Cleveland Heights, Ohio Building Permit Guide

To get a building permit in Cleveland Heights, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Cleveland Heights’ Building and Permitting Division at City Hall, 40 Severance Circle, issues building and trade permits, and any exterior change must clear the Architectural Board of Review before a permit is issued.

Authority: Cleveland Heights Building DepartmentFees: Ordinance 259-2024Phone: 216-291-4900
Authority
City Building Department40 Severance Circle
Houses
$150 + 1% of costNew homes and additions
Exterior changes
ABR approval firstBoard meets twice a month
Permit hours
8:30–noon, 12:30–3:30216-291-4900, option 1

In Cleveland Heights, permits come from the Building Department, the Building and Permitting Division of the Department of Planning, Neighborhoods and Development, at City Hall, 40 Severance Circle (216-291-4900, option 1), where Eric Elmi is the Chief Building Official. Plans for new structures and exterior design changes need Architectural Board of Review approval before a permit is issued. Under Ordinance No. 259-2024, in effect since January 1, 2025, a new house or addition pays $150 plus 1% of the construction cost, plus the 1% state surcharge.

What requires a building permit in Cleveland Heights?

The city’s rule is that most construction needs a permit; minor repairs, interior or exterior painting and gutter or downspout work are the exceptions it names. The homeowner is ultimately responsible for making sure permits are obtained, and when a contractor does the work, the contractor pulls them.

Permit required

  • New structures and additions
  • Demolition, alteration or major repair of any building or structure
  • Window replacement, new siding (beyond small patches), decks and new or rebuilt steps
  • Concrete or asphalt replacement or resurfacing, and any paving, including brick walks
  • Grading or regrading yard areas
  • Electrical work other than minor violation corrections, and plumbing, heating and air conditioning work

No permit

  • Minor repairs
  • Interior and exterior painting
  • Gutters and downspouts

Tents have their own application, and work on a public street needs a street excavation permit from the Building Commissioner. Work done without a permit brings a stop-work order or violation notice and higher fees, and repeat offenders can be summoned to court.

What Cleveland Heights decides and what the state holds

Ohio adopts the building codes; Cleveland Heights decides how its buildings look and how much permits cost. The Architectural Board of Review rules on the design of new and altered buildings, the Landmark Commission protects designated landmarks and historic districts under Ordinance 011-2019, and the city requires a point-of-sale inspection before any property is sold. Zoning is changing: the city is rewriting its Zoning Code, with a diagnostic report dated September 1, 2026, a public open house held on September 17, 2026, a review draft planned for winter 2026 and adoption steps in early 2027. Separately, Ordinance No. 142-2026, introduced on July 6, 2026 to allow accessory dwelling units, had a Council public hearing scheduled for October 15, 2026; the city’s page does not yet show a final Council vote. FEMA lists Cleveland Heights as a participating flood insurance community, with maps dated December 3, 2010.

Cleveland Heights building department: who handles permitting

The Building Department issues permits, examines plans and inspects construction throughout the city, and also handles business occupancy permits, contractor registration, forestry licenses and snowplow and landscaping permits. Housing inspections, including point-of-sale, rental and systematic exterior inspections, are handled by the city’s Inspectional Services and Housing Inspections staff, also at 40 Severance Circle. Cleveland Heights is its own city with its own department; the City of Cleveland next door is a different jurisdiction.

Short on time to read all of this?

Get a free quote →
Cleveland Heights permit contacts
DetailInformation
OfficeBuilding and Permitting Division, City Hall, 40 Severance Circle, Cleveland Heights, OH 44118
Phone216-291-4900, option 1
Emailbuilding@clevelandheights.gov
Permit hoursMonday to Friday, 8:30 a.m. to noon and 12:30 to 3:30 p.m.
Chief Building OfficialEric Elmi
Inspection requests216-291-4935 or building@clevelandheights.gov (the inspections page also lists 216-291-4900, option 1)
Point-of-sale and housing inspections216-291-5900 or 216-291-4958
Online portalCitizenserve (citizenserve.com/clevelandheights)

Cleveland Heights permit types

Cleveland Heights posts separate applications for residential building, commercial building, siding, electrical, mechanical, plumbing and sewer, fire protection, and apron, driveway and sidewalk work, plus a business occupancy permit and a utilities right-of-way application. You can download a form, fill it out and bring it to the Building Department during permit hours; the Architectural Board of Review application is filed through Citizenserve.

Residential permits

  • New homes and additions pay on the cost of construction, and their exterior design needs ABR approval first; homes reviewed under the Residential Code of Ohio are charged $60 an hour for plan examination.
  • Exterior changes such as new siding, windows, steps and decks need a permit, and those that change how a property looks go to the ABR.
  • Pools with more than 100 square feet of water surface and more than 2 feet deep need a permit, in-ground or above ground.
  • Plumbing includes a separate sheet for installing interior non-metallic water lines.

Commercial permits

Commercial projects reviewed under the Ohio Building Code pay $110 an hour of plan review time, with a three-hour minimum ($330) plus the 3% state surcharge, and $80 for each resubmission. Commercial signs and awnings need ABR approval. A new business, or a change of occupancy, needs a business occupancy permit from the Building Department, followed by a business maintenance inspection booked with Inspectional Services at 216-291-5900, option 1.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Architectural Board of Review. Three members and two alternates, staffed by the Planning Department, meeting online on the second and fourth Thursdays from 4:00 to 6:00 p.m. Fees for one-, two- and three-family homes are $50 for new construction and $35 for additions or alterations, covering two appearances; each later appearance is $25 and a special meeting $200.
  • Landmark Commission. Changes to designated landmarks or properties in historic districts need its Certificate of Appropriateness.
  • Board of Zoning Appeals. Hears standard variances (height, area, distance) and use variances, and appeals of certain officials’ decisions; a standard variance needs a written statement of practical difficulty.
  • Planning Commission and Board of Control. The commission, seven residents appointed by Council for six-year terms, grants conditional use permits and resubdivisions and advises Council on zoning; the Board of Control oversees the S-1 district around Severance Town Center.

Cleveland Heights permit costs and fees

The permit fee schedule is Ordinance No. 259-2024, in effect as of January 1, 2025. Most permits are a basic fee plus 1% of the cost of construction, and the owner must give estimates that let the Building Official set the cost. The schedule adds the state surcharge of 1% on one-, two- and three-family properties and 3% on all other permits, paid to the Board of Building Standards.

Cleveland Heights permit fees (Ordinance No. 259-2024, as of January 1, 2025)
WorkFee
New 1–3 family building or addition$150 + 1% of construction cost
New home trades: electrical, plumbing, heating, ventilating$75 + 1% each
Detached garage up to 500 sq ft / 501 sq ft or more$100 + 1% / $150 + 1%
New commercial building or addition (including three or more townhomes)2% of construction cost; each trade $100 + 1%
Interior alteration (residential or commercial)$150 + 1%
Siding, windows, roof$50 + 1% each
Pool: in-ground / above ground$100 + 1% / $50 + 1%
Central residential air conditioning$75 + 1%
Repairs not listed elsewhere$50 + 1%
Plan examination: residential / commercial$60 per hour / $110 per hour, $330 minimum
Driveway (new or 50%+ replaced); sidewalk; apron; curb cut$50; $35; $25; $50
Street excavation$200 (under 20 sq ft) to $800 (100 sq ft or more)
Re-inspection$50
Permit obtained after notice of unpermitted workSurcharge up to $500 within 5 days; up to $1,000 per week after

Rather talk it over?

Call 1-855-478-4290 →

Worked example from the ordinance: a $30,000 interior remodel of a house pays $150 plus 1% of $30,000, or $450, and the 1% state surcharge brings it to $454.50; electrical or plumbing permits for the job are separate. The city’s Building page says fees double when work starts without a permit, while the ordinance sets the surcharges in the table; the ordinance is the adopted rule.

Trade permits and who may pull them

Electrical, plumbing, heating, air conditioning and fire protection work each need a separate permit, and the minimum electrical fee is $50. Only a registered contractor can be issued a permit, apart from the homeowner exception below. Registration, required since September 18, 2001 under Chapter 1317, includes:

  • an application signed by the company owner, who also signs the bond;
  • a $10,000 bond on the city’s own form, approved by the Law Department, with the bonding company’s embossed seal;
  • insurance of $100,000 per person and $300,000 per occurrence for bodily injury and $50,000 for property damage, naming the City of Cleveland Heights as certificate holder and additional insured, with 10 days’ written notice before any cancellation;
  • for electricians, plumbers and HVAC, refrigeration and fire suppression or alarm contractors, a copy of the state license;
  • a fee of $150 for the first trade and $100 for each additional trade.

Registrations expire on December 31. Plumbing, sewer, electrical and HVAC firms must employ a registration holder full time to supervise every installation, and a general contractor without such a certificate cannot get trade permits.

Homeowners. The owner of a one-, two- or three-family home who lives there may do work personally without registering, by signing the notarized Homeowner’s Exception Affidavit (Section 1317.01(c)). The owner arranges every inspection, may not connect to the public sewer or water system, and must have the permit voided if a contractor is hired later. Subcontractors cannot work under a homeowner permit except on tasks that need no permit, such as floor tile in a permitted bathroom remodel.

Rather not deal with the building department?

Get a free quote →

How to apply for a Cleveland Heights building permit

1. Call the Building Department

Ring 216-291-4900, option 1, during permit hours to confirm which permits and boards the project needs.

2. Clear ABR and Landmark review

File the Architectural Board of Review application in Citizenserve for any change to a building’s look, and a Certificate of Appropriateness for a landmark.

3. Register or sign the affidavit

Contractors register by trade; owner-occupants doing their own work sign the Homeowner’s Exception Affidavit.

4. Fill out the permit forms

Use the residential or commercial building application and a separate form for each trade, with plans and cost estimates.

5. File and pay

Bring the forms to City Hall between 8:30 a.m. and noon or 12:30 and 3:30 p.m., and pay the permit and plan review fees plus the state surcharge.

6. Post the permit

Keep the permit posted for the whole job and book each inspection in advance.

Review, corrections and what causes delay

ABR approval comes before the permit, and the base fee covers only two appearances; each later one costs $25. Commercial resubmissions cost $80, residential review is billed by the hour, and a submission that needs an adjudication order from the Chief Building Official carries a $40 fee. Incomplete cost estimates can lead the Building Official to require an estimate from a professional.

Inspections and certificates in Cleveland Heights

Every permitted job is inspected. Electrical, plumbing and heating work must be inspected before it is closed into walls, floors or ceilings, and the city suggests having the final inspection made before the last payment to a contractor. A failed inspection, or work not ready when the inspector arrives, costs $50 to re-inspect. Construction debris must go to a landfill; the city’s Public Works Department does not collect it.

Point-of-sale inspections. Before signing an agreement to sell any property, including houses, duplexes, apartments, condominiums and commercial buildings, the owner must get a Certificate of Inspection. It costs $200 for the first unit and $50 for each additional unit, so a two-family home is $250, and it is valid for one year. The seller gives the buyer copies of the certificate and any certificate of compliance before the sale contract is signed; schedule the inspection through the online portal. Housing Inspections (216-291-5900) also publishes the city’s escrow requirements for repairs left open at a sale.

Ohio building code in Cleveland Heights

Cleveland Heights reviews commercial projects under the Ohio Building Code and houses under the Residential Code of Ohio, and its fee ordinance collects the Board of Building Standards surcharge on both. The Board’s look-up map shows the department with authority over an address.

Ohio has statewide building codes: the Ohio Building Code for commercial and other nonresidential buildings and the Residential Code of Ohio for detached one-, two- and three-family dwellings. Only departments certified by the Ohio Board of Building Standards may approve plans and inspect, and residential rules are uniform statewide. How Ohio’s statewide code works

Want this handled start to finish?

Get a free quote →

Cleveland Heights building permit FAQs

Do I need a permit to replace windows in Cleveland Heights?

Yes. Windows, new siding, decks and new steps all need permits; windows are $50 plus 1% of the cost, and visible changes may need ABR review.

What does a permit for a new house or addition cost?

$150 plus 1% of the construction cost, with separate trade permits at $75 plus 1% each and the 1% state surcharge.

Can I do my own work without a contractor?

Yes, in a one-, two- or three-family home you live in, by signing the notarized Homeowner’s Exception Affidavit; homeowners may not make sewer or water line hookups themselves.

When is an Architectural Board of Review approval needed?

For new structures and any change that alters how a property looks, plus commercial signs and awnings, before the permit is issued.

How much is a point-of-sale inspection?

$200 for the first unit and $50 for each additional unit; the certificate is valid for one year.

How do I book an inspection?

Call 216-291-4935 or 216-291-4900, option 1, or email building@clevelandheights.gov during permit hours.

Are accessory dwelling units allowed?

Ordinance No. 142-2026 would permit them; Council scheduled its public hearing for October 15, 2026, and the city’s page has not yet shown a final vote.

Cleveland Heights permit search and official resources

Permit holders follow applications, ABR filings and point-of-sale scheduling in Citizenserve. For older permits on a property, email building@clevelandheights.gov or call 216-291-4900, option 1; the city also links a website listing registered contractors for owners checking a firm.

Inspections are where schedules slip.

Get a free quote →

Simplify Cleveland Heights permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Ohio. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Cleveland Heights sooner?

Let Alliance prepare, file, and track your Cleveland Heights permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Cleveland Heights permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.