Outside the Village of Massena, building permits come from the Town of Massena Code Enforcement Office, Room 3 of Town Hall at 60 Main Street (315-769-3588 ext. 11). Residential, commercial and roofing permits can be filed through the town’s iWorQ portal, which also has a permit search and a map of permits. The Town Board sets permit fees by resolution and keeps the schedule with the Town Clerk, and a permit gives you six months to start work.
What requires a building permit in Massena?
The town’s printable forms map the work it permits: residential and commercial building permits, roofing and siding, swimming pools, fences, electrical work and site plans, with building guides for additions, garages, finished basements and decks. The residential application covers new buildings, conversions, additions, alterations, repairs and replacements, relocation, demolition, fences, signs and in-ground or above-ground pools.
Town permit forms
- New homes, additions, garages and finished basements
- Alterations, repairs, relocation and demolition
- Roofing and siding
- Swimming pools, in-ground or above-ground
- Solid fences, and open fences over 4 feet
- Electrical work: services, fire alarms, electric heat
- Commercial buildings and site plans
Without a fence permit
- Open lattice, picket, rail or wire fences up to 4 feet tall
- No fence may exceed 6 feet
- Barbed wire and electric fences only on working farms or lots of 7 acres or more
Massena’s zoning law (Chapter 207, adopted 2009) controls where things go. An accessory building may stand in a side or rear yard if it is no taller than 25 feet; in the R-1 district it sits 5 feet from the rear line and 10 feet from the side line, and in the R-A district 10 feet from the rear and 7 from the side, in both cases at least 50 feet from the right-of-way or 108 feet from the road center, and all accessory buildings together may cover no more than 30% of the required yard. Solid fences belong in side or rear yards, need a permit, may be up to 6 feet tall and must stay at least 2 feet off every lot line with the finished side facing out. At street corners nothing over 30 inches may stand within the 30-foot sight triangle.
What Massena decides and what the state sets
The Uniform Code and Energy Code set the construction standards. The town decides its fees and permit time limits (Chapter 109), zoning (Chapter 207), flood damage prevention (Chapter 131), solar rules (Chapter 186) and, since September 2024, where commercial cryptocurrency mining may operate (Chapter 120).
Short on time to read all of this?
Get a free quote →Massena building department: who handles permitting
The Town Code Enforcement Office issues building permits, inspects construction, handles code complaints and carries out yearly fire inspections of businesses and inspections of apartments. Its code enforcement officer is Patrick O’Brien, certified through the New York Department of State. The office is in Room 3 of Town Hall, the building the town shares with the village.
| Area | Office |
|---|---|
| Town outside the village | Town Code Enforcement, 60 Main Street, Room 3; 315-769-3588 ext. 11; fax 315-769-7957 |
| Town online filing | Town of Massena iWorQ permit portal |
| Village of Massena | Village Code Enforcement Division (Village Fire Department); code secretary 315-769-6803 |
Village of Massena. The village holds 9,898 of the town’s 12,058 residents (Census 2025 estimate) and runs its own code enforcement through the career firefighters of the Village Fire Department, with its own portal, permit forms, zoning code and boards, and a rental registration rule adopted in October 2023. Town permits cover only the roughly 2,200 residents outside the village.
Massena permit types and filing rules
Residential permits
Residential, commercial and roofing permits can be filed in the iWorQ portal; for a residential or commercial building permit, first download the town’s attachment from the portal (the residential one is filled in and uploaded with the plans). The February 2024 paper forms remain available for every permit type. The residential application asks for the project location and tax map number, owner, designers and contractors, the estimated cost, a lot drawing showing where the work goes, the materials list and truss information. No permit issues without current workers’ compensation and disability insurance certificates attached or on file.
Plans must carry an architect’s or engineer’s stamp unless the job falls within the Education Law exceptions printed on the form: farm buildings, a single-family house of 1,500 square feet or less (not counting garages, porches, cellars or unfinished attics), or alterations costing $20,000 or less that do not affect structural or public safety. The town’s pool form asks for a survey map showing the pool, hot tub or spa, the barrier and any heater, and for the barrier type: a fence at least 48 inches high, a locking safety cover or alarms on doors and the pool. The deck building guide shows guards with openings small enough that a 4-inch sphere cannot pass and stair handrails 34 to 38 inches above the nosings. The fence form needs the material, height, total linear feet and setbacks on all four sides, with a dimensioned sketch; the roofing and siding form counts work in squares of 100 square feet.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial work uses its own application and usually the Planning Board’s site plan application and planning packet. Since Local Law 3 of 2024, commercial cryptocurrency mining is allowed only in industrial zones, with site plan approval and a special use permit, a containment building of at least 700 square feet designed by a New York licensed engineer and noise held below 60 decibels at the lot line. Businesses receive yearly fire inspections from the town office. On September 16, 2026 the Town Council voted 2 to 3 against a six-month moratorium on data center development (Resolution 147-2026), and on October 21 it hired engineering and legal reviewers for the proposed NCCS/NYDIG data center campus on County Route 45.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning: in the R-1 district lots need 30,000 sq ft and 150 feet of width, houses sit 50 feet from the right-of-way or 83 feet from the road center, 20 feet from side lines and 30 from the rear, cover no more than 25% of the lot, and have at least 850 sq ft of living space.
- Planning Board: subdivision and site plan approval starts with a meeting with the code enforcement officer, who walks you through the town’s flowcharts, then a presubmission conference with the board; the request form must reach the officer at least 10 days before the meeting. Engineered drawings are not required for this stage, and the board accepts neat, legible hand-drawn plans that show the required information. Variances go to the Town Zoning Board.
- Flood zones: the town takes part in the National Flood Insurance Program under a 1986 flood map with no base flood elevations determined (Zones A, C and X only).
- Sewer: tapping a public sewer needs a permit from the Town Clerk ($3 on a dirt or macadam road, $5 on a paved one).
Massena building permit fees
Under Section 109-9 the Town Board sets building permit fees by resolution and keeps the current schedule on file with the Town Clerk; the town has not posted it online. The permit forms leave the fee blank, and the electrical, fence and roofing forms record a project valuation next to it. Section 109-18 of the code does fix the charges that come with a permit.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Building permit | Town Board schedule, on file with the Town Clerk |
| Inspection requested outside business hours | $15 per hour, 2-hour minimum, on top of the permit fee |
| Plan review where no permit is requested | 50% of the permit cost |
| Extra plan review for changes to approved plans | $15 per hour |
| Application not approved, no work started | 50% of the fee refunded |
| Permit renewal | $10 or 10% of the original fee, whichever is larger |
| Certificate of occupancy | Free with a permit in effect; otherwise $25 (one- and two-family) or $100 |
| Temporary certificate of occupancy | $10; $100 for the third and later |
Ask the Code Enforcement Office or the Town Clerk for the current schedule before you budget. A renewal on a permit that cost $300 is $30, and on one that cost $80 the $10 minimum applies.
Trade permits and who may pull them
Electrical. Massena issues its own electrical permit through the Building Department, on a form that covers new services, service changes, fire alarms, electric wall heaters and furnaces and construction meters, with a valuation and a permit fee. The residential application adds that all permitted electrical work must be inspected at the owner’s expense. The form asks for the contractor’s license number, but neither the Town Code nor the town pages set up a local electrician license.
Plumbing and heating. Plumbing, mechanical and fuel gas work is enforced by the town office under the state codes, and building systems, including underground and rough-in work, are an inspection stage on every residential permit.
Septic and wells. The town’s pages do not describe a septic permit of their own. The State Health Department’s Canton District Office, 58 Gouverneur Street, Canton (315-386-1040), is the state health office for St. Lawrence County; call it about private wells and septic systems before designing one.
Contractors. The town requires workers’ compensation and disability insurance certificates with every permit. It has no contractor licensing law of its own.
Rather not deal with the building department?
Get a free quote →How to apply for a Massena building permit
Village of Massena parcels go to the village office.
Setbacks, accessory limits and any Planning Board step.
Lot drawing, materials list, truss data, stamped plans if required.
Upload the town attachment and plans, or file the paper form at Room 3.
The permit is valid once approved and paid.
Then book inspections 48 hours ahead.
Review, corrections and what causes delay
The town publishes no review time, and its application warns that an incomplete application may delay the permit; it asks applicants to write N/A in any section that does not apply rather than leave it blank. Changes to approved plans bring added plan review at $15 an hour. A permit authorizes work for six months from issue; for good cause the code officer can grant up to two extensions of three months each, after which a renewal is needed.
Massena inspections and certificates
The owner is responsible for calling the Building Department, Monday to Friday between 8 am and 4 pm, at least 48 hours before an inspection is wanted. The application lists the stages: the site before the permit issues, footings and foundation, slab preparation, framing, building systems including underground and rough-in work, fire-resistant construction and penetrations, solid-fuel appliances and chimneys, Energy Code compliance and a final inspection. Covering work before it is inspected can mean opening it up again at the owner’s expense. Inspections outside business hours cost $15 an hour with a two-hour minimum.
The town’s forms page also posts a certificate of occupancy checklist whose items, from exit signs and emergency lighting to fire extinguishers, alarm testing and a posted street address, show what inspectors look for in commercial space. A certificate is free while the permit is in effect.
New York building code
New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York
Want this handled start to finish?
Get a free quote →Massena permit FAQ
Does the town issue permits inside the Village of Massena?
No. The village runs its own code enforcement through the Village Fire Department; call its code secretary at 315-769-6803.
Can I apply online in the Town of Massena?
Yes, residential, commercial and roofing permits through the town’s iWorQ portal; other permits use the printable forms.
How much is a building permit?
The Town Board’s fee schedule is kept by the Town Clerk and is not posted online, so ask the code office for the fee on your project; renewals and certificates are priced in the Town Code.
Do I need a permit for a fence?
Yes for any solid fence and for open fences over 4 feet; no fence may be taller than 6 feet.
Do I need a permit for a swimming pool?
Yes, for in-ground and above-ground pools; the form asks for a survey map and the barrier you will use, such as a fence at least 48 inches high or a locking safety cover.
How close to the lot line can a garage or shed go?
In the R-1 district, 5 feet from the rear line and 10 feet from the side line, and at least 50 feet from the right-of-way; accessory buildings may be up to 25 feet tall.
How long do I have to start work?
Six months from the permit date, with up to two three-month extensions for good cause.
Do I need an architect or engineer?
Not for a single-family house of 1,500 sq ft or less, farm buildings, or non-structural alterations costing $20,000 or less; otherwise yes.
How do I look up an existing permit?
Search by permit number in the iWorQ portal or use its map view; permit records are also open for inspection at the office.
Permit search and official resources
The town’s iWorQ portal has a permit search by permit number and a map of permits by parcel; the portal notes that a contractor access code may be asked for. Section 109-5 makes the code office’s permits, certificates and inspection reports public records open to inspection during business hours; for copies, ask the office or file a Freedom of Information request with the Town Clerk.
Inspections are where schedules slip.
Get a free quote →- Town Code Enforcement Office
- Town of Massena iWorQ permit portal and search
- Printable town permit forms
- Residential building permit application
- Commercial building permit application
- Town electrical permit
- Fencing permit
- Town Code Chapter 109, Building and Fire Prevention
- Town Code Chapter 207, Zoning
- Town Code Chapter 120, Cryptocurrency Mining Operations
- Village of Massena code enforcement
- NYS code adoption notice
Simplify Town of Massena permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Town of Massena sooner?
Let Alliance prepare, file, and track your Town of Massena permits while your crew stays on the job.
More New York permitting guides
St. Lawrence County
Read guide →Town of Canton
Read guide →City of Watertown
Read guide →City of Middletown Building Permit Guide
Read guide →Town of Milton Building Permit Guide
Read guide →Village of Mineola Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Town of Massena permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.