Itawamba County, Mississippi Building Permit Guide

Itawamba County, governed from Fulton, requires a county Floodplain Development Permit before any development in a mapped floodplain; Fulton, Mantachie and Tremont are separate towns.

Authority: Itawamba County Board of Supervisors (unincorporated area)Flood permits: Floodplain Division, 12 in. freeboardPhone: 662-862-5600
Board office
100/102 S. Clifton St., Fulton; 662-862-5600
Floodplain permit
Required before work; expires if not started in 6 months
911 addresses
Tax Assessor’s office, in person
Septic
Mississippi State Department of Health

Outside Fulton, Mantachie and Tremont, the Itawamba County Board of Supervisors governs, and state law requires it to require a permit for construction. The county’s own rule that applies most often is the Floodplain Development Permit: no development may start in a mapped floodplain until the county Floodplain Administrator issues one, and the finished building’s as-built elevation must show 12 inches of freeboard above the base flood elevation. Call the Board office at 100/102 South Clifton Street in Fulton (662-862-5600) or the County Administrator (662-862-4967).

Who issues permits in Itawamba County?

Three towns are incorporated: Fulton (4,640 residents, Census 2025 estimate), Mantachie (1,143) and Tremont (473). The rest of the county is unincorporated and under the five-member Board of Supervisors, which meets on the first Monday of each month and on the third Tuesday after it.

Short on time to read all of this?

Get a free quote →
Itawamba County permit contacts
Area or needContact
Unincorporated county: general questions and the county construction permitBoard of Supervisors office, 100/102 South Clifton Street (PO Box 68), Fulton, MS 38843; 662-862-5600. County Administrator, PO Box 355, Fulton; 662-862-4967
Development in a floodplain outside the townsFloodplain Division, 662-862-5600; the Emergency Management Director’s office is at 107 West Wiygul Street, Fulton
911 address for a new home or businessTax Assessor’s office (911 Addressing), 304 West Wiygul, Fulton; 662-862-5739; the application must be filled out in person
County roadsRoad Manager, through the Board office (662-862-5600)
FultonThe published sources do not say which city office issues permits; ask Fulton City Hall
Mantachie and TremontThe published sources do not say who permits in these towns; ask each town clerk
Septic systems where there is no sewerMississippi State Department of Health; wastewater call center 1-855-220-0192

House Bill 1163 of 2022 added §19-5-9(11) to the Mississippi Code, which makes every county require permits for construction in its unincorporated area whether or not it has adopted building codes. The permit must carry the contractor’s material purchase certificate or taxpayer identification number and licence number.

Steps for a project in Itawamba County

1. Check whether the site is in a town

Fulton, Mantachie and Tremont are separate municipalities; everything else is county land.

2. Check the flood map

The county’s flood insurance rate maps have been effective since November 28, 2025. If the site is in a mapped floodplain, file the county Floodplain Development Permit with an elevation certificate before any work.

3. Get a 911 address

Fill out the E-911 address application in person at the Tax Assessor’s office.

4. Ask the Board office about the county permit

Call 662-862-5600 or the County Administrator (662-862-4967) about the construction permit the county must require under state law.

5. Get septic approval

Without a sewer connection, the Mississippi State Department of Health must approve the onsite wastewater system.

6. Close out the flood permit

Submit the as-built elevation certificate; the building may not be used until the Floodplain Administrator’s final inspection and approval.

Not sure this scope needs a permit?

Get a free quote →

Floodplain permits and other local rules

Itawamba County takes part in the National Flood Insurance Program and enforces a Flood Damage Prevention Ordinance through its Floodplain Development Permit. The permit covers any development in a designated floodplain: buildings, additions and remodeling, demolition, fill, grading, paving, fences and retaining walls, placing a manufactured or mobile home, and storage of equipment or materials.

Rather talk it over?

Call 1-855-478-4290 →
Itawamba County Floodplain Development Permit: main terms
RuleRequirement
When to applyBefore any work; no work may start until the permit is issued
With the applicationSite plan, an Elevation Certificate by a certified engineer or surveyor (Section C completed) and scaled development plans
As-built elevation12 inches of freeboard above the base flood elevation, shown on an as-built Elevation Certificate
Additions and remodelsIf the work equals or exceeds 50% of the structure’s value, the whole structure must meet the ordinance
Relocated homes and cabinsTreated as new construction, including mobile and manufactured homes
Floodproofed non-residential buildingsCertification from a registered engineer or architect
ExpiryThe permit expires if no work has started within 6 months of issue
OccupancyNo use or occupancy until final inspection, final elevation and approval by the Floodplain Administrator
If the application is refusedThe Floodplain Administrator lists the deficiencies in writing; revise and resubmit, or request a hearing before the Board of Supervisors

FEMA lists Itawamba County, Fulton and Mantachie in the National Flood Insurance Program, all with maps effective November 28, 2025; Mantachie’s map shows flood zones without determined elevations. Tremont appears on FEMA’s list of Mississippi communities that are not in the program.

Septic systems: the Mississippi State Department of Health’s On-Site Wastewater program permits individual septic systems after a soil and site evaluation. Apply online or by fax, mail or e-mail; the fee is paid through a link the Department sends.

Rather not deal with the Itawamba County building department?

Get a free quote →

Mississippi building code

Some work is exempt statewide: farm structures once the owner files an affidavit (Mississippi Code §17-2-7), and manufactured housing built to federal standards, certain industrial and utility facilities, buildings on non-public fairgrounds and hunting or fishing camps with an owner’s affidavit (§17-2-9). None of these exemptions reaches floodplain rules. The state minimum codes are the Mississippi Building Code and Mississippi Residential Code, the residential code drawn from the 2021 International Residential Code. How building codes apply in Mississippi

Official Itawamba County permit resources

Want this handled start to finish?

Get a free quote →

Itawamba County permit FAQs

Do I need a permit to build in a floodplain in Itawamba County?

Yes. A county Floodplain Development Permit is required before any development in a designated floodplain outside the towns; call the Floodplain Division at 662-862-5600.

How high must a new building be in an Itawamba County flood zone?

The county requires 12 inches of freeboard above the base flood elevation, shown on an as-built Elevation Certificate.

How long is an Itawamba County floodplain permit good for?

It expires if no work has started within 6 months of issue.

Where do I get a 911 address in Itawamba County?

At the Tax Assessor’s office, 304 West Wiygul in Fulton, where the application must be filled out in person.

Inspections are where schedules slip.

Get a free quote →

Is Tremont in the flood insurance program?

No. FEMA lists Tremont among Mississippi communities not in the National Flood Insurance Program; the county, Fulton and Mantachie take part.

Who approves a septic system in Itawamba County?

The Mississippi State Department of Health, wastewater call center 1-855-220-0192.

Simplify Itawamba County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Mississippi. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Itawamba County sooner?

Let Alliance prepare, file, and track your Itawamba County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Itawamba County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.