Hocking County, Ohio Building Permit Guide

To get a building permit in Hocking County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Outside Logan, the Hocking County Health Department issues a $55 building placement permit for a new or replacement home, plus plumbing, septic and well permits; commercial buildings, cabin rentals and manufactured homes go to the state’s Industrial Compliance Division.

Authority: Hocking County Health DepartmentCommercial: Ohio Industrial CompliancePhone: 740-385-3030 ext. 2
Home placement permit
$55Health Department, outside Logan
Commercial and cabins
State permitIndustrial Compliance, 800-523-3581
New septic system
$662Under 500 gallons a day
Floodplain
Regional Planning93 W. Hunter St., 740-380-9634

Hocking County has no county building department. Outside the City of Logan and licensed manufactured home parks, the Hocking County Health Department in Logan issues a building placement permit, $55 under its 2026 fees, before anyone builds or replaces a home, and it also permits all residential and commercial plumbing, septic systems and wells. The Health Department sends manufactured homes and every commercial building, including transient cabin rentals, to the Industrial Compliance Division of the Ohio Department of Commerce for a building permit. The county Regional Planning Office handles lot splits and floodplain determinations, and the County Engineer issues driveway permits on county roads.

What requires a building permit in Hocking County?

In the townships and villages outside Logan, the permit that comes closest to a building permit for a house is the Health Department’s building placement permit, needed both to build a new home and to replace one, before construction starts. The Regional Planning Office’s own guidance adds that new construction, including remodeling, needs Health Department plan review and permits for plumbing, on-site sewage and water systems, and a floodplain determination from Regional Planning.

Homes outside Logan

  • Building placement permit for a new or replacement home
  • Plumbing permit for new construction, additions or replaced plumbing in a building or room
  • Plumbing permit for a water treatment or conditioning unit, and for placing a manufactured home
  • Sewage treatment system permit, or an inspection of the existing system when replacing a home
  • Private water system (well or pond) permit
  • Floodplain determination and, in the flood area, a floodplain permit
  • Driveway permit from the road authority

No Health Department plumbing permit

  • Minor plumbing repairs
  • Replacing a plumbing fixture

Commercial buildings of every kind, including transient or cabin rentals, and manufactured homes need a building permit from the state’s Industrial Compliance Division (800-523-3581), according to the Health Department. Inside Logan, the Health Department’s placement permit does not apply; ask the city about its own permits.

What the county decides and what the state holds

Building codes and the plan approval for commercial buildings outside a certified department rest with the state. Locally, the Board of Health set the 2026 fees on December 8, 2025 and enforces Plumbing Regulation #5 of the Logan-Hocking County Health District; the county enforces subdivision regulations from 1978 (amended 2000) and flood plain regulations adopted in 2012; and the Board of Commissioners has a county rural zoning commission under ORC 303.04, although the Regional Planning FAQ says zoning is currently in place only in the City of Logan. A draft short-term rental regulation (Draft 9.0, posted October 2026) is under review and has not been adopted.

Short on time to read all of this?

Get a free quote →

Hocking County building department: who handles permitting

For a house outside Logan, the Health Department’s Environmental Division issues the building placement permit after a sanitarian’s site evaluation, and its Plumbing Division permits and inspects the plumbing. For commercial buildings, cabin rentals and manufactured homes, the building permit is the state’s. The other county offices handle land and roads.

Hocking County permit offices
OfficeRole and contact
Hocking County Health Department, Environmental HealthBuilding placement permits, plumbing, septic, wells, lot split approvals; 350 State Route 664 North, Logan, OH 43138; 740-385-3030 ext. 2; Monday to Friday, 8:00 a.m. to 4:00 p.m.
Ohio Department of Commerce, Industrial Compliance DivisionBuilding permits for commercial buildings, transient and cabin rentals, and manufactured homes; 800-523-3581
Hocking County Regional Planning OfficeSubdivision and lot split review, large-lot rules, floodplain administration; Director Scott L. Schrader; 93 West Hunter Street, Logan; 740-380-9634
Hocking County EngineerDriveway permits on county roads, survey approval; William R. Shaw, P.E., P.S.; 1286 California Avenue, Logan; 740-385-8543
Mapping & Drafting DepartmentHouse numbers and deed approval for transfer; Courthouse, 1 East Main Street, second floor; 740-385-8546

Logan, the villages and the townships

Logan (about 7,160 people) is the county seat and only city, and the only place with zoning according to the Regional Planning FAQ. The villages are Laurelville, Murray City and a small part of Buchtel. Township roads are under each township’s trustees, who issue driveway permits there. The county’s rural zoning commission meets on the last Thursday of the month at 2:00 p.m. in the Commissioners’ office, 1 East Main Street.

Hocking County permit types

The Health Department posts its applications as printable forms, and Regional Planning posts a step-by-step checklist for land splits that ends at the Auditor and Recorder.

Residential permits

  • Building placement permit: complete the application, pay the fee and schedule a site evaluation with a sanitarian. When replacing a home, the existing sewage system is inspected, risers to grade are required on all septic tanks and aerators, and the system must meet the rules in force when it was installed without causing a nuisance. Post the permit at the end of the driveway by the road.
  • Plumbing: a residential plumbing permit application with isometric drawings; a homeowner may install the plumbing in their own residence using the homeowner’s affidavit, otherwise a registered contractor does the work.
  • Sewage system: an installation permit for a new or replacement household system, or an alteration permit.
  • Private water: a well, pond or conversion permit before construction.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

The state’s Industrial Compliance Division issues building permits for commercial buildings, including transient and cabin rentals. The Health Department still permits their plumbing: commercial applications need architectural plans, and all commercial plumbing work must be done by a licensed plumbing contractor registered with the department. Transient (R-1) rentals have their own building placement and plumbing permit fees.

What comes before the building permit

  • Land splits. A new split must be at least 80,000 square feet (1.836 acres) unless it goes to a neighbor, have at least 100 feet of public road frontage, and keep a depth of no more than three times its width for tracts up to 20 acres; only 5 splits (4 new tracts and the remainder) may be made from a parent tract before platting is needed, followed by a 6-year wait.
  • Health approval of splits. Splits under 5 acres need Health Department approval of sewage feasibility ($125 per lot).
  • Driveways. County-road driveways are approved by the Engineer before construction and inspected afterwards; the approved permit is then taken to Mapping & Drafting for a house number. Township trustees and ODOT handle their own roads.
  • Floodplain. Every tract must meet the county flood plain regulations administered by Regional Planning.

Hocking County permit costs and fees

The Health Department’s fees were set on December 8, 2025 and took effect on January 1, 2026. Commercial building fees are charged by the state, not the county.

Rather talk it over?

Call 1-855-478-4290 →
Hocking County Health Department fees, 2026
WorkFee
Residential building placement permit$55
Transient (R-1) rental building placement permit$105
Building or placing a home before the permit issues$500 penalty; $1,000 for a second offense
Building not in accordance with the issued permit$2,000 penalty
Site evaluation / variance request$135 / $125
Property split or subdivision lot approval$125
New or replacement septic system under 500 gallons a day$588 + $74 state fee = $662
Septic system alteration$340 + $35 state fee = $375
Single well$336 + $74 state + $20 ODNR = $430
Residential plumbing$50 permit and inspection + $15 per fixture
Commercial plumbing$200 processing + $25 per fixture + $200 plan evaluation
Plumbing re-inspection, residential / commercial$50 / $75

Worked example from the 2026 fees: a new house on a rural lot with a standard septic system and a well pays $55 for the placement permit, $135 for the site evaluation, $662 for the septic permit and $430 for the well, $1,282 before plumbing. Its plumbing permit for 12 fixtures is $50 + (12 × $15 = $180) = $230. Plumbing started before the permit costs an extra 50% of the permit fee the first time.

Trade permits and who may pull them

Plumbing is the trade the county regulates directly. Plumbing contractors register with the Health Department ($125 a year), post a $20,000 bond, carry liability insurance and have a state plumbing license assigned to the company; journeymen and apprentices register too, and plumbing without registration costs $150 plus the fee. Homeowners may plumb their own residence. The Health Department pages describe no county electrical or HVAC permit; for commercial work, electrical, HVAC, hydronics and refrigeration contractors need the matching OCILB license, and the state’s permit covers the building.

Rather not deal with the Hocking County building department?

Get a free quote →

How to apply for a permit in Hocking County

1. Talk to Regional Planning first

Its office reviews splits, floodplain status, road frontage and health requirements before you spend money.

2. Get the lot approved

Have an Ohio surveyor prepare the survey for the Engineer’s approval, then the Health Department and Regional Planning stamps, then Mapping & Drafting, the Auditor and the Recorder.

3. Secure the driveway and address

File the driveway permit with the Engineer, township trustees or ODOT, and take the approved permit to Mapping & Drafting for a house number.

4. Apply for the placement permit

Submit the Health Department application and fee and book the sanitarian’s site evaluation.

5. Add septic, well and plumbing permits

File each with the Health Department, with isometric drawings for plumbing.

6. Commercial projects

Apply to the state’s Industrial Compliance Division for the building permit and to the Health Department for plumbing, with architectural plans.

Review, corrections and what causes delay

Splits that lack road frontage, exceed the 3-to-1 shape rule or need platting are the usual stumbling blocks, which is why Regional Planning asks to be consulted first. Building a home in a way that departs from the placement permit carries a $2,000 penalty, so changes should go back to the Health Department before construction.

Inspections and certificates

Plumbing inspections, underground, rough-in and final, are booked with the Health Department at 740-385-3030 ext. 2. If one fails, the re-inspection fee must be paid before another can be scheduled, the address must be visible from the road, and the building card must be on site. The sanitarian inspects the site before the placement permit and the septic installation during construction, and the Engineer inspects a county-road driveway after it is built. For commercial buildings, the state’s inspectors and certificate of occupancy apply.

Ohio building code in Hocking County

FEMA’s Community Status Book lists unincorporated Hocking County (community 390272) as participating in the National Flood Insurance Program, with a current effective flood map dated November 4, 2010; the Regional Planning Office administers the county flood plain regulations adopted in 2012.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Want this handled start to finish?

Get a free quote →

Hocking County permit search and official resources

The Health Department’s map-based permit search shows permits it has issued for a property. Split approvals and floodplain files sit with the Regional Planning Office, and recorded deeds with the Recorder.

Inspections are where schedules slip.

Get a free quote →

Hocking County building permit FAQs

Do I need a building permit to build a house in Hocking County?

Outside Logan, you need the Health Department’s building placement permit ($55) before construction, plus plumbing, septic and well permits.

Who issues building permits for cabin rentals?

The Industrial Compliance Division of the Ohio Department of Commerce (800-523-3581), which the Health Department names for all commercial buildings, including transient and cabin rentals.

What happens if I build before getting the placement permit?

The Health Department charges a $500 penalty, $1,000 for a second offense.

Can I do my own plumbing?

Yes, a homeowner may install the plumbing for their own residence with a Health Department permit; other work needs a registered plumbing contractor.

Does Hocking County have zoning?

The Regional Planning FAQ says zoning is in place only in Logan, although the county has a rural zoning commission that meets monthly.

How small can a new lot be?

At least 80,000 square feet (1.836 acres) with 100 feet of public road frontage, unless the land goes to an adjoining owner.

How much does a new septic system permit cost?

$662 including the state fee for a household system under 500 gallons a day, plus a $135 site evaluation.

Simplify Hocking County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Hocking County sooner?

Let Alliance prepare, file, and track your Hocking County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Hocking County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.