Holmes County’s list of county departments includes no building department and names the Planning Commission (2 Court Street, Suite 21, Millersburg, 330-674-8625) as the office for zoning and building code information, subdivisions and floodplain management. On unincorporated land the county’s own permits are the floodplain development permit, County Engineer driveway, address and right-of-way permits, and Holmes County General Health District permits for septic systems ($225 site review, $300 permit to install) and wells. Use the state building-department look-up to see which certified department, if any, covers your address for each type of work.
What requires a building permit in Holmes County?
Ohio’s codes require approved plans before a building is built, altered or equipped, and those plans are approved by a department the Board of Building Standards has certified or, for nonresidential plans where none has authority, by the state. The permits Holmes County and its agencies publish are below.
County-level permits
- Floodplain development permit for any building, addition, fill, grading, mining, storage, bridge or watercourse change in an identified flood hazard area
- Driveway access and address number for a new home on a county, township or private road
- Right-of-way permit for driveway work, sidewalk repairs, mailbox posts or utility digging in a county road right-of-way
- Sewage treatment system and private water system permits from the health district
- Erosion and sediment control permit for lots in a county subdivision
Inside the villages
- Millersburg requires prior village approval for any construction, alteration or modification of buildings or lots inside its limits
- Design review in Millersburg’s historic district, under the village’s design guidelines
- Each other village sets its own zoning rules; ask its office before work starts
Where no department certified for residential work has authority, Ohio law does not require plans to be submitted for a house (ORC 3791.04(A)(1)); nonresidential plans then go to the state. That rule is about building plans only: the floodplain, septic, well, driveway and village approvals above still apply.
What Holmes County decides and what the state holds
The county commissioners adopted the Special Purpose Flood Damage Reduction Resolution on September 29, 2008, under the county’s authority in ORC 307.37 and 307.85, and named the Director of County Planning as Floodplain Administrator. The county also sets subdivision regulations, and the County Engineer controls access to county roads. The building code itself is statewide, so neither the county nor a village may write its own technical rules for houses.
Holmes County building department: who handles permitting
The answer depends on the address and on the type of work. The Board of Building Standards certifies building departments separately for residential and nonresidential code, and its look-up map shows which department, if any, holds authority over a parcel. On the county’s own site the office that answers building code questions is the Planning Commission and Office of Community Development, led by Director Arnie Oliver.
Short on time to read all of this?
Get a free quote →Commercial and other Ohio Building Code work has a certified department: the East Central Ohio Building Authority (ECOBA), 339 Oxford Street, Dover (Holmes County line 330-674-1131). ECOBA says a Holmes County commissioners’ resolution effective September 20, 2004 gave it authority to enforce the Ohio Building Code in the county, and its 2024 policy covers all of Holmes County except the villages of Glenmont, Holmesville, Killbuck and Nashville, where the state’s Division of Industrial Compliance (614-644-2622) enforces it. Its Holmes County page lists the townships and Millersburg, both from September 6, 2005. Plumbing stays with the state throughout the county.
| Office | Contact |
|---|---|
| Planning Commission (zoning and building code information, subdivisions, floodplain) | 2 Court St., Suite 21, Millersburg, OH 44654; 330-674-8625; fax 330-674-1582; 8:30 a.m. to 4:30 p.m., Monday to Friday |
| Holmes County General Health District (septic systems, wells) | 2600 Glen Drive, Millersburg; 330-674-5035; Environmental Health 330-674-8422; 8:30 a.m. to 4:30 p.m., Monday to Friday |
| Holmes County Engineer (driveways, addresses, right-of-way) | 330-674-1856; County Engineer Christopher R. Young, P.E., P.S. |
| Holmes Soil & Water Conservation District (erosion control) | 62 West Clinton Street, Millersburg; 330-674-2811 |
| ODOT (access to a state route) | 330-674-1906 |
Villages and townships
Holmes County has 14 townships and seven villages. Millersburg, the county seat with 3,295 residents in the Census Bureau’s 2025 estimate, runs a Planning and Zoning Commission and a zoning inspector from Village Hall at 6 North Washington Street (330-674-1886, 8 a.m. to 4:30 p.m.). Glenmont, Holmesville, Killbuck and Nashville lie wholly in the county; only small parts of Baltic and Loudonville do. For every village, ask the village office who reviews building work and confirm the certified department on the state look-up.
Holmes County permit types
Because the county issues no building permit of its own, a typical Holmes County project collects several separate approvals from different offices, and the septic site review often decides where on the lot a house can go.
Residential permits
- Sewage treatment system. A certified soil scientist or soil classifier evaluates the site, a system designer prepares the plan, and the owner files a site review application with both documents. After approval a registered installer needs a permit to install before construction of the system begins.
- Private water system. Wells, cisterns, springs and ponds used for drinking water need a health district permit before they are installed or altered; the owner or the registered contractor can apply, and directions to the property must be included.
- Driveway and address. A new home on a county, township or private road needs the Engineer’s driveway access and address number application; a new access onto a state route needs an ODOT access permit submitted with that application.
- Floodplain. Homes, additions, manufactured homes and accessory buildings in a mapped flood hazard area need a development permit from the Floodplain Administrator.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Nonresidential buildings follow the Ohio Building Code, and plan approval must come from a certified department or, where none has authority, from the state. Small commercial sites that cannot reach a sewer use a small flow on-site sewage treatment system, which the health district permits only with a plan from a qualified system designer. Commercial work in a flood hazard area is reviewed under the same 2008 resolution as homes.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Lot creation. New lots go through the county Subdivision Regulations and the Planning Commission, which meets at 3:00 p.m. on the second Wednesday of each month in the Old Jail building.
- Erosion control. The Soil & Water Conservation District requires an erosion and sedimentation control agreement for subdivision lots under Section 9.04 of the Subdivision Regulations; larger sites file a stormwater pollution prevention plan, and Ohio EPA permitting applies when one acre or more is disturbed.
- Village approvals. Inside Millersburg, prior village approval and, in the historic district, design review come first.
- Flood map check. The county GIS viewer shows parcels; the Floodplain Administrator confirms whether a site is in a special flood hazard area.
Holmes County permit costs and fees
No county building fee schedule is published, because the county lists no building department. The fees that are posted belong to the health district and the Soil & Water Conservation District. For a building or trade permit, the fee comes from whichever certified department or state office approves the plans.
| Item | Fee |
|---|---|
| Sewage treatment system site review (application, soil evaluation and design plan) | $225 |
| Permit to install a sewage treatment system | $300 |
| Private water system application made after the work is done | $30 late fee added (not for emergencies) |
| Erosion control permit, subdivision lot disturbing not more than one acre | $10 |
| Erosion control permit, three or more lots or more than one acre (with stormwater plan) | $50 |
| Board of Building Standards assessment on certified-department fees | 3% nonresidential; 1% residential |
Rather talk it over?
Call 1-855-478-4290 →The health district reviews a septic site within seven business days of receiving a complete package, and longer if problems are found; it then writes to the owner approving or disapproving the design or asking for more information. Ask the Planning Commission and the Engineer’s office about any fee for the floodplain, driveway and right-of-way permits when you apply.
Trade permits and who may pull them in Holmes County
Electrical, plumbing and mechanical permits are issued by the certified department that approves the building work, or by the state for nonresidential work where no local department has authority. Ask that office which trade permits your job needs before rough-in starts.
- Commercial trade licenses. Electrical, HVAC, hydronics, plumbing and refrigeration contractors on commercial work need a license from the Ohio Construction Industry Licensing Board.
- Septic installers. The health district registers sewage treatment system installers every year; registered installers must pass an exam on the state sewage code, complete continuing education and carry bonding and liability insurance. Only a registered installer may install, replace or alter a system.
- Well contractors. Private water system contractors register through the State of Ohio, and a registered contractor may obtain the well permit for the owner.
- Designers and soil professionals. The health district posts lists of certified soil scientists or classifiers and sewage system designers; a small flow system must have a plan from a qualified designer.
No county contractor registration appears among Holmes County’s offices. A village may register contractors under its own ordinances, so ask the village office before work inside village limits.
How to apply for permits in Holmes County
Open the Board of Building Standards look-up for the parcel and note whether a certified department covers residential or commercial work there; then call the Planning Commission at 330-674-8625 with any questions.
Ask the Floodplain Administrator whether the site is in a special flood hazard area, and contact the village office if the parcel is inside a village.
Hire a certified soil scientist or classifier, give the evaluation to a system designer, and file the site review application with the $225 fee.
Submit the Engineer’s driveway access and address application; for a state route, include the approved ODOT access permit.
Submit the development permit application with scaled site plans and elevations where the site is mapped, and the Soil & Water erosion control form for subdivision lots.
Submit building plans to the certified department or state office that has authority, and get the well permit and septic permit to install before those systems are built.
Rather not deal with the Holmes County building department?
Get a free quote →Review, corrections and what causes delay
The septic site review is the step most likely to change a plan: the review letter can approve, disapprove or ask for more information, and soils may limit where the house can go. Floodplain applications stall when site plans lack elevations or the cost and market-value figures needed for the substantial-improvement test. A floodplain permit is void if work has not begun within 180 days and is valid for one year.
Inspections in Holmes County
Each agency inspects its own permit. The Soil & Water Conservation District may visit sites under the erosion control agreement, and the Floodplain Administrator can require scaled site plans with ground and floor elevations. Building, electrical and mechanical inspections are booked with the certified department or state office that approved the plans, which also issues the certificate of occupancy.
- Septic: the health district inspects new, replacement and altered systems and the permit to install and fee must be in place before construction of the system starts.
- Wells: new private water systems are inspected and sampled; the health district may also take samples from existing supplies.
- Sale of a home: Holmes County does not currently require a private water system inspection before a home is sold, though the health district recommends one.
- Floodplain: a structure substantially improved (work equal to 50% or more of its market value) must meet the flood protection standards; for homes and manufactured homes that means the lowest floor, including any basement, at or above the flood protection elevation.
Ohio building code in Holmes County
The county’s flood rules set a flood protection elevation of the base flood elevation plus one foot of freeboard, and new or substantially improved homes, including manufactured homes, must have the lowest floor, basement included, at or above that level. FEMA’s Community Status Book lists unincorporated Holmes County (community 390276) as participating in the National Flood Insurance Program, with current flood maps effective October 18, 2011; villages participate separately.
Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Want this handled start to finish?
Get a free quote →Holmes County permit search and official resources
Permit records sit with the office that issued them. Septic and well records are kept by the Holmes County General Health District; floodplain and subdivision files by the Planning Commission; driveway, address and right-of-way permits by the County Engineer. The county’s Property Record Search, Property Transfer History and GIS map show parcel details, and the commissioners post their meeting minutes online by date. For records held by a certified building department or the state, ask that office.
- Holmes County Planning Commission overview
- Planning Commission document library (floodplain, subdivision forms)
- Special Purpose Flood Damage Reduction Resolution, adopted September 29, 2008
- Special Flood Hazard Area Development Permit Application
- Holmes County Subdivision Regulations
- Holmes County General Health District: sewage treatment systems
- Holmes County General Health District: private water systems
- Holmes County Engineer: permits and applications
- Holmes SWCD erosion and sedimentation control permit
- Village of Millersburg Planning and Zoning Commission
- Holmes County GIS map viewer
- Holmes County commissioners’ meeting minutes
- Ohio Board of Building Standards — Certified Building Departments
- Ohio Board of Building Standards
Inspections are where schedules slip.
Get a free quote →Holmes County building permit FAQs
Does Holmes County have a building department?
No county building department appears in the county’s list of offices. The Planning Commission (330-674-8625) answers zoning and building code questions, and the state look-up shows which certified department, if any, covers an address.
Do I need a permit to build a house in rural Holmes County?
Ohio does not require house plans to be submitted where no certified residential department has authority, but a new home still needs health district septic and well permits, the Engineer’s driveway and address number, and a floodplain permit if the site is mapped.
How much does a septic permit cost?
The health district charges $225 for the site review and $300 for the permit to install, and the review starts only with a soil evaluation and a system design.
Who handles floodplain permits?
The Director of County Planning is the Floodplain Administrator under the September 29, 2008 resolution; the county’s unincorporated area takes part in the National Flood Insurance Program.
Where do I get a driveway permit?
From the County Engineer for county, township and private roads (330-674-1856), and from ODOT (330-674-1906) for new access onto a state route.
What about building in Millersburg?
The village requires prior approval for any construction, alteration or modification of buildings or lots; its Planning and Zoning Commission and Design Review Board meet on the first Wednesday of each month.
Who approves commercial building plans?
ECOBA in Dover (330-674-1131) reviews Ohio Building Code plans everywhere in the county except Glenmont, Holmesville, Killbuck and Nashville, where the state does; plumbing plans go to the state.
Simplify Holmes County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Holmes County sooner?
Let Alliance prepare, file, and track your Holmes County permits while your crew stays on the job.
More Ohio permitting guides
Coshocton County
Read guide →Wayne County
Read guide →Tuscarawas County
Read guide →Hudson Building Permit Guide
Read guide →Huron County Building Permit Guide
Read guide →Ironton Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Holmes County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.