Burlington building permits come from the city's own Inspections Department at the Municipal Building, with everything running through BurlingtonSmart — the city's online permits and inspections portal. Alamance County permits outside the city, and Graham runs its own department too.
Permits here are distributed across four city departments. Most go through Inspections and Planning, but fences, sheds, and pools are Planning records, new driveways are Engineering, fire permits go to the Fire Department, and special events to the Special Events Division.
Applies inside Burlington city limits, including the part of the city in Guilford County. Alamance County permits unincorporated Alamance land; Graham and Mebane run their own inspections departments.
Four o'clock costs a whole day. Inspections requested before 4 p.m. are scheduled the following business day; anything after 4 p.m. is scheduled two business days from the request. 15 minutes late is a full extra day on site.
What requires a permit in Burlington?
A Burlington building permit is required before most construction, alteration, repair, demolition, or change of occupancy inside the city limits. Burlington runs its own Inspections Department — Alamance County permits outside the city, and Graham next door runs its own as well.
Permit required
- New construction, additions, and structural alterations
- Commercial construction, upfits, and change of use
- Electrical service changes, panel work, and most wiring alterations
- Plumbing additions, repipes, gas piping, and non-identical water heater swaps
- Mechanical and HVAC installations and changeouts
- Decks, sheds, pools, and fences — several handled by Planning rather than Inspections
- New driveways, handled by the Engineering Department
- Exterior work and tree removal in a local historic district, which needs a COA
Typically exempt
- Nonstructural work costing $40,000 or less in a single-family home, farm building, or commercial building (G.S. 160D-1110(c))
- Replacement windows, doors, exterior siding, and porch/deck pickets, railings, stair treads, and decking
- Like-for-like plumbing swaps that keep size and capacity, and like-kind light fixtures, receptacles, and switches
- Same-spec water heater changeouts installed by a licensed contractor
- Painting, flooring, cabinetry, and other cosmetic work
North Carolina enforces one State Building Code statewide; the 2018 edition still governs while the 2024 edition waits on the State Fire Marshal and the new Residential Code Council. North Carolina rules
Burlington building department: who handles permitting
The City of Burlington Inspections Department works from the Municipal Building at 425 South Lexington Avenue, with inspectors verifying work against state code requirements for the building, electrical, mechanical, and plumbing trades. Everything runs through BurlingtonSmart, the city's online inspections and permits portal, launched in 2020.
Permits are split across several departments. Most run through Inspections and Planning, but fences, sheds, and pools are Planning records, new driveways are Engineering, fire permits go through the Fire Department, and special events through the Special Events Division. Knowing which department owns your record saves a phone call and sometimes a week.
| Detail | Information |
|---|---|
| Office | City of Burlington Inspections, Municipal Building, 425 South Lexington Avenue, Burlington, NC |
| Inspections | (336) 222-5080 — also the BurlingtonSmart help line |
| Planning | (336) 222-5110 — fences, sheds, pools, and historic COAs |
| Engineering | (336) 222-5050 — new driveways |
| Online portal | BurlingtonSmart, a SmartGov public portal |
| Inspection scheduling | Before 4 p.m. for next business day; after 4 p.m. for two business days out |
Short on time to read all of this?
Get a free quote →If you are working on behalf of a company, stop and get an access code before you create your account — call Inspections or Planning first. Registering without one creates the wrong kind of account and is a nuisance to unwind. Also avoid uploading digitally signed or protected PDFs, which the portal does not handle.
This guide covers Burlington, North Carolina, mostly in Alamance County with a small part in Guilford. Burlington, Vermont is an unrelated and much-searched city, and there are Burlingtons in Iowa, Massachusetts, New Jersey, and Wisconsin. Locally, Burlington, Graham and Mebane each run their own inspections departments, leaving Alamance County to serve unincorporated land and the smaller towns.
In 2025, building permits issued in Burlington authorized 412 new privately owned housing units, 219 of them single-family homes, according to the U.S. Census Bureau Building Permits Survey.
Burlington permits: record types and what each covers
Burlington's records are distributed across four city departments, which is the first thing to establish. These are the ones you will file:
Residential permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | New dwellings, additions, and accessory structures above the local size threshold | Full plan review against the 2018 NC Residential Code, plus zoning | Valuation-based |
| Renovation / alteration | Load-bearing changes, work over $40,000, or added or redesigned plumbing, HVAC, or electrical | Plan review scaled to scope; 15-business-day residential clock applies | Valuation-based |
| Reroof | Roof covering replacement costing over $40,000, and any work that adds rather than replaces roofing | Inspections set by the local department; plan review rarely required | Valuation or squares |
| Solar photovoltaic | Rooftop or ground-mount PV, with or without battery storage | Electrical review led, with structural review of the attachment | Flat or system-size based |
| Battery energy storage | Wall or floor-mounted ESS added to a dwelling | Electrical review plus fire separation and location check | Flat or per-permit minimum |
| Electrical | Service changes, panel upgrades, new circuits, EV chargers, most rewiring | Trade review by the electrical inspector; filed as its own record | Per-permit minimum or per-device |
| Plumbing | New piping, repipes, fixtures, gas piping, and non-identical water heater swaps | Trade review; like-for-like same-capacity swaps are statutorily exempt | Per-permit minimum or per-fixture |
| Mechanical / HVAC | All HVAC equipment installs and changeouts, including like-for-like swaps, plus ductwork and refrigeration | Trade review by the mechanical inspector | Per-permit minimum or per-unit |
| Deck and porch | New decks and structural rebuilds; pickets, rails, treads, and decking are exempt replacements | Footing and framing review against the residential code | Flat or valuation-based |
| Pool and spa | In-ground and above-ground pools, spas, barriers, and bonding | Structural, barrier, and electrical bonding review | Valuation-based |
| Accessory structure | Sheds, detached garages, and carports above the local size threshold | Zoning first, then structural review where applicable | Flat or valuation-based |
| Demolition | Full or partial demolition of a structure | Utility disconnect verification and asbestos notification | Flat |
| Fence, shed, and pool permit | Handled by the Planning Department, not Inspections | Planning review under the Unified Development Ordinance | Planning fee schedule |
| Driveway permit | New driveways, handled by the Engineering Department | Engineering review | Engineering fee schedule |
| Zoning — accessory structures | Under Section 4.5 of the Unified Development Ordinance | Planning review | Planning fee schedule |
Not sure this scope needs a permit?
Get a free quote →Commercial permit types
| Permit type | What triggers it | Review path | Fee basis |
|---|---|---|---|
| New construction | Ground-up commercial, industrial, and multifamily buildings | Full multi-discipline review; sealed plans required | Valuation-based |
| Upfit / tenant improvement | Interior build-outs and suite fit-ups in an existing shell | Concurrent building, trade, and fire review | Valuation-based |
| Renovation / alteration | Structural, envelope, or system changes to an existing building | Plan review scaled to scope; accessibility triggers attach | Valuation-based |
| Change of occupancy | Converting a building from one occupancy classification to another | Life-safety, accessibility, and zoning review | Valuation or flat |
| Shell building | A building permitted without a known tenant or use | Shell review only; no certificate of occupancy until an upfit closes | Valuation-based |
| Reroof | Commercial roof covering replacement or recover | Structural check on added dead load; fire review where applicable | Valuation or squares |
| Solar photovoltaic | Commercial rooftop, carport, and ground-mount arrays | Structural, electrical, and fire access review | Valuation or system-size based |
| Electrical | Service, distribution, and branch circuit work | Trade review; separate record from the building permit | Valuation or per-device |
| Plumbing | Supply, waste, vent, grease, and gas systems | Trade review; backflow and grease interceptor sign-offs attach | Valuation or per-fixture |
| Mechanical / HVAC | Rooftop units, ductwork, exhaust, and refrigeration | Trade review; energy compliance documentation required | Valuation or per-unit |
| Fire protection | Sprinkler, standpipe, alarm, hood, and suppression systems | Fire prevention review, often a separate submittal | Valuation or per-device |
| Sign | Wall, monument, and illuminated signage | Zoning review plus electrical where illuminated | Flat or per-sign |
| Certificate of Appropriateness | Exterior work and tree removal in a historic district | Historic Preservation Commission approval, issued by Planning | Planning fee schedule |
| Sign and temporary banner permits | Under the Unified Development Ordinance | Planning review | Planning fee schedule |
| Live-remote inspection | Where the scope qualifies | Published by the Inspections Department as an option | Per inspection |
Rather talk it over?
Call 1-855-478-4290 →Residential
- Single-discipline review in most cases
- One permit covers simultaneous same-address residential projects (G.S. 160D-1110(d))
- Initial review due within 15 business days; after 20, 10% of the fee is refunded for each business day late (up to 10 days)
- No engineer's or architect's seal may be demanded unless the code itself requires it
Commercial — multi-discipline
- Concurrent review across building, trades, fire, and zoning
- Signed and sealed plans where state law requires them; small commercial buildings can be exempt (G.S. 83A-13)
- Third-party plan review available under G.S. 160D-1110.1 when review stalls
- Accessibility and life-safety review attach to any change of occupancy
Records you will actually see in Burlington
| Record | What it covers |
|---|---|
| Building permit | New construction, additions, and alterations, through Inspections |
| Trade permits (electrical, plumbing, mechanical) | Filed by the state-licensed contractor for each trade |
| Fence, shed, and pool permits | Handled by the Planning Department rather than Inspections |
| Driveway permit | Handled by the Engineering Department |
| Certificate of Appropriateness | Exterior work and tree removal in a local historic district |
| Sign and temporary banner permits | Under the Unified Development Ordinance |
| Temporary storage container / temporary dwelling | Each under its own UDO section |
| Zoning — accessory structures | Under Section 4.5 of the Unified Development Ordinance |
Rather not deal with the building department?
Get a free quote →Solar permits in Burlington
Solar in Burlington is an electrical-led BurlingtonSmart record. Ask whether the scope qualifies for a live-remote inspection, which the city publishes as an option and which can save a site visit on a small trade item.
Roofing permits in Burlington
Reroofs inside the city are city permits. In a locally designated historic district a Certificate of Appropriateness governs exterior work — and notably tree removal as well — approved by the Historic Preservation Commission before the permit does any good.
Solar covenants and the roofing permit exemption are set by state law, and utilities run interconnection on their own timeline. North Carolina rules
Burlington permit cost
Burlington building permit fees follow the city's adopted schedule, paid through BurlingtonSmart along with the application. Trade permits are charged separately, and records handled by Planning, Engineering, or the Fire Department carry their own fees.
The city also publishes an Inspections Refund Policy alongside its Informal Review Policy — worth reading before a project is cancelled rather than after. North Carolina also makes the money visible. Under S.L. 2022-11, every local government must publish an annual financial report showing how it used the prior year's building-code fees to support, administer, and implement its code enforcement program (G.S. 160D-402(d), with G.S. 160D-1102 governing the inspection department's own accounting).
| Fee component | How it works |
|---|---|
| Building permit | City fee schedule; paid through BurlingtonSmart |
| Trade permits (E/P/M) | Charged separately per trade record |
| Planning records | Fences, sheds, pools, signs, and COAs on the Planning schedule |
| Engineering records | New driveways on the Engineering schedule |
| Refund policy | Published by the Inspections Department |
| Business licences | No longer required except for beer and wine sales or taxi services |
Want a precise number for a specific Burlington project? Send us the scope and we will price the permit path before you file.
Burlington trade permits
Burlington trade permits for electrical, plumbing, and mechanical work are separate BurlingtonSmart records, and the city publishes its own Informal Review Policy under G.S. 160D-1104(e) if you disagree with a call.
Electrical permits
Required for services, panel upgrades, circuits, EV chargers, and solar interconnection. Electrical work takes a contractor licensed by the NC State Board of Examiners of Electrical Contractors, unless owners wire their own home that is not for sale or rent.
Plumbing permits
Required for new piping, repipes, fixtures, gas piping, and non-identical water heater changeouts by a state-licensed contractor.
Mechanical (HVAC) permits
Required for all installations and changeouts, including like-for-like swaps, plus ductwork and refrigeration, by a state-licensed heating contractor.
Live-remote inspections
Burlington publishes live-remote inspections as an available option, which on a small trade item can save a site visit entirely — ask whether your scope qualifies.
Want this handled start to finish?
Get a free quote →Burlington permit application: how to apply step by step
Here is how to get a building permit in Burlington, from confirming the requirement through to close-out. Each step below corresponds to a real decision point where projects commonly stall.
Inspections for building and trades; Planning for fences, sheds, pools, signs, and historic COAs; Engineering for driveways; Fire for fire permits.
If you are working on behalf of a company, call Inspections or Planning for an access code before creating your BurlingtonSmart account.
A Certificate of Appropriateness from the Historic Preservation Commission is required for exterior work and tree removal in a local historic district.
Apply, track approvals, and pay fees in the portal. Avoid uploading digitally signed or protected PDFs.
After initial review, staff comments are incorporated into a markup set of plans that must be addressed before approval.
Requests before 4 p.m. are scheduled the following business day; after 4 p.m. they go two business days out.
Inspections in Burlington
Burlington inspections are scheduled through BurlingtonSmart, and the timing rule has real teeth: requests before 4 p.m. are scheduled the following business day, and requests after 4 p.m. are scheduled two business days from the request.
The department follows the statutory requirement that an inspector conduct all inspections requested by the permit holder for each scheduled inspection and inform the permit holder of instances where the work fails to meet the code — and publishes an Informal Review Policy under G.S. 160D-1104(e) for disagreements. If the local inspection department will not inspect within two business days of the request, the permit holder may ask the State Fire Marshal in writing to send an inspector (G.S. 143-139.4). G.S. 160D-1104 also requires the inspector to carry out every inspection requested for a scheduled visit and to point out each part of the work that fails the code.
State law sets how long a North Carolina permit stays valid and when changes need written approval. North Carolina rules
Burlington permit search and official resources
Open BurlingtonSmart, reach the Inspections Department, or find the applications list with the official links below.
- City of Burlington Inspections & Permits
- BurlingtonSmart portal
- Burlington applications
- Burlington Inspections policies
- NC Licensing Board for General Contractors
- LiensNC — designate a lien agent (jobs of $40,000 or more)
Inspections are where schedules slip.
Get a free quote →Frequently asked questions
Who issues building permits in Burlington, NC?
The City of Burlington Inspections Department, at the Municipal Building on South Lexington Avenue. Alamance County permits outside the city, and Graham runs its own department as well.
When do I need to request a Burlington inspection?
Before 4 p.m. Requests made before 4 p.m. are scheduled the following business day; requests made after 4 p.m. are scheduled two business days from the date of request. 15 minutes late costs a full day.
Do I need an access code for BurlingtonSmart?
If you are working on behalf of a company, yes — contact Inspections on (336) 222-5080 or Planning on (336) 222-5110 for an access code before creating your account. Registering without one creates the wrong kind of account.
Which Burlington department handles fences, sheds, and pools?
The Planning Department, not Inspections. New driveways go to Engineering, fire permits to the Fire Department, and special events to the Special Events Division. Permits are distributed across four departments here.
Do I need a Certificate of Appropriateness in Burlington?
In a locally designated historic district, yes — for exterior work and, notably, for tree removal. The COA is approved by the Historic Preservation Commission and issued by the Planning Department.
Does Burlington offer remote inspections?
The Inspections Department publishes live-remote inspections as an available option alongside its Informal Review Policy and Inspections Refund Policy. On a small trade item that can save a site visit — ask whether your scope qualifies.
What is Burlington's Informal Review Policy?
A published internal process under G.S. 160D-1104(e) giving a permit holder a defined route to raise a disagreement about an inspection result short of a formal appeal, starting with review by the inspector’s supervisor. State law requires every inspection department to have one.
Can I upload a signed PDF to BurlingtonSmart?
Avoid it. The city asks applicants not to upload digitally signed or protected PDFs, which the portal does not handle reliably. Flatten the file before submitting.
Does Burlington still require business licences?
Mostly no — with a few exceptions, businesses do not need a licence to operate in Burlington. Beer and wine licences, taxicab licences, and solicitor-peddler registration are still required.
Is Burlington, NC the same as Burlington, Vermont?
No — different states entirely. Burlington, North Carolina is in Alamance County between Greensboro and Durham. Burlington, Vermont sits on Lake Champlain, and there are Burlingtons in Iowa, Massachusetts, New Jersey, and Wisconsin.
When is a general contractor licence required in Burlington?
On projects of $40,000 or more, under G.S. 87-1 and the NC Licensing Board for General Contractors, with tiers capping single-project value at $750,000, $1,500,000, or without limit excluding land cost.
What is a markup set in Burlington?
After an initial review, staff comments on a plan set are incorporated into what the city calls a markup set, which must be addressed before approval. Watch for it in the portal rather than waiting for a call.
Simplify Burlington permitting with Alliance Permitting
Four departments issuing permits, an access code you need before you register, a portal that rejects signed PDFs, and a four o'clock cutoff that costs a whole extra day — Burlington is well-run and unforgiving of improvisation. A permit expediter for Burlington knows which department owns what and files inside the window.
Trusted by leading builders, developers, and national contractors — 21+ years of filing in the jurisdictions we write about.
Contractors and builders choose Alliance for Burlington because the work is done by people who have stood at the counter:
- Right department, first time — Inspections, Planning, Engineering, or Fire, depending on the record.
- Inside the window — inspections requested before 4 p.m. so they land the next day, not the day after.
- Complete oversight — every Burlington permit and inspection tracked across your jobs in one place.
Alliance Permitting is a permit documentation and expediting service. We are not a law firm and do not provide legal advice, and we are not the permitting authority.
Ready to break ground in Burlington sooner?
Let Alliance prepare, file, and track your Burlington permits while your crew stays on the job.