Anoka County, Minnesota Building Permit Guide

Anoka County does not issue building permits or inspect permitted projects: each city does. Here are the building offices of Blaine, Coon Rapids, Andover and Fridley, plus the county’s road permits.

Authority: City building departmentsCounty role: Road access and right-of-wayLargest city: Blaine
Authority
City building departmentCounty issues no building permits
Blaine
763-785-6177iMS portal
Coon Rapids
763-767-6476BS&A Online
County roads
763-324-3100Access permits

Anoka County states that it does not issue permits nor inspect permitted projects; each city or jurisdiction issues and finals its own. Zoning and planning are handled by the cities and Linwood Township as well. The county’s municipality list names Andover, Anoka, Bethel, Blaine, Centerville, Circle Pines, Columbia Heights, Columbus, Coon Rapids, East Bethel, Fridley, Ham Lake, Hilltop, Lexington, Lino Lakes, Linwood Township, Nowthen, Oak Grove, Ramsey, Spring Lake Park and St. Francis. By the Census Bureau’s latest estimates the largest cities are Blaine (76603), Coon Rapids (64193), Andover (33874) and Fridley (30829).

This guide covers the building offices of the four largest cities and the permits the county itself issues for work on county roads.

What requires a building permit in Anoka County?

The Minnesota State Building Code applies statewide and supersedes local building codes, but Anoka County does not enforce it: each city (and Linwood Township) does. What changes from place to place is the office, how it takes applications and what it adds locally.

One local example: Coon Rapids no longer issues or inspects stand-alone radon mitigation permits (since August 10, 2020); those go to the Minnesota Department of Health.

Residential building contractors, remodelers and roofers, electricians and plumbers are licensed by the state Department of Labor and Industry, so the same credential is valid in Anoka County as anywhere in Minnesota. Building without a required permit exposes a job to stop-work orders, penalties and delayed occupancy, and unlicensed residential contracting is a separate violation enforced by the state. How Minnesota’s statewide code works

Short on time to read all of this?

Get a free quote →

Who handles permitting in Anoka County?

Each city issues and inspects its own building permits. The county’s role is its roads: the Highway Department, 1440 Bunker Lake Boulevard NW, Andover (763-324-3100), issues access permits and right-of-way permits, and development plans touching county roads go to its Development Review ((763) 324-3186).

Building offices of the four largest cities
CityOfficeContact and hours
BlaineBuilding Inspections Division, 10801 Town Square Drive NE763-785-6177; Monday - Friday 8AM - 4:30PM
Coon RapidsBuilding Permits & Inspections, City Hall, 11155 Robinson Drive NW763-767-6476; 8 a.m. to 4:30 p.m. M-F
AndoverBuilding Department, 1685 Crosstown Blvd NW763-755-8700; Monday - Friday 8 a.m. - 4:30 p.m.
FridleyBuilding Inspections Division763-572-3604; BuildingInspections@FridleyMN.gov

Local rules in the largest Anoka County cities

Blaine

The Building Inspections Division reviews plans, issues permits and inspects. Applications go through the city’s iMS system, where contractors register and resubmit license and insurance information. Residential plumbing, mechanical, roofing, siding and window replacement permits may be issued at the time of application. Septic owners must have an MPCA-licensed service provider file a Septic Tank Maintenance Reporting Form with the Inspections Department at least every three years.

Coon Rapids

Apply through the city’s BS&A Online portal, and call ahead before coming to City Hall in person. Allow 7-10 business days for Planning/Zoning approval of exterior permit applications.

Not sure this scope needs a permit?

Get a free quote →

Andover

Online applications go through the Baseline permit portal. Mechanical contractors (heating, ventilation, air conditioning, refrigeration, gas fireplaces and fuel piping) must hold an Andover Mechanical Contractor License. The city issues its own septic system permits.

Fridley

The Building Inspections Division administers the State Building Code, and all permits, for building, demolition, mechanical, plumbing and electrical work, must be applied for online.

Electrical permits in Anoka County

The electrical route differs between neighbouring cities. In Blaine, electrical permits and inspections are through the State Department of Labor and Industry (state electrical inspector: 612-528-2533). Andover’s electrical inspections are by Tokle Inspections, 763-421-2360 (M-F 7-8:30am). In Fridley, electrical inspections are scheduled separately with the electrical inspector.

Whether an electrical permit goes to the state Department of Labor and Industry or to the city depends on the area: if the state’s Authority Having Jurisdiction directory lists “State”, file with the state; if it lists “Local”, contact the city or township.

Electrical and plumbing work must be done by state-licensed trades, though an individual may do electrical work on a home they own and occupy if it has its own electrical service. Whether the electrical permit comes from the state or the local office depends on whether that city or township has taken on electrical inspection. Electrical and plumbing rules in Minnesota

Rather talk it over?

Call 1-855-478-4290 →

Anoka County permit costs and fees

Building permit fees are set by each city. Coon Rapids bases them on project valuation (materials and labor) and collects them when the permit is issued; since April 14, 2025 card payments carry a 2.95% service fee and ACH 2.50%, and no refund is available after 180 days. Andover’s online payments carry 2.9% plus $0.30 and a $10 technology fee on the first online payment per permit, with an $8,000 card limit.

County fees for work on county roads:

  • Access permits: Residential Single Driveway $175, Agricultural Field Access $175, Temporary Construction Access $250, Street Access/Connection $400, New Development/Commercial Driveway $400. A culvert pipe is generally required unless curb is present.
  • Right of Way permits (any work in the county right of way, including private sewer and water connections): Annual Registration $40; Utility, Obstruction and Excavation $250 each.

How to get a building permit in Anoka County

1. Find the city

The city where the parcel is issues and finals the permit; the county does not.

2. Check county road work

A new driveway or street onto a county road needs an Access Permit, after a site review by the county Traffic Department; work in the county right of way needs a Right of Way Permit.

3. Apply in the city system

Blaine through iMS, Coon Rapids through BS&A Online, Andover through Baseline, Fridley online.

4. Septic

Septic permits come from the city, not the county; Andover issues its own.

5. Pay and collect the permit

Coon Rapids collects the valuation-based fee when the permit is issued.

Rather not deal with the Anoka County building department?

Get a free quote →

A Minnesota municipality may require exterior work under a building permit to be finished within a set period, but not sooner than 180 days after the permit is issued, so confirm whether Anoka County has adopted such a rule. Minnesota’s statewide code rules

Inspections in Anoka County

Each city inspects its own permits. Blaine: call 763-785-6170, option 1, with the permit number, address, inspection type and contractor name. Coon Rapids: schedule online with the permit number, in windows of 8-10 a.m., 10 a.m. - 12 p.m. and 1-3 p.m., Monday-Friday, or call 763-767-6476 at least 48 hours ahead. Andover: from June 1, inspections can be booked every half hour between 7:30am - 12pm and 1:30pm - 4pm. Fridley: call 763-572-3604 with at least 24 hours’ notice and the permit number ready.

On public buildings, state-licensed facilities and school district and charter school projects, plumbing permits and inspections generally run through the state Department of Labor and Industry rather than the local office. State plumbing review in Minnesota

Official Anoka County permitting resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Want this handled start to finish?

Get a free quote →

Frequently asked questions

Does Anoka County issue building permits?

No. The county does not issue permits nor inspect permitted projects; each city issues and finals its own.

Who issues septic permits in Anoka County?

The cities. The county has no records for private septic systems in its municipalities, as all permitting is done at the city level.

Inspections are where schedules slip.

Get a free quote →

What does a driveway onto a county road cost in Anoka County?

A Residential Single Driveway access permit is $175, issued after a site review by the county Traffic Department.

Simplify Anoka County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build
  • Confirm which city or township issues the permit and whether electrical goes to the State or the city
  • Line up the county highway, right-of-way, septic or well permits the site needs alongside the city permit
  • File in each city’s own portal and book inspections the way that office takes them

Alliance Permitting is a permit documentation and submission company in Minnesota. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Anoka County sooner?

Let Alliance prepare, file, and track your Anoka County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Anoka County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.