Brunswick County building permits come from Code Administration in Bolivia — a single department carrying Building Inspections, Central Permitting, and the Fire Marshal together. On commercial work that consolidation is a genuine scheduling advantage, because building and fire review sit in the same building rather than in two agencies.
Brunswick has been among the fastest-growing counties in the United States, and it is a CAMA county — so the coastal permit question runs alongside the building one on its own clock. Several municipalities, the beach towns among them, permit their own work.
Applies to Brunswick County's permitting jurisdiction. Several municipalities permit their own work; CP Online publishes a municipalities page because the question comes up constantly.
A building permit is not a CAMA permit. Code Administration can issue a building permit for a project that still needs coastal clearance. Settle the Area of Environmental Concern question before the design is fixed.
What requires a permit in Brunswick County?
A Brunswick County building permit is required before most construction, alteration, repair, demolition, or change of occupancy in the county's jurisdiction. Brunswick has been among the fastest-growing counties in the United States, driven by coastal retirement and second-home construction along a shoreline that runs from the South Carolina line up to the Cape Fear.
The enforced edition is the 2018 NC State Building Code family (2018 Residential Code, 2020 NC Electrical Code). The 2024 NC State Building Code was originally slated for January 1, 2025, but S.L. 2024-57 and then S.L. 2025-2 (the Disaster Recovery Act of 2025, passed after Hurricane Helene) pushed its effective date to 12 months after the State Fire Marshal certifies publication and the seating of the new Residential Code Council — currently expected no earlier than 2027. Until then the 2018 code governs, though an owner may elect the 2024 code as an alternate method under § 102.5 of the Administrative Code if the plan set says so clearly.
Permit required
- New construction, additions, and accessory structures over the statutory exemption
- Structural and load-bearing alterations, repairs, and demolition
- Electrical service changes, panel work, and most wiring alterations
- Plumbing additions, repipes, gas piping, and non-identical water heater swaps
- Mechanical and HVAC installations and changeouts
- Development inside an Area of Environmental Concern, which adds a CAMA permit
- Docks, piers, bulkheads, and shoreline structures
- Fire protection systems, reviewed by the Fire Marshal in the same department
Typically exempt
- Nonstructural work costing forty thousand dollars or less in a single-family home, farm building, or commercial building (G.S. 160D-1110(c))
- Replacement windows, doors, exterior siding, and porch/deck pickets, railings, stair treads, and decking
- Like-for-like plumbing swaps that keep size and capacity, and like-kind light fixtures, receptacles, and switches
- Same-spec water heater changeouts installed by a licensed contractor
- Painting, flooring, cabinetry, and other cosmetic work
Brunswick County building department: who handles permitting
Brunswick County Code Administration is a single department carrying Building Inspections, Central Permitting, and the Fire Marshal together, working from 75 Courthouse Drive, Building I, in Bolivia. Consolidating building and fire under one roof is genuinely useful on commercial work, where the two reviews otherwise run in different buildings on different clocks.
Brunswick contains a long list of municipalities — the beach towns among them — and several run their own permitting. The county's CP Online portal publishes a municipalities page precisely because the question comes up so often. Settle it before you prepare anything, because on this coast a mailing address and a permitting jurisdiction routinely disagree.
| Detail | Information |
|---|---|
| Office | Brunswick County Code Administration, 75 Courthouse Drive Building I, Bolivia, NC 28422 |
| Mailing | P.O. Box 249, Bolivia, NC 28422 |
| Phone | (910) 253-2050; permit application help on (910) 253-2021 option 2 |
| Department scope | Building Inspections, Central Permitting, and the Fire Marshal |
| Online portal | Brunswick County CP Online — permits, inspections, and a municipalities page |
| Coastal overlay | CAMA county — Areas of Environmental Concern trigger a separate permit |
Brunswick publishes its permit data openly, and it is worth using. Archived residential new-home and commercial building data is posted to the county open data site around the 25th of the following month, with live data available alongside it — so you can see exactly what is being built, where, and at what pace before you commit to a site or a bid.
This guide covers Brunswick County, North Carolina, seated in Bolivia. Brunswick County, Virginia is a separate jurisdiction, and there is also a Brunswick in Maine and in Georgia. Locally, note that the county seat Bolivia is a town of under two hundred people — the population is on the coast, not at the courthouse.
Brunswick County permits: record types and what each covers
Brunswick's catalog carries coastal and fire records that inland counties never issue, and those are usually what governs a waterfront schedule. These are the records you will encounter:
Residential permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | New dwellings, additions, and accessory structures over the statutory exemption ceiling | Full plan review against the 2018 NC Residential Code, plus zoning | Valuation-based |
| Renovation / alteration | Load-bearing changes, layout changes, or added plumbing, HVAC, or electrical | Plan review scaled to scope; 15-business-day residential clock applies | Valuation-based |
| Reroof | Roof covering replacement, and any work that adds rather than replaces roofing | Sheathing and dry-in inspection; plan review rarely required | Valuation or squares |
| Solar photovoltaic | Rooftop or ground-mount PV, with or without battery storage | Electrical review led, with structural review of the attachment | Flat or system-size based |
| Battery energy storage | Wall or floor-mounted ESS added to a dwelling | Electrical review plus fire separation and location check | Flat or per-permit minimum |
| Electrical | Service changes, panel upgrades, new circuits, EV chargers, most rewiring | Trade review by the electrical inspector; filed as its own record | Per-permit minimum or per-device |
| Plumbing | New piping, repipes, fixtures, gas piping, and non-identical water heater swaps | Trade review; like-for-like same-capacity swaps are statutorily exempt | Per-permit minimum or per-fixture |
| Mechanical / HVAC | Changeouts that are not like-for-like, ductwork, and refrigeration | Trade review by the mechanical inspector | Per-permit minimum or per-unit |
| Deck and porch | New decks and structural rebuilds; pickets, rails, treads, and decking are exempt replacements | Footing and framing review against the residential code | Flat or valuation-based |
| Pool and spa | In-ground and above-ground pools, spas, barriers, and bonding | Structural, barrier, and electrical bonding review | Valuation-based |
| Accessory structure | Sheds, detached garages, and carports above the local size threshold | Zoning first, then structural review where applicable | Flat or valuation-based |
| Demolition | Full or partial demolition of a structure | Utility disconnect verification and asbestos notification | Flat |
| CAMA minor permit | Residential development inside an Area of Environmental Concern | Issued locally by a designated Local Permit Officer | State-set, CPI-adjusted |
| Elevation certificate / flood review | Construction in a mapped flood zone | Elevation and flood-resistant construction review | Flat plus survey cost |
| Dock, pier, or bulkhead | Waterfront and shoreline structures | Structural review plus CAMA clearance where an AEC applies | Valuation-based |
Commercial permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | Ground-up commercial, industrial, and multifamily buildings | Full multi-discipline review; sealed plans required | Valuation-based |
| Upfit / tenant improvement | Interior build-outs and suite fit-ups in an existing shell | Concurrent building, trade, and fire review | Valuation-based |
| Renovation / alteration | Structural, envelope, or system changes to an existing building | Plan review scaled to scope; accessibility triggers attach | Valuation-based |
| Change of occupancy | Converting a building from one occupancy classification to another | Life-safety, accessibility, and zoning review | Valuation or flat |
| Shell building | A building permitted without a known tenant or use | Shell review only; no certificate of occupancy until an upfit closes | Valuation-based |
| Reroof | Commercial roof covering replacement or recover | Structural check on added dead load; fire review where applicable | Valuation or squares |
| Solar photovoltaic | Commercial rooftop, carport, and ground-mount arrays | Structural, electrical, and fire access review | Valuation or system-size based |
| Electrical | Service, distribution, and branch circuit work | Trade review; separate record from the building permit | Valuation or per-device |
| Plumbing | Supply, waste, vent, grease, and gas systems | Trade review; backflow and grease interceptor sign-offs attach | Valuation or per-fixture |
| Mechanical / HVAC | Rooftop units, ductwork, exhaust, and refrigeration | Trade review; energy compliance documentation required | Valuation or per-unit |
| Fire protection | Sprinkler, standpipe, alarm, hood, and suppression systems | Fire prevention review, often a separate submittal | Valuation or per-device |
| Sign | Wall, monument, and illuminated signage | Zoning review plus electrical where illuminated | Flat or per-sign |
| CAMA major permit | Coastal development needing other approvals, or dredge and fill | Issued by the NC Division of Coastal Management | State-set, CPI-adjusted |
| Fire Marshal permit | Sprinkler, alarm, hood, and suppression systems | Reviewed inside Code Administration alongside the building record | Valuation or per-device |
Residential
- Single-discipline review in most cases
- One permit covers simultaneous same-address residential projects (G.S. 160D-1110(d))
- The 15-business-day review clock and its 10%-per-day fee refund apply
- No engineer's or architect's seal may be demanded unless the code itself requires it
Commercial — multi-discipline
- Concurrent review across building, trades, fire, and zoning
- Signed and sealed plans across every affected discipline
- Third-party plan review available under G.S. 160D-1110.1 when review stalls
- Accessibility and life-safety review attach to any change of occupancy
Records you will actually see in Brunswick
| Record | What it covers |
|---|---|
| Residential building permit | New dwellings, additions, and alterations in the county's jurisdiction |
| Commercial building permit | Ground-up commercial, upfits, and alterations with multi-discipline review |
| Fire Marshal permit | Sprinkler, alarm, hood, and suppression, reviewed inside the same department |
| CAMA minor permit | Development inside an Area of Environmental Concern, issued locally |
| CAMA major permit | Larger or multi-agency coastal development, via the Division of Coastal Management |
| Dock, pier, and bulkhead | Waterfront structures, frequently CAMA-triggering |
| Trade permits (electrical, plumbing, mechanical) | Filed by the state-licensed contractor for each trade |
| Flood zone and elevation review | Elevation certificates and flood-resistant construction in mapped zones |
Solar permits in Brunswick
Solar is its own record in North Carolina rather than a line item on a building permit, and it is reviewed on two tracks at once: the electrical side (conductors, overcurrent protection, rapid shutdown, labelling, and the service or supply-side connection) and the structural side (attachment detail, rail spacing, and whether the existing framing carries the added dead load).
Solar files through CP Online as an electrical-led record with structural review. On the coast the attachment detail carries the array into the roof's wind load path, so the structural review matters more here than it does inland.
The HOA question comes up on nearly every residential array, and North Carolina answers it more favourably than most states. G.S. 22B-20 voids covenants that prohibit — or merely have the effect of prohibiting — rooftop solar, and in Belmont Association v. Farwig (2022) the NC Supreme Court held a review committee's general aesthetic authority cannot block street-facing panels: an HOA must ban them explicitly, and even then cannot force a relocation that defeats reasonable use (a north-facing roof cutting output roughly in half fails that test). Condominiums under Chapters 47A/47C sit outside the statute.
Utility interconnection runs on its own clock alongside the permit. Duke Energy and the state's electric cooperatives each set their own application, meter, and witness-test sequence, and the utility's approval to energize is not something the inspection department controls — plan for the two tracks to finish at different times.
Roofing permits in Brunswick
A roof covering replacement needs a permit in most of North Carolina, and the statutory exemption is narrower than contractors expect: replacing roofing is treated differently from adding roofing, and adding a layer pushes the job out of the exemption regardless of what it costs.
Because North Carolina runs a statewide code, there is no state product-approval database to search and no local product-approval number to cite — the assembly simply has to comply with the NC code and the manufacturer's listed installation instructions, which is what the inspector checks against.
Reroofs in the county's jurisdiction are county permits; in the beach towns that permit their own work they are not. Coastal wind requirements drive the fastening schedule regardless of which counter issues the permit.
Sequencing is where reroofs go wrong. The sheathing and dry-in condition has to be visible when the inspector arrives, so covering it before the inspection means opening it back up. On a structure that has had a previous layer removed, expect the inspector to look at deck fastening and at any decking replaced along the eaves.
Brunswick County permit cost
Brunswick County building permit fees are set by the county's adopted schedule and vary with record type and scope, with trade permits charged separately. Applications and payments run through CP Online, and the permit application help line is a separate option on the main number.
Coastal costs sit outside the county schedule. CAMA permit fees are set by the state and, under G.S. 143B-279.19, adjusted to the Consumer Price Index beginning July 1, 2025 and every four years afterwards, so a figure quoted from an older handbook will understate the current cost.
| Fee component | How it works |
|---|---|
| Building permit | County fee schedule by record type and scope |
| Trade permits (E/P/M) | Charged separately per trade record |
| Fire Marshal review | Charged separately, though administered in the same department |
| CAMA minor permit | State-set, CPI-adjusted from July 1, 2025 on a four-year cycle |
| CAMA major permit | State-set, through the Division of Coastal Management |
| Re-inspection | Charged on failed inspections before final or certificate |
Want a precise number for a specific Brunswick project? Send us the scope and we will price the permit path before you file.
Brunswick County trade permits
Brunswick County trade permits for electrical, plumbing, and mechanical work are separate CP Online records pulled by the state-licensed contractor performing the work, filed against the building record for the same address.
Electrical permits
Required for services, panel upgrades, circuits, EV chargers, and solar interconnection. Electrical work takes a contractor licensed by the NC State Board of Examiners of Electrical Contractors.
Plumbing permits
Required for new piping, repipes, fixtures, gas piping, and non-identical water heater changeouts by a state-licensed contractor.
Mechanical (HVAC) permits
Required for installations, non-identical changeouts, ductwork, and refrigeration. Salt-air exposure drives equipment selection here more than the code does.
Fire protection
Sprinkler, alarm, and suppression work is reviewed by the Fire Marshal inside Code Administration rather than by a separate agency — a real scheduling advantage on commercial jobs.
Brunswick County permit application: how to apply step by step
Here is how to get a building permit in Brunswick County, from confirming the requirement through to close-out. Each step below corresponds to a real decision point where projects commonly stall.
Several Brunswick municipalities permit their own work. CP Online publishes a municipalities page because this question is the county's most common one.
Determine whether the parcel sits inside an Area of Environmental Concern. If it does, the CAMA minor or major permit starts now, not after the building permit.
Mapped flood zones drive elevation and construction requirements. Get the elevation certificate question settled while the design is still fluid.
Submit the application with plans and supporting documents. Call the application help line if the portal is unfamiliar.
Because Code Administration carries the Fire Marshal, commercial building and fire review sit in the same department — use that rather than treating them as separate errands.
Pay in the portal, request inspections against the record, and run through to your certificate.
Inspections in Brunswick County
Brunswick County inspections are requested against your permit record through CP Online, which also publishes future inspections and a permit data download. Typical checkpoints run footing and foundation, rough-in trades, framing, insulation, and final.
Because building and fire sit in one department, commercial projects can sequence sprinkler and alarm inspections alongside the building trades rather than coordinating across agencies. G.S. 143-139 requires code enforcement inspections to be performed within two business days of the request. That is a statutory duty, not a courtesy, and it sits alongside G.S. 160D-1104's requirement that the inspector complete every inspection requested for a scheduled visit and itemize exactly what failed.
Keep the permit and approved plans on site. an NC building permit expires six months after issuance if work has not commenced (local ordinance can set less), and expires immediately if work stops for 12 months (G.S. 160D-1111) — changes from approved plans need written inspection-department approval first (G.S. 160D-1112).
Brunswick County permit search and official resources
Run a Brunswick County permit search, open CP Online, or check whether your project sits in an Area of Environmental Concern with the official links below.
- Brunswick County Code Administration
- Brunswick County CP Online permit portal
- Brunswick County permit reports and open data
- Brunswick County CAMA information
- NC Division of Coastal Management
- NC Licensing Board for General Contractors
Frequently asked questions
Who issues building permits in Brunswick County?
Brunswick County Code Administration, at 75 Courthouse Drive Building I in Bolivia. The department combines Building Inspections, Central Permitting, and the Fire Marshal. Several municipalities in the county permit their own work — CP Online publishes a municipalities page for exactly that reason.
Is Brunswick County a CAMA county?
Yes — one of North Carolina's twenty. A CAMA permit attaches only where the project falls inside an Area of Environmental Concern, which is a measured test rather than a general coastal designation.
Does a Brunswick County building permit cover CAMA?
No. They are separate approvals on separate timelines, and Code Administration can issue a building permit for a project that still needs coastal clearance. The stop-work order that follows is the most avoidable delay on the North Carolina coast.
What makes a project fall inside an Area of Environmental Concern?
Being in or on state waters, a marsh, or a wetland; within 75 feet of the normal high water line along an estuarine shoreline; within 30 feet of the normal water level of designated inland fishing waters; or within 575 feet of the mean high water line along an Outstanding Resource Water shoreline.
How do I run a Brunswick County permit search?
Through CP Online, which carries permits, future inspections, and a permit data download. The county also publishes archived residential and commercial permit data on its open data site, updated around the 25th of the following month, alongside live data.
Does Brunswick County handle fire permits too?
Yes — the Fire Marshal sits inside Code Administration alongside Building Inspections and Central Permitting. On commercial projects that means building and fire review are in the same department rather than in two separate agencies.
Which Brunswick County towns issue their own permits?
Several municipalities, including beach towns, run their own permitting. The county publishes a municipalities page in CP Online rather than a static list, because the arrangement changes — check it against your parcel before preparing anything.
How do coastal wind and flood rules affect a Brunswick County build?
They shape the structure rather than decorate it. Flood zone elevation, elevation certificates, and coastal wind design all drive the design, and oceanfront parcels add ocean hazard setbacks measured from erosion rates.
Who do I call for help with a Brunswick County permit application?
The main Code Administration number is (910) 253-2050, and there is a dedicated option for online permit application assistance on (910) 253-2021, option 2.
When is a general contractor licence required in Brunswick County?
On projects of forty thousand dollars or more, under G.S. 87-1 and the NC Licensing Board for General Contractors, with tiers capping single-project value at $750,000, $1,500,000, or without limit excluding land cost.
Do I need a lien agent for a Brunswick County project?
For work costing forty thousand dollars or more, yes — designated through LiensNC before the permit issues. Improvements to an owner-occupied existing single-family residence and incidental accessory structures are exempt.
Where is Brunswick County's building department?
In Bolivia, the county seat — a town of under two hundred people. That surprises people whose project is at Ocean Isle, Holden Beach, or Leland, because the population and the construction are on the coast while the courthouse is inland.
Simplify Brunswick County permitting with Alliance Permitting
One of the fastest-growing counties in the country, a coastal permit running on its own clock, and a municipal map that changes — Brunswick punishes assumption and rewards a filer who checks. A permit expediter for Brunswick County confirms the jurisdiction and the AEC question first, then files, tracks, and inspects through to certificate.
Trusted by leading builders, developers, and national contractors — 21 years of filing in the jurisdictions we write about.
Contractors and builders choose Alliance for Brunswick because the work is done by people who have stood at the counter:
- Jurisdiction and AEC settled first — before a drawing is prepared, not after a stop-work order.
- Complete oversight — every Brunswick permit and inspection tracked across your jobs in one place.
- Building and fire sequenced together — using the fact that both sit in one department, rather than treating them as separate errands.
Alliance Permitting is a permit documentation and expediting service. We are not a law firm and do not provide legal advice, and we are not the permitting authority.
Ready to break ground in Brunswick sooner?
Let Alliance prepare, file, and track your Brunswick permits while your crew stays on the job.
More North Carolina permitting guides
This guide is provided by Alliance Permitting for general information about Brunswick County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.