In the Incorporated Village of Lynbrook, the village Building Department, led by Superintendent Brian Stanton, reviews plans and issues building permits, not the Town of Hempstead. A complete application carries a notarized owner’s signature, two sets of stamped plans, two surveys and a $75 nonrefundable application fee, and every electrician and plumber on the job must be licensed and registered with the village.
What requires a building permit in Lynbrook?
Chapter 81 of the Village Code requires a permit before anyone erects, enlarges, alters, removes or demolishes a structure, and before installing any fence or swimming pool. The Building Department’s own list shows how far that reaches.
Building Department permits
- New dwellings, garages and commercial buildings
- Alterations and extensions: decks, dormers, side or rear extensions, skylights
- New or replacement fences
- In-ground or above-ground pools, with a code-compliant fence
- Demolition
- Plumbing and mechanical work, and tank installation or removal
- Signs (permanent, temporary or change of copy), awnings and canopies
- Temporary trailers
Street and Public Works permits
- Sewer connections and disconnections
- Sidewalks and curbs ($25)
- Street openings
- Dumpsters in the street (none if it sits in your driveway)
- Tree removal (no-fee permit from Public Works, 548 Merrick Road, 516-599-8838)
The code exempts only repairs that leave structural features, fire-safety items such as smoke detectors, sprinklers and exits, and electrical systems untouched and do not add a wood or coal stove or chimney. A pool is any outdoor body of water deeper than 22 inches; it must sit in the rear yard, at least 4 feet from the rear and side lines and 8 feet from the house. Fences in the residential districts may reach 6 feet along the rear yard, with lower limits toward the street shown on the village’s fence diagram, and every fence must sit fully inside the property line, footings included, with its finished side facing the neighbor or street. Fences at a corner must be an open type such as picket or chain link, and the 6-foot setback for a high fence along a corner street can be cut to 2 feet only with Architectural Review Board approval.
What the village decides and what the state sets
Construction standards come from the 2025 Uniform Code and Energy Code, which Chapter 81 enforces; stricter technical rules would need state Code Council approval. Lynbrook’s own controls are its zoning code (Chapter 252), Architectural Review Board design review, the fence, pool, electrical and plumbing chapters, its fire limits, flood damage prevention (Chapter 130) and the fees the Board of Trustees sets by resolution.
Short on time to read all of this?
Get a free quote →Lynbrook building department: who handles permitting
The Building Department reviews plans, issues permits and certificates, inspects work and enforces the code on existing buildings, including the village’s over-occupancy rules. Brian Stanton is the Building Department Superintendent, and the Superintendent also acts as secretary to the Architectural Review Board. The Board of Trustees approved iWorQ software for an online permit system in March 2025, and in February 2025 it raised the over-occupancy fines and allowed a certificate of occupancy to be revoked for over-occupancy (Local Law 1 of 2025). Forms that are not online can be picked up at the office, to the right of the main stairs on Village Hall’s lower level.
| Detail | Information |
|---|---|
| Office | Building Department, Village Hall lower level, 1 Columbus Drive, Lynbrook, NY 11563 |
| Phone | 516-599-8828 (fax 516-593-8309) |
| Hours | Monday to Friday, 8 a.m. to 4 p.m. |
| Superintendent | Brian Stanton |
| Online portal | iWorQ citizen portal (marked under construction) |
| Area served | The Incorporated Village of Lynbrook |
Lynbrook is an incorporated village inside the Town of Hempstead, and work inside its limits is permitted by the village, not by the town’s Department of Buildings. The village links an iWorQ citizen portal for online applications, but the portal currently says it is under construction, so applications are filed at the office.
Permit types and submission requirements
Residential permits
The 2026 residential building permit application is not accepted until it is complete. It needs the owner’s notarized signature, the signed Nassau County assessment form, the $75 application fee, two sets of architect’s or engineer’s drawings, stamped and signed with the zoning setbacks on the front page, a digital copy of the plans by email, and two copies of the property survey. The same package carries the plumbing permit application and the mechanical permit application, both signed by the homeowner, the electrician’s third-party inspection application, the contractors’ workers’ compensation and liability certificates naming the village as holder, and a copy of the contractor’s Nassau County Consumer Affairs license. The stated cost must be accurate or the application will not be reviewed, and a homeowner may act as contractor only on an owner-occupied property. Fences use their own permit with two copies of the survey for anything over 3 feet.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
The commercial application uses the same checklist plus a code data worksheet. No frame or other combustible building may be put up inside the village’s fire limits, which cover listed blocks along Merrick Road, Hempstead Avenue, Union Avenue, Broadway and other streets and every Industrial, Commercial and Light Manufacturing district. Commercial fences may be 6 feet high, with barbed wire on the owner’s side only in the Light Manufacturing and Industrial districts. Places of assembly, buildings open to the public and common areas of multiple dwellings are inspected every 12 months, and other commercial and industrial buildings every 24 months.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
Any building or sign permit that changes a building’s exterior appearance is referred to the Architectural Review Board, whose public hearing calendar is published at least a week ahead. Solar installers must submit two color renderings of the panels on the roof, and the homeowner must attend the hearing. Variances go to the Zoning Board of Appeals with ten copies of the application, floor plans, short environmental assessment form, denial letter, survey, photographs and a list and radius map of owners within 200 feet; notices are mailed 10 to 20 days before the hearing, and corporations must appear through an attorney. The Board of Trustees itself hears special use permits at a public hearing (it approved one for basement parking at 831 Sunrise Highway on March 30, 2026) and has been granting demolition permits for houses by resolution, such as the January 12, 2026 permit for 110 Stella Court, which was made subject to Zoning Board and Architectural Review Board approval of the replacement house. In a mapped flood zone, the Superintendent of Public Works issues a floodplain development permit, and new or substantially improved buildings need the lowest floor at least 2 feet above the base flood elevation. FEMA lists the village as a participating community in the flood insurance program, with its current flood map dated September 11, 2009.
Lynbrook permit fees
Chapter 81 leaves building permit fees to resolutions of the Board of Trustees, and the application asks for an accurate cost of the work, which the department uses in its review. The village’s own pages and forms print these amounts:
Rather talk it over?
Call 1-855-478-4290 →| Item | Amount |
|---|---|
| Building permit application (residential or commercial) | $75, nonrefundable |
| Sidewalk and curb permit | $25 |
| Tree removal permit (Public Works) | No fee |
| Master electrician license | $200 new; $100 renewal |
| Plumber license | $200 for two years; $150 two-year renewal |
| Plumber bond for sewer work | $2,000 |
| Demolition security | Cash, certified check, letter of credit or bond, amount set by the Superintendent |
| Over-occupancy, first offense | $3,500 minimum fine |
| Over-occupancy, second offense | $5,000 minimum fine |
| Zoning code violation / village code violation | $350 / $250 |
Because the application fee is charged up front and is not refunded, a rejected or abandoned filing still costs $75.
Trade permits and who may pull them
Electricians. Every electrician working in Lynbrook must hold a Lynbrook master electrician’s license. To get one, an electrician files a notarized application with a current license and certificate of competency from the Town of Hempstead, the Town of North Hempstead or the Town of Oyster Bay (both from the same town), a letter of good standing, and liability and workers’ compensation certificates. Under Chapter 112 no electrical work may begin until a copy of the application for inspection, addressed to one of the inspection agencies the Board of Trustees has approved, is on file with the Building Department; the village’s License Board recommends the approved agencies every two years.
Plumbers. Plumbers must also be licensed and registered with the village, on a two-year license, presenting a license and certificate of competency from a town, city or village honored under the Tri-Town Agreement (the towns of Hempstead, Islip, North Hempstead and Oyster Bay, the cities of Glen Cove and Long Beach, and a list of villages). Sewer work needs a $2,000 bond. Water pipe and boiler connections on a mechanical permit must be made by a village-licensed plumber. The mechanical form adds local installation rules: fireproofing over a boiler must run from the brick chimney to at least 3 feet in front of the burner and 3 feet to each side, every new or old domestic water heater needs a safety relief valve, and any carbon-producing unit needs smoke and carbon monoxide detectors.
Home improvement contractors. Building and fence contractors must show a Nassau County Department of Consumer Affairs license; the county licenses every residential home improvement business and fingerprints its licensees. A homeowner installing his or her own fence files a workers’ compensation affidavit instead.
Rather not deal with the building department?
Get a free quote →How to apply for a Lynbrook building permit
Confirm setbacks on the survey and whether the work changes the exterior and so goes to the Architectural Review Board.
Use an electrician and plumber registered with the village and a county-licensed contractor.
Notarized application, county assessment form, two sets of stamped plans and surveys, trade applications and insurance.
Deliver it to the Building Department, email the digital plans, and pay the $75 application fee.
Attend the ARB or Zoning Board hearing if the department refers the job.
Display the permit, book inspections and apply for the certificate with a new survey.
Review, corrections and what causes delay
Incomplete applications are refused at the counter, and an application with an inaccurate cost is not reviewed. If plans do not meet the code, the Superintendent returns them and will give the reasons in writing on request. A permit requires the work to start and finish within 12 months, with up to two three-month extensions for good cause; a permit under which no work starts within 12 months expires. Plumbing and mechanical permits also expire one year after issuance, and the village warns that plumbers with expired or open permits lose good standing.
Lynbrook inspections and certificates
The owner or permit holder calls the Building Department when each stage is ready; the code calls for inspection before anything is covered, covering foundations, structure, electrical, plumbing, heating, insulation, ventilation, fire protection and exits. Plumbing and mechanical inspections are booked for Monday or Thursday between 8:30 and 9:30 a.m., and the plumber must be on site. Electrical inspections are made by the approved agency named on the electrician’s application, and the village relies on its written certificate.
A new building cannot be used until a certificate of occupancy is issued, and an altered or enlarged building cannot be used for more than 30 days after the work ends without a certificate of completion; a change of use needs its own certificate. Each certificate application must include a survey by a licensed engineer or land surveyor at a scale of 20 feet to the inch or larger. A temporary certificate of occupancy lasts three months and can be renewed twice.
New York building code
New York builds on one statewide code, the Uniform Code, outside New York City; the 2025 edition and 2025 Energy Code took effect on 31 December 2025 (the all-electric provisions remain suspended by court order). Cities, towns and villages administer it, and local standards stricter than the code need Code Council approval. The Uniform Code in New York
Want this handled start to finish?
Get a free quote →Lynbrook permit FAQ
Do I need a permit for a fence in Lynbrook?
Yes, for any new or replacement fence; anything over 3 feet needs two copies of the survey, and corner-lot fences over 4 feet close to the street go to the Architectural Review Board.
Can I apply online?
Not yet: the village’s iWorQ portal is marked under construction, so applications are filed at the Building Department in Village Hall.
Can I do my own work as a homeowner?
Only on a property you live in, and plumbing and electrical work still has to be done by trades registered with the village.
Does a pool need a permit?
Yes, for water deeper than 22 inches, placed in the rear yard at least 4 feet from the side and rear lines and 8 feet from the house.
Do solar panels need design review?
Yes. Installers submit two color renderings, and the homeowner must attend the Architectural Review Board meeting.
How long is a permit good for?
Twelve months, with up to two three-month extensions for good cause.
Do I need a permit to take down a tree?
Yes, a no-fee tree removal permit from the Department of Public Works at 548 Merrick Road.
Permit search and official resources
Lynbrook has no working online permit search. Permit files, certificates of occupancy and surveys are requested from the village’s Records Access Officer at 1 Columbus Drive on the Application to Examine Public Records; a denial can be appealed in writing to the Mayor within 30 days.
Inspections are where schedules slip.
Get a free quote →- Lynbrook Building Department
- Forms and documents
- 2026 residential building permit application
- 2026 commercial building permit application
- Fence permit and requirements
- Plumbing permit application
- Mechanical permit application
- Electrician’s registration application
- Plumber’s registration application
- Variance application (July 2026)
- Village code for swimming pools
- Architectural Review Board
- Zoning Board of Appeals
- Village Code Chapter 81, Building Construction and Fire Prevention
- Village Code Chapter 112, Electrical Standards
- Village Code Chapter 144, Hedges and Fences
- Application to examine public records
- Nassau County home improvement licensing
- NYS Department of State code adoption notice
Simplify Village of Lynbrook permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in New York. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Village of Lynbrook sooner?
Let Alliance prepare, file, and track your Village of Lynbrook permits while your crew stays on the job.
More New York permitting guides
Village of Freeport
Read guide →Village of Garden City
Read guide →City of Glen Cove
Read guide →Town of Lysander Building Permit Guide
Read guide →Town of Malone Building Permit Guide
Read guide →Town of Mamaroneck Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Village of Lynbrook permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.