listed in the code
- Exempt work can still need county building review
The city’s code compliance page sums it up for homeowners: new fences, pools, sheds, garages, sidewalks, decks, driveways and extra parking all need a permit. Since October 2026 the county has said that a shingle tear-off and re-roof without structural repairs needs no county permit, though it must still meet the code; replacing rotted rafters or supports does.
What Piqua decides and what the state holds
The building codes themselves are state law, and only a department certified by the Ohio Board of Building Standards may approve plans. Piqua decides land use: its Development Code, adopted by Ordinance O-2-23 on April 18, 2023 and in force since May 18, 2023, is Title XV of the Codified Ordinances and covers zoning, site design, stormwater, subdivisions and historic review. The city also enforces the 2021 International Property Maintenance Code, registers contractors and rentals, and runs water, sewer and right-of-way permits.
Short on time to read all of this?
Get a free quote →Piqua building department: who handles permitting
Section 7.2.5 of the Development Code is blunt: the city’s development permit “does not include building permit review by Miami County”, and a separate application goes to the county for the building permit, including any mechanical, electrical or plumbing permits. The county’s jurisdiction list marks Piqua for both commercial and residential work, and its Chief Building Official is Rob England. Inside the city, Community Services Director Chad Henry heads the Planning and Zoning Division.
| Office | Details |
|---|---|
| Building, electrical and HVAC permits; inspections; certificates of occupancy | Miami County Department of Development, Building Regulations, 1506 One Stop Court, Suite 6, Troy, OH 45373; 937-440-8121 (option 1 for permits) |
| Development (zoning) permits, contractor registration, floodplain permits | Planning and Zoning Division, Community Services Department, 201 W Water Street, 2nd floor, Piqua, OH 45356; 937-778-2049; piquapermits@piquaoh.gov |
| Right-of-way, curb, water and sewer connections | Engineering Division, 201 W Water Street; 937-778-2044 |
| Plumbing inspections | Miami County Public Health, 937-573-3500, as the county building department lists it |
| Online filing | City: GovWell portal. County: Miami County iWorQ customer portal |
Piqua permit types
The city files its own permits in GovWell under residential, commercial, floodplain, change of use, change of occupancy, temporary use and contractor registration headings. Paper forms are still posted, and completed residential and commercial packets can be emailed to piquapermits@piquaoh.gov with payment through the city’s online payment link.
Residential permits
- City residential construction (zoning) permit: needed before you build, add to, move, alter or remodel any home structure, and for garages, porches, paving or new gravel. Send the application, a site plan and an elevation drawing.
- County residential approval: new dwellings, additions and alterations can be filed as one complete approval covering building, electrical, HVAC, gas piping, fireplaces, solar and the certificate of occupancy, or split into building/electrical and mechanical approvals. Accessory structures such as detached garages, decks, sheds and barns have their own approval type.
- One contact, one file: since June 17, 2024 the county wants one person to submit every plan for a home project as a single multipage PDF, in two main submittals (foundation, then the rest).
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
A city commercial development permit covers new buildings, additions, accessory structures, signs, site work and demolition, with a site plan, construction drawings and, where they apply, a landscape plan and elevations. County commercial review needs Ohio-certified drawings and, among other items, proof of zoning approval, a site plan and a site accessibility plan; submittals and resubmittals must come through the project’s original architect of record. A non-residential change of use or occupancy needs both a city permit and a county certificate.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Development permit first. The city encourages a pre-application meeting with the Development Director’s staff, then reviews the complete application internally; no public hearing is needed.
- Boards. The Planning Commission (plats, subdivisions, special uses, rezoning) meets at 6:00 p.m. on the second Tuesday of each month; the Board of Zoning Appeals (variances and appeals) at 6:00 p.m. on the fourth Tuesday, both in Commission Chambers at 201 West Water Street. Filing for the December 22, 2026 BZA meeting closes on November 25.
- Historic district. Work in the Piqua Historical District or on a landmark needs a certificate of appropriateness from the City Historic Review Commission; its December 28, 2026 meeting also has a November 25 deadline.
- Floodplain. Any activity in the 100-year floodplain is reviewed by the City Planner through a $75 floodplain permit. Separately, any use of land the Miami Conservancy District owns or controls along the Great Miami River needs the District’s prior approval.
- Stormwater and sewer. Sites disturbing an acre or more need a stormwater management plan, and the City Engineer can ask for one on smaller sites. A failed or worn-out septic system may not be rebuilt; the property must connect to the Piqua sewer instead.
Piqua permit costs and fees
A Piqua project usually pays two sets of fees. City fees are printed on the development permit applications. County building fees come from Miami County’s residential schedule (effective March 17, 2023) and its commercial schedule (page one marked effective July 21, 2026), which covers Miami, Mercer, Shelby and Auglaize counties. The county adds 1% to residential and 3% to commercial fees for the state Board of Building Standards.
| Work | Fee |
|---|---|
| City residential zoning permit: new home / accessory structure or addition / fence | $150 / $50 / $25 |
| City commercial development permit: new building or site redevelopment / accessory or addition | $300 / $100 |
| City floodplain permit | $75 |
| County complete dwelling, addition or alteration (building, electrical, HVAC, plan review, certificate) | $300 up to 500 sq ft; $500 for 501–1,500 sq ft; $0.34 per sq ft over 1,500 sq ft |
| County accessory structure with electrical or HVAC | $300 up to 1,000 sq ft; $550 to 3,000 sq ft; $700 above |
| County furnace or air conditioner / both | $100 / $150 |
| County in-ground pool / above-ground pool or hot tub | $300 / $150 |
| County residential re-inspection or missed inspection | $150 each |
| County commercial structural | $302.50 processing plus $11.55 per 100 sq ft; plan review $140 per hour |
| County commercial electrical or mechanical | $302.50 processing plus $7.15 per 100 sq ft each |
| Residential work without approval / commercial work before a permit | $300 / permit fees doubled, up to $4,000, plus 3% |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedules: a new 2,000-square-foot house filed as a complete approval costs 2,000 × $0.34, or $680, plus 1% ($6.80) for the state, and the city’s $150 zoning permit comes on top. County fees are due when the permit is issued, not when you apply; the county takes cash, check or card, with a 2.65% charge on card payments.
Trade permits and who may pull them
Electrical and mechanical permits in Piqua are county approvals, filed through the same iWorQ portal as the building work; a new or changed electrical service needs a drawing reviewed before the service permit is issued. The county issues a permit to the owner or the owner’s agent, such as the contractor or another person responsible for the work.
- City contractor registration. Piqua requires contractors working in the city to register through GovWell or on paper at the Community Services window: a completed application, a $3,000 surety bond, a certificate of insurance naming the City of Piqua, and an Ohio contractor license for commercial work. The fee is $100 for each master and $25 for each journeyman.
- State licenses. Commercial electrical, HVAC, plumbing, hydronics and refrigeration contractors need an Ohio Construction Industry Licensing Board license; Ohio has no state license for general or residential contractors.
- Plumbing. The county’s inspection list says rough and final plumbing must be approved by the Health Department before the county’s framing and final inspections; call Miami County Public Health at 937-573-3500.
- Fire protection. Sprinkler, alarm and hood suppression systems are commercial county permits; the county posts a list of fire department plan review contacts.
Rather not deal with the building department?
Get a free quote →How to apply for a Piqua building permit
Call 937-778-2049 or ask for a pre-application meeting to confirm the zoning district, setbacks and any historic or floodplain review.
Apply in GovWell or email the residential or commercial application, site plan and drawings to piquapermits@piquaoh.gov, and pay the city fee.
Each contractor registers with the city, with bond and insurance, before work starts.
Upload the county application and plans in the iWorQ portal; a home project goes in as one multipage PDF from one contact.
The county emails a payment link after approval and then returns the stamped drawings.
Driveway aprons, sidewalks, curb cuts and utility taps need Engineering Division permits.
Review, corrections and what causes delay
The county reviews most residential applications in 3 to 5 business days and commercial plans in roughly 14 to 21 days, depending on size and season; a footing and foundation permit can be processed in 1 to 3 days. City engineering permits usually get a status notice within 3 to 5 business days. A home submittal that is not one multipage PDF, or each extra submittal after the two allowed, costs $100 plus the 1% state fee, and rejected plans do not count toward the limit. Start no work until the permit is paid and issued; an emergency furnace or central air replacement may go ahead if the application is filed at once.
Inspections and certificates in Piqua
County inspectors inspect Piqua jobs, and requests go through the iWorQ portal at least 24 hours ahead. Each project gets its own list of required inspections, typically footings, slabs, post holes, framing with rough electric and HVAC, insulation, the electric service and the finals. One inspection per phase is free; a re-inspection, a missed inspection or a visit with no access, no visible address or no approved drawings on site costs $150 on a residential job.
A certificate of occupancy follows once every inspection, including plumbing and fire department sign-offs, is approved. A temporary certificate may be granted by the Chief Building Official when the work is safe to occupy, and the county reminds owners that a zoning certificate is not a building certificate of occupancy. County decisions can be appealed: the county runs a residential appeals board and the Board of Building Standards hears commercial appeals.
Ohio building code in Piqua
Piqua’s Development Code adopts the Ohio codes by reference and names the Miami County Department of Development as the office that administers them. FEMA’s Community Status Book lists the City of Piqua (community 390400) as participating in the National Flood Insurance Program, with flood maps effective June 5, 2020, and the city’s floodplain permit applies inside the mapped 100-year floodplain.
Want this handled start to finish?
Get a free quote →Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Piqua permit search and official resources
Status of a city permit shows in your GovWell account, and county permits, invoices and inspections show in the Miami County portal. For older city files, use the City of Piqua Non-Police Record Request; the city provides records during business hours, 8 a.m. to 4 p.m., Monday to Friday. Building permit records sit with the county department, which posts monthly permit reports for the counties it serves.
- City of Piqua permits and applications
- Piqua GovWell permit portal
- Planning and Zoning Division
- Contractor registration program
- Development Code and property maintenance code
- Residential construction zoning permit application
- Commercial development permit application
- Floodplain permit application
- Engineering permits: when a permit is required
- Public records requests
- Miami County Building Regulations
- Miami County areas of jurisdiction
- Miami County residential permit fees
- Miami County commercial permit fees, page 1 (July 21, 2026)
- Miami County required inspections list
- Miami Conservancy District permits
- Ohio Board of Building Standards
Inspections are where schedules slip.
Get a free quote →Piqua building permit FAQs
Does the City of Piqua issue building permits?
No. Piqua issues development (zoning) permits; building, electrical and mechanical permits come from Miami County Building Regulations in Troy, as the city’s Development Code states.
How much is a zoning permit for a new house in Piqua?
$150 for a new home, $50 for an accessory structure or addition, and $25 for a fence, paid to the city before the county building permit.
Do contractors have to register with Piqua?
Yes. Contractors working in the city register with Community Services, with a $3,000 surety bond and insurance naming the city; the fee is $100 per master and $25 per journeyman.
Do I need a permit for a fence or shed in Piqua?
Yes, the city requires a permit for new fences and sheds. The county building permit applies to structures in its checklist, and its accessory fees start at $200.
Is a permit needed to replace a roof?
Not from the county for a shingle tear-off and re-roof without structural repairs, under its October 7, 2026 policy; structural repairs need a permit.
How long does county plan review take?
Most residential applications take 3 to 5 business days and commercial plans about 14 to 21 days.
Who inspects plumbing in Piqua?
The Health Department must approve rough and final plumbing; the county lists Miami County Public Health at 937-573-3500.
Simplify Piqua permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Piqua sooner?
Let Alliance prepare, file, and track your Piqua permits while your crew stays on the job.
More Ohio permitting guides
Miami County
Read guide →Troy
Read guide →Montgomery County
Read guide →Portage County Building Permit Guide
Read guide →Portsmouth Building Permit Guide
Read guide →Powell Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Piqua permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.