A building project in Hudson goes through two offices. The city’s Community Development Department at 1140 Terex Road (330-342-1790) issues the zoning permit and, for many projects, routes it through the Architectural and Historic Board of Review; the Summit County Division of Building Standards at 1030 East Tallmadge Avenue in Akron (330-630-7280) then reviews the plans, issues the building permit and inspects the work. Hudson’s Land Development Code requires the city’s zoning certificate before the county issues a building permit for a house.
What requires a building permit in Hudson?
Hudson’s rule for residential land is broad: any alteration to an existing structure, or any new structure on a parcel in a residentially zoned district, needs a zoning permit from the city. The city then notes that most projects also need Summit County Building Department approval before work starts. The city’s application list shows what it reviews:
- Additions, decks, porches and new houses
- Accessory structures such as sheds, gazebos, pavilions, pergolas, outdoor fireplaces and fire pits, seating walls and retaining walls
- Exterior alterations, including windows, entry doors, siding and a change of roofing material (replacing asphalt shingles alone is not on this list)
- Fences, pools and spas, solar panels, driveway extensions and patios, and grading and drainage work
- Demolition of any structure in a residential district, and home occupations
On the county side, Summit County Building Standards does not require a permit for a shed of 200 square feet or less, and a residential fence needs a county permit only when it is taller than 6 feet; commercial fences always need one. A shed or fence that needs no county permit can still need Hudson’s zoning permit.
What Hudson decides and what the state holds
The building code itself is the state’s, enforced in Hudson by the county department. Hudson controls land use through its Land Development Code, updated in January 2026: zoning districts, design review by the Architectural and Historic Board of Review, the historic district, floodplain permits, a growth management allocation system Council can switch on, and its own right-of-way and grading rules.
Hudson building department: who handles permitting
The Summit County Division of Building Standards provides plan review and inspection for Hudson; its services booklet lists Hudson among the cities it serves, and its plans examiners and building, electrical, plumbing and fire inspectors cover residential and commercial work. The city’s Community Development Department handles residential and commercial zoning permits, code enforcement and the city’s boards, and the Engineering Department handles right-of-way permits.
Short on time to read all of this?
Get a free quote →| Office | Details |
|---|---|
| Summit County Building Standards (building permits and inspections) | 1030 East Tallmadge Avenue, Akron, OH 44310; 330-630-7280; office Monday to Friday 7:30 a.m. to 4:00 p.m., inspections and application drop-off 8:00 a.m. to 3:00 p.m.; GovWell portal for new permit and inspection requests |
| Hudson Community Development (zoning permits) | 1140 Terex Road, Hudson, OH 44236; 330-342-1790; Monday to Friday 7:30 a.m. to 4:00 p.m.; Viewpoint portal for zoning applications and status |
| Hudson Engineering (right-of-way) | 330-342-1770; right-of-way permits and inspections |
| Hudson Public Power | Reviews solar applications with Community Development in its service area |
The county moved its online permit and inspection services to GovWell from Monday, September 28, and keeps the old CityWorks portal only for requests made before then. Use the Board of Building Standards look-up map to confirm the department for an address near the city line.
Hudson permit types
Zoning applications are filed on Hudson’s Viewpoint portal, one application type per project, and Community Development tells you at review whether the Architectural and Historic Board of Review (AHBR) or the Board of Zoning and Building Appeals must approve it. The building, electrical, mechanical and plumbing permits are then filed with the county through GovWell.
Residential permits
- New houses. A zoning certificate for a new house needs AHBR design approval, plus a residential allocation if Council has put the growth management system into effect, before the county can issue the building permit.
- Historic District and landmarks. Accessory structures, additions, alterations, decks, demolitions, fences, roof shingle replacement and other exterior work in the Historic District or at a Historic Landmark use the Historic District application; a representative should attend the AHBR meeting, and the zoning certificate follows one to two business days after approval.
- Demolition. Removing a structure more than 50 years old puts the application on an AHBR agenda.
- Driveways. Widening a driveway or adding a patio needs the extension application and a right-of-way permit for the apron; replacing a driveway in kind needs only the right-of-way permit.
- Solar. One application covers the city’s reviews, and inside the Hudson Public Power service area it generates the solar interconnection agreement.
- Other uses. Home occupations, RV and trailer parking and green-certified home registration each have their own application.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial and nonresidential zoning permits are reviewed by the city’s associate planners and City Planner. Additions under 2,000 square feet use their own application; an addition over 2,000 square feet (or 20% of the existing building) or a new building goes to the Planning Commission. A new business or a change of occupancy needs a Change of Use Certificate, which confirms the use is allowed in the district and lets the Fire Department inspect. Permanent signs, temporary signs and outdoor dining on a sidewalk have separate applications, and new businesses can ask the Economic Development Manager for a New Business Checklist.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning certificate. Issued within seven days after final action and approval; for minor and basic development it lapses if construction is not completed within 12 months (24 months for major development), and the City Manager may extend it by up to six months if asked before it expires.
- Design review. Community Development decides at review whether a project needs the AHBR; the city describes the board as reviewing zoning certificate applications other than industrial buildings in industrial zones, which the Planning Commission reviews.
- Floodplain. Work in a mapped floodplain may need a floodplain development permit, decided within 30 days of a complete application.
- Pre-application meeting. An applicant can request a conceptual review with city staff, which may include Summit County’s Department of Environmental Services and the Summit Soil and Water Conservation District.
- Right-of-way. Work in the street, including driveway aprons, needs an Engineering right-of-way permit and a $10,000 bond on file.
- Septic systems and wells. Where no sanitary sewer is available, Summit County Public Health requires a site and soil evaluation before a new house, a replacement system or two or more added bedrooms, then permits and inspects the sewage treatment system, which a registered STS contractor must install; drilling, altering or sealing a well also needs its permit. Its Environmental Health office is at 1867 West Market Street, Akron (Building C), 330-926-5600.
- Address. Summit County Public Health tells owners of Hudson parcels to get a new address from the city itself.
Hudson permit costs and fees
A Hudson project pays two sets of fees. The building, trade and plan review fees are Summit County’s, set in the Summit County Building Code, and the county adds the Board of Building Standards assessment (3% of nonresidential fees and 1% of residential fees, as state law sets it). The zoning, design review, board and right-of-way fees are the city’s, charged under the fees established by City Council; the city keeps a fee schedule page under Applications and Permits, and Community Development will quote the fee for each application.
Rather talk it over?
Call 1-855-478-4290 →| Fee | Who sets it and how |
|---|---|
| Building, electrical, mechanical and plumbing permits | Summit County Building Standards, under the Summit County Building Code |
| State assessment | Added to county permit fees: 3% nonresidential, 1% residential |
| Zoning certificates, AHBR, Planning Commission and BZBA applications | City of Hudson, under the fee schedule established by City Council |
| Right-of-way permits | City of Hudson Engineering; contractors keep a $10,000 bond on file |
| Contractor registration | None in Hudson; Summit County ended its $145 annual registration fee and $10,000 bond in March 2024 |
| Payment at the county | Cash or check at the office (no cash after 3:00 p.m.), by mail, or check or card through the portal; no payments by phone |
When the county revised its building code in March 2024, commercial application fees rose by $10, while the annual contractor fee and bond were dropped. Ask both offices for their current figures before you budget: the city’s schedule and the county’s code are separate documents.
Trade permits and who may pull them
Summit County Building Standards issues the electrical, mechanical and plumbing permits in Hudson and sends its own electrical, plumbing and fire inspectors. Hudson itself does not register contractors, although every contractor must pull the permits the job needs, and right-of-way work needs the city permit and bond.
At the county, registration is per permit: each application carries a certificate of insurance naming Summit County Building Standards, 1030 East Tallmadge Avenue, as certificate holder, a federal ID number and any state license the work requires. Commercial electrical, HVAC, plumbing, hydronics and refrigeration contractors need the OCILB license. A homeowner may pull a county permit for work on a home in their own name, except gas lines, with a signed and notarized Homeowners Affidavit, and the county asks owners to call its electrical clerk first. Owners working on homes they do not or will not occupy must have a qualified contractor responsible for the installations.
Rather not deal with the building department?
Get a free quote →How to apply for a Hudson building permit
Find the matching residential or commercial zoning application on Hudson’s Viewpoint portal; use the Historic District form for landmark or district properties.
If the project needs AHBR, Board of Zoning and Building Appeals or Planning Commission approval, Community Development schedules it.
The certificate is issued within seven days after final approval.
Submit the building and trade permit requests through the county’s GovWell portal, with the insurance certificate or a homeowner affidavit.
Apply to Hudson Engineering for street and apron work, and file a floodplain development permit where the lot is mapped.
City zoning fees go to Hudson; building permit fees go to the county.
Review, corrections and what causes delay
The county says a permit typically takes a couple of days when all the paperwork is in, but it will not issue construction permits until zoning approval is in place, so get Hudson’s zoning certificate moving first. AHBR and Planning Commission schedules add time, and a growth management allocation can be a condition for a new house in a year Council implements the system. You may submit plans to the county while the city reviews zoning.
Inspections and certificates in Hudson
Summit County Building Standards inspects the building, electrical, plumbing and mechanical work it permits. Requests go through the GovWell portal at any time, and the county can do some inspections by video call; it also issues certificates of occupancy after its occupancy inspections.
Hudson runs its own inspections for right-of-way work and the new house pre-construction inspection, booked through the city’s online scheduling tool at least 24 hours before the work is ready, with the contractor on site. Questions about right-of-way inspections go to Engineering at 330-342-1770; pre-construction questions go to Community Development at 330-342-1790. After floodplain construction, the owner supplies as-built certifications such as a FEMA Elevation Certificate.
Ohio building code in Hudson
Summit County Building Standards, which lists Hudson among the communities it serves, enforces the statewide codes in the city. FEMA’s Community Status Book lists the City of Hudson (community 390660) as participating in the National Flood Insurance Program, with a current flood map dated April 19, 2016, and floodplain development permits come from the city.
Want this handled start to finish?
Get a free quote →Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works
Hudson permit search and official resources
Zoning permit status is shown on Hudson’s Viewpoint portal. Building permits are public records at the county: search them in the GovWell portal, which covers permits from October 2026, or use the county’s records request form for older files, including the separate process for records from before 2021.
- Hudson applications and permits
- Residential zoning permits
- Commercial and nonresidential permits
- Hudson Viewpoint permit portal
- Contractor registration and right-of-way bond
- Online right-of-way and pre-construction inspection scheduling
- Hudson Land Development Code (January 2026)
- Hudson boards and commissions
- Summit County Building Standards
- Summit County GovWell portal
- Summit County Building Standards records request
- BBS building department look-up
- Ohio Construction Industry Licensing Board
Inspections are where schedules slip.
Get a free quote →Hudson building permit FAQs
Who issues building permits in Hudson?
Summit County Building Standards in Akron issues building and trade permits; the City of Hudson issues the zoning permit that must come first.
Do I need a permit for a shed in Hudson?
A Hudson zoning permit, yes; a county building permit only if the shed is larger than 200 square feet.
Do I need a permit for a fence?
Hudson requires a fence zoning application, and the county requires a building permit for a residential fence over 6 feet.
Do contractors register with Hudson?
No. Contractors pull the permits each job needs, and right-of-way work needs a $10,000 bond on file with the city.
Can a homeowner pull a permit?
Yes, at the county, for a home in the owner’s name except gas lines, with a notarized Homeowners Affidavit.
Does a new roof need a permit?
Hudson’s zoning list leaves out plain asphalt shingle replacement outside the Historic District but includes a change of roofing material; shingle work in the Historic District goes to the AHBR, and the county can say whether the job needs a building permit.
How do I find an old permit?
Ask the county through its records request process; Hudson’s portal shows zoning permits.
Who permits a septic system in Hudson?
Summit County Public Health, after a site and soil evaluation; a system cannot be installed where sanitary sewer is available.
Simplify Hudson permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Hudson sooner?
Let Alliance prepare, file, and track your Hudson permits while your crew stays on the job.
More Ohio permitting guides
Summit County
Read guide →Stow
Read guide →Twinsburg
Read guide →Huron County Building Permit Guide
Read guide →Ironton Building Permit Guide
Read guide →Jackson County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Hudson permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.