Skip to main content
Municipal GuideNebraskaPapillion · Sarpy County

Papillion, Nebraska Building Permit Guide

Papillion’s Building & Fire Safety Department at City Hall, 122 E. Third Street, permits and inspects construction in the city and its two-mile extraterritorial jurisdiction, with applications filed in the Accela online portal.

Authority: Papillion Building & Fire Safety DepartmentCode: 2018 I-Codes, 2023 NEC (Ordinance 2087)Phone: 402-597-2029
Authority
Building & Fire Safety Department
Filing
Accela online permit portal
Plan review
70% of the building permit fee
Inspections
Hotline 402-597-2072, by 4:30 p.m. the day before

Papillion’s Building & Fire Safety Department issues building, electrical, mechanical and plumbing permits for the city and the land within two miles of its limits, and applications are filed in the City’s Accela portal. Fees follow the Master Fee Schedule adopted by Resolution R26-0152 on August 4, 2026: a project valued at $300,000 carries a $2,456.85 building permit fee, and plan review adds 70% of that when plans are reviewed.

What needs a permit in Papillion?

Papillion re-adopted its building codes with local amendments in Ordinance No. 2087, passed on third reading on June 16, 2026. The amendments rewrite the residential code’s list of work that needs no permit, and the City publishes submittal lists for each common project in its portal.

Permit required

  • New homes, townhouses, large homes and commercial or multifamily buildings
  • Additions, remodels and basement finishes
  • Decks, detached garages, sheds, drives and patios, fences and pools (Accessory Use application)
  • Roof replacement of 50% or more of a side or of the total roof
  • Signs, curb cuts, storage tanks, grading, moving and demolition
  • Electrical, mechanical and plumbing work, each on its own permit

Exempt under Ordinance 2087

  • One-story detached sheds and similar buildings up to the IRC’s 200 sq ft, only when in the rear yard and under 10 feet tall
  • Fence repairs on the line of an existing approved fence, within zoning heights
  • Replacement sidewalk or driveway slabs with no added area or grading change
  • Soft-sided pools under 18 inches deep
  • Swings, playhouses and playground equipment
  • Siding repair or replacement; roofing under 50% of a side and of the roof

Who issues permits in Papillion?

The Building & Fire Safety Department handles plan review, inspections and code enforcement for Papillion and its two-mile extraterritorial jurisdiction; Brad Sojka is the Director of Building & Fire Safety. The department also enforces the NFPA 101 Life Safety Code and other state-adopted fire codes as the State Fire Marshal’s delegated authority. Land in Sarpy County beyond Papillion’s two-mile line is the Sarpy County Planning and Building Department’s unless another city’s zoning area covers it.

Short on time to read all of this?

Get a free quote →
Papillion Building & Fire Safety contact
DetailInformation
OfficeCity Hall, 122 E. Third Street, Papillion, NE 68046
Office phone402-597-2029
Inspections hotline402-597-2072
Emailinspections@papillion.org
PortalAccela Citizen Access (account required)

Papillion online filing and forms

All building permits go through the Accela portal: create an account, submit the application and documents, and pay there. Some simple permits are issued automatically; others go to plan review, and staff call the contact on the permit once plans are approved. The permit is issued when payment is received, by card in the portal (3% convenience fee, $1 minimum) or by cash or check at the office or by mail.

The forms page and the portal’s submittal pages cover new single-family homes, residential additions and remodels, accessory uses (fence, shed, deck, re-roof, pool, garage), commercial and multifamily buildings, change of occupancy, electrical, mechanical, plumbing, fire sprinkler and alarm, grading, moving, demolition and signs. New homes and commercial buildings need the Nebraska Energy Code Certification form, and commercial jobs add a Papillion Fire Review Form.

Papillion permit fees

The building permit fee is based on the total value of the work, including site work, foundations and all trades but not land. Staff compare the declared value with the adopted ICC Building Valuation Data table and charge on whichever is greater. Rates come from Table 3-A of the Master Fee Schedule (Resolution R26-0152, adopted August 4, 2026).

Not sure this scope needs a permit?

Get a free quote →
Papillion building permit fees (Resolution R26-0152)
ProjectFee
Valuation $1–$500$27.50
Valuation $100,001–$500,000$1,162.85 plus $6.47 per additional $1,000 or fraction
Valuation $500,001–$1,000,000$3,631.44 plus $5.49 per additional $1,000 or fraction
Valuation over $1,000,000$6,376.44 plus $3.99 per additional $1,000 or fraction
Plan review70% of the building permit fee, or a third-party reviewer’s invoice if greater
Commercial fire plan review5% of the building permit fee, $1,000 maximum
Re-inspection after a second / third straight failed inspection$52 / $100
After-hours or weekend inspection$100 an hour, 2-hour minimum
Change of occupancy; demolition$100; $50
Work without a permit3 times the permit fee, after one warning

For example, a project valued at $300,000 has a building permit fee of $1,162.85 plus 200 × $6.47, or $2,456.85. Where plans go to review, the plan review fee of 70% is paid when the construction documents are submitted. The City refunds 90% of a permit fee if work has not started and the refund is requested within six months of issue.

Development charges on new homes: the schedule’s latest Arterial Street Improvement Program column (FY 2025–2026) charges 77.9 cents per total square foot for single-family homes, townhouses and duplexes, counting above-grade floors, the basement and the garage. A capital facilities charge of $1,675 (north of the ridgeline) or $3,500 (south) per equivalent residential unit applies by water pressure zone. Sewer connection is $1,300 per single-family unit in the City’s outfall areas; in Sarpy County outfall areas the county collects it, and proof of payment is needed before a building permit for a new primary structure.

Electrical, plumbing and mechanical permits in Papillion

Papillion runs its own electrical inspection program and appears on the State Electrical Division’s list of municipal programs, so electrical permits and inspections inside its jurisdiction are the City’s. Electrical contractors must hold a State of Nebraska licence. A homeowner who lives in a single-family house may wire it after signing the Homeowner Verification form at the office; that permit is valid for 180 days. Only a resident homeowner may act as the contractor on mechanical and electrical permits.

Rather talk it over?

Call 1-855-478-4290 →
Papillion trade permit fees (Tables 3-B to 3-D)
PermitFee
Issuance, each electrical, mechanical or plumbing permit$25 ($8 supplemental)
Electrical service up to 200 A$35.05
Outlets, switches and fixtures$1.25 each for the first 20, $0.90 after
Pre-connect inspection$27
Plumbing fixture$11 each
Water heater with vent$13.75
Furnace up to 100,000 Btu/h$17.05

Fire sprinkler and alarm systems need their own permit; residential fire sprinkler plan review and fire alarm plan review are $50 each, and commercial sprinkler review starts at $100 for 1–20 devices.

What to submit for a new house

  • Three sets of legible, scaled drawings: elevations, footing and foundation details, framing and beam locations, stairs, guards and decks, and trade layouts for a cursory review
  • Three site plans and three surveyor’s certificates (a surveyor’s certificate is required for any work on a new or vacant lot)
  • Three REScheck reports or IECC compliance, plus one Nebraska Energy Code Certification form
  • Gross areas for each floor, garage and finished and unfinished basement
  • The application with owner, contractor and building value; the older submittal sheet says to leave site work out, but the current Permit Fees page counts site work in the valuation used for the fee

Rather not deal with the building department?

Get a free quote →

Accessory projects need a site plan with setbacks to the rear and side lot lines and the house; separate permits cover any electrical, mechanical or plumbing work. Commercial and multifamily jobs follow the City’s Minimum Standards for Site and Building Plans and civil site plan guidance.

How to get a Papillion permit

1. Confirm the parcel is in Papillion’s jurisdiction

The city limits plus the two-mile extraterritorial area; beyond that, Sarpy County.

2. Open an Accela account

Register in the portal before starting an application.

3. Upload the submittal set

Use the document list for your project type on the Online Submittal Documents page.

4. Pay plan review if required

The 70% plan review fee is due when plans are submitted for review.

5. Pay and pick up the permit

Staff call when plans are approved; the permit issues once the fee is paid.

6. Build within 180 days

Permits lapse if work does not start within 180 days or stops for more than 180 days.

Papillion inspections

Request inspections through Accela, by email or on the hotline at 402-597-2072, by 4:30 p.m. the day before. Inspections are scheduled between 8:30 a.m. and 4 p.m., Monday to Friday; footing, foundation and sewer inspections get a set time, and the rest follow the day’s schedule. Give your name, phone, job address, the type of inspection and, for commercial work, the permit number.

Inspection types include footing, foundation wall, groundwork plumbing, rough-in framing, electrical, mechanical and plumbing, sewer connection, temporary power poles, electrical pre-connection and final. A house built with an optional fire sprinkler system needs a third-party inspection certificate at final.

Local Papillion details

Optional home sprinklers: Ordinance 2087 makes the IRC sprinkler section optional at the applicant’s choice; it sets installation rules only for owners who choose a system.

Want this handled start to finish?

Get a free quote →

Frost depth and site work: the amended IRC table uses a 42-inch frost line, and new or vacant lots need a surveyor’s certificate with the site plan.

Construction address sign: permitted additions, alterations and repairs must show a rigid address sign readable from the street for the whole job.

Zoning changes: Ordinance 2093, a rewrite of the zoning chapter to allow “Missing Middle” housing, is on the October 20, 2026 council agenda for third reading.

Nebraska building code

Nebraska's state building code applies by default where a city, village or county has adopted none; local codes must conform generally, and the energy code is mandatory statewide. Nebraska rules

Official Papillion resources

Inspections are where schedules slip.

Get a free quote →

Papillion permit FAQs

Who issues building permits in Papillion?

The Building & Fire Safety Department at City Hall, 122 E. Third Street, for the city and its two-mile extraterritorial jurisdiction. Call 402-597-2029.

How much is a building permit in Papillion?

It follows the valuation table in Resolution R26-0152. A $300,000 project pays $2,456.85, plus 70% of that for plan review when plans are reviewed.

Do I need a permit for a shed in Papillion?

Sheds go on the Accessory Use application. The IRC exemption for one-story sheds up to 200 sq ft applies in Papillion only when the shed is in the rear yard and under 10 feet tall; any other shed needs a permit.

Do I need a permit to replace my roof?

Yes when the work covers 50% or more of a roof side or of the whole roof; smaller repairs and siding replacement are exempt.

Can I do my own electrical work in Papillion?

Only in a single-family house you own and live in, after signing the Homeowner Verification form at the Building Department.

How do I schedule an inspection?

Through Accela, by email to inspections@papillion.org or on 402-597-2072, by 4:30 p.m. the day before.

Simplify Papillion permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Nebraska. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Papillion sooner?

Let Alliance prepare, file, and track your Papillion permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Papillion permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.