Emmet County runs one of Michigan’s county construction code programs. Emmet County Construction Resources, 3434 Harbor-Petoskey Road, Suite E, Harbor Springs (231-348-1735), issues building, electrical, mechanical and plumbing permits in Petoskey, Harbor Springs, Alanson, Pellston and the townships; Bear Creek Township issues its own building and electrical permits. Tom Doss is the Construction Resources Director and Building Official. Applications are fillable PDFs sent by email, fax, mail or in person, and a new house is priced at $65 plus 0.462% of its table value, plus plan review.
What requires a building permit in Emmet County?
Construction Resources applies the state code’s permit rules, and its published answers spell out how they work for trade jobs. Ask the department before starting anything you are unsure of; work begun without a permit carries an extra $200 fee.
Permit needed
- New buildings, additions, alterations, moved houses and manufactured or modular home set-ups
- Any added or replaced wiring, and changing an overhead service to underground
- Plumbing work that alters drain, waste, vent or water piping, or a fixture
- Mechanical work beyond replacing minor parts, including a boiler in a private home or in an apartment building for fewer than six families
- Towers, including wind turbines
No trade permit
- Drain cleaning and repairs to faucets and toilets
- Portable heating and cooling units, gas burners under 30,000 Btu per hour and window air conditioners of 1.5 hp or less
- Self-contained refrigeration equipment and unvented oil stoves
- Boilers and pressure vessels that need a state boiler permit (the connecting components still need a local permit)
The department also posts handouts on off-site built structures such as sheds, play structures and small cabins, single-story accessory buildings, pole buildings and decks, which show what it checks for each.
What the county decides and what the state holds
The construction code is the state’s and cannot be amended locally. Emmet County chose to enforce it, its Building Official is appointed by the Board of Commissioners, and the board approves the fee factors. Zoning is split between county zoning and the units that zone themselves, and wetland, critical dune and high-risk erosion permits stay with the state.
Emmet County building department: who handles permitting
The state’s Statewide Jurisdiction List (Bureau of Construction Codes, revised November 6, 2026) marks Emmet County and its units as COUNTY for all four codes, with one exception: Bear Creek Township is LOCAL for building and electrical and COUNTY for mechanical and plumbing. The county’s own Permit Issuing Agencies sheet (updated May 6, 2025) says the same. The Village of Mackinaw City, which lies partly in Emmet County, has no row on the state list; the county sheet lists it only for zoning and house numbers, so call the village office (231-436-5351) for its part of the county.
Short on time to read all of this?
Get a free quote →| Permit | Issued by |
|---|---|
| Building and electrical | Emmet County Construction Resources; Bear Creek Township inside Bear Creek (373 N. Division Road, Petoskey, 231-347-3204) |
| Mechanical and plumbing | Emmet County Construction Resources, including Bear Creek Township |
| Zoning | Emmet County zoning in most townships, and for residential zoning in Alanson and Little Traverse Township; Petoskey, Harbor Springs, Pellston, Mackinaw City, Pleasantview, Resort (with Bay Harbor) and West Traverse zone themselves |
| Soil erosion | City of Petoskey inside the city; Emmet County everywhere else, including Bay Harbor |
| Septic and well | Health Department of Northwest Michigan, 3434 Harbor-Petoskey Road, Suite A (231-347-6014) |
| Driveways | Emmet County Road Commission, 2265 E. Hathaway Road, Harbor Springs (231-347-8142); MDOT Gaylord on state highways (989-731-5090) |
| Wetlands, critical dunes, high-risk erosion areas | State of Michigan, Gaylord office |
Petoskey is the largest city (5,772 residents in the Census Bureau’s 2025 estimate), followed by Harbor Springs (1,255) and the villages of Pellston (791) and Alanson (783). House numbers are assigned by Emmet County (231-348-0667) except in Harbor Springs, Mackinaw City and Petoskey, which number their own.
Emmet County permit types and what comes first
All applications are interactive PDFs: building, electrical, mechanical and plumbing permits, a plan-review-only application, a fire protection and fire alarm plan review application, a permit extension request and a permit release or cancellation form. Since January 31, 2024 only the revised trade applications are accepted, and each must arrive with its fee, worked out on page 2 of the form. Send finished forms by email, fax, mail or in person.
Residential permits
The department’s list of required submittals asks, for a house under 3,500 square feet or an accessory building, for the completed application, copies of every other permit that applies (zoning, driveway, septic, well, soil erosion, wetlands, critical dunes or high-risk erosion) and two sets of plans with the site plan, foundation and floor plans, building and wall sections and elevations. Houses over 3,500 square feet, and accessory buildings with walls over 12 feet high, need sealed plans. A re-roof or re-siding permit needs only the site, owner, builder and cost sections and the signature. Incomplete applications are returned.
Not sure this scope needs a permit?
Get a free quote →- Houses and garages are priced from the county’s valuation table, with basements, crawl spaces and decks counted at a share of the full rate.
- Energy code: new homes need an insulation certificate and a blower door test report, both posted as forms.
- Manufactured and mobile homes: the county posts set-up requirements and plumbing connection rules (cleanouts, proper fittings, pipe hangers; blocks or piping laid on the ground are not allowed), and completes the HUD Form 309 for a $100 fee.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial buildings are priced on the higher “O” factor, and plans are reviewed for compliance before the permit, including sub-trade plan reviews where needed. Sprinkler, fire pump, kitchen hood suppression, clean-agent and fire alarm systems have their own plan review fee tables, and complex projects that need outside consultants are billed for that review.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning from the county zoning office (same Harbor-Petoskey Road address) or the city, village or township that zones itself.
- Septic and well from the Health Department of Northwest Michigan, in the same building complex.
- Driveway from the road commission, or MDOT on a state highway.
- Soil erosion from the county (or Petoskey within the city).
- State permits for wetlands, critical dunes or high-risk erosion areas along the shoreline.
Emmet County permit costs and fees
The posted Building Department Fee Schedule is the 2020 schedule, updated October 22, 2020. New construction is valued from the department’s construction valuation table (based on the February 2017 ICC table) and multiplied by a factor that the Building Official reviews and the Board of Commissioners approves.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Houses, mobile homes and residential garages or accessory buildings | $65 + (building value × 0.00462), plus plan review |
| All other use groups (commercial) | $65 + (building value × 0.0060), plus plan review |
| Valuation shares | Crawl space or slab 10%, unfinished basement 30%, finished basement 60%, decks and porches 33% of the table rate for type III to V construction |
| Administrative fee on every building and sub-trade application | $65 |
| Minimum building permit / moved, modular or HUD home set-up | $90 / $200 |
| Plan review by construction value | $25 up to $66,000; $40, $55, $70, $85 and $100 in steps to $400,000; over $400,000, value ÷ 1,000 × 0.25 |
| Sub-trade plan review | 25% of the building plan review, minimum $65 |
| Towers (including wind turbines) | $200 to 100 feet, plus $2 per foot above |
| Re-inspection or additional inspection | $65 each |
| Special inspection | $65 plus $65 an hour |
| Work started without a permit | $200 extra |
| Expired permit renewed within 30 days | $65 per permit |
| Construction Board of Appeals | $500 |
Worked example from the schedule: a 2,000-square-foot wood-frame house (type VB, valued at $113.85 a square foot) has a building value of $227,700, so the permit is $65 + ($227,700 × 0.00462) = $1,116.97, and plan review for a value between $198,001 and $264,000 is $70. A basement, crawl space, garage or deck adds its own value. Trade permit fees come from page 2 of each trade application, and the Building Official may waive up to half of the extra fee for a homeowner who quickly fixes work started without a permit; the waiver is never given to contractors.
Trade permits and who may pull them
The county’s answers to common license questions are specific:
- Electrical: a homeowner may get the permit and do the work on the home he or she occupies or is about to occupy; commercial, industrial, apartment and rental work needs an electrical contractor to apply and do the work. Inside Bear Creek Township, the township issues electrical permits.
- Plumbing: the same owner-occupant rule applies; commercial work and rentals need a licensed contractor.
- Mechanical: a state mechanical contractor’s license is needed to secure the permit, except that a homeowner may do the installation in a single-family home he or she occupies or will occupy.
- License registration: electrical, mechanical and plumbing contractors licensed under the Skilled Trades Regulation Act (2016 PA 407) and working in the county register their licenses with the department; the 2024–2026 licensee registration application is posted.
Rather not deal with the Emmet County building department?
Get a free quote →Power company disconnects and reconnects for a service change need at least two days’ notice to the department for the inspection.
How to apply for a permit in Emmet County
Confirm who issues each permit for the parcel, especially in Bear Creek Township, Petoskey or Mackinaw City.
Zoning, health department septic and well, driveway and soil erosion approvals as the project needs.
Building application and the revised trade applications, with each trade fee worked out on page 2.
Plans for review, plus the insulation certificate and blower door report plan for new homes.
By email, fax, mail or at Suite E; pay online or with the application.
Use the online permit search to follow the permit and inspection results.
Review, corrections and what causes delay
Old versions of the trade forms are refused, and each trade application must include its fee. Revised plans after a permit is issued need a new building application, revised plans, another $65 administrative fee, a plan review fee and fees on the added value; scope changes without new plans are billed on the added value before further inspections.
Inspections in Emmet County
The permit holder must tell the department when work is ready, as the state code requires, and the department’s Required Inspection Document lists each inspection and the stage it belongs to. Request inspections by 4 p.m. the day before, by phone or with the online inspection request form. Inspectors usually work five days a week and aim to inspect within 24 to 48 hours; if your date cannot be met, the office will contact you, and the department posts inspectors’ planned time off on its page.
The required inspections list sets the order: demolition (utilities disconnected first), footing, electrical grounding in footings, underground electrical, mechanical and plumbing, pre-pour, foundation before backfill, and framing before any trade work starts. Every trade must pass its rough inspection before the building rough, which comes before insulation; masonry and factory-built fireplaces, brick or stone veneer and deck replacements have their own stages.
Re-inspections cost $65 when corrections were not made or the inspector could not get in, and so do inspections made before a permit is issued. An expired permit can be renewed within 30 days for $65; after that you must reapply and pay $65 per inspection still needed for final approval.
Want this handled start to finish?
Get a free quote →Michigan building code in Emmet County
Construction Resources enforces the codes the state most recently adopted and lists them on its page. No Michigan county is a National Flood Insurance Program community; each township, city and village joins on its own, so check flood maps with the local unit, and remember that shoreline work may also need a state critical dune or high-risk erosion permit.
Michigan enforces one statewide construction code under the Stille-DeRossett-Hale Single State Construction Code Act (1972 PA 230); local units cannot amend it, and enforcement sits with the city, village or township, a county program or the state Bureau of Construction Codes, sometimes split by trade. Michigan rules
Emmet County permit search and official resources
The department’s online permit search shows permit status and inspection results. For copies of plans or older files, send a Freedom of Information Act request to the Emmet County Administration office, Suite G70, 200 Division Street, Petoskey, by the online FOIA form, email or mail; copying and labor fees may apply.
- Emmet County Construction Resources (forms, inspections, FAQs)
- Emmet County Permit Issuing Agencies
- Building Department Fee Schedule (updated October 22, 2020)
- Permit search online (BS&A)
- Inspection request form
- Emmet County Planning & Zoning
- Construction Board of Appeals
- Construction Resources Committee
- Emmet County FOIA office
- State Statewide Jurisdiction List (Bureau of Construction Codes)
Inspections are where schedules slip.
Get a free quote →Emmet County building permit FAQs
Does Emmet County issue building permits in Petoskey?
Yes. The county issues building and trade permits in Petoskey and Harbor Springs; the cities run their own zoning, and Petoskey its own soil erosion permits.
Who issues permits in Bear Creek Township?
The township issues building and electrical permits; Emmet County issues mechanical and plumbing permits there.
How much is a building permit for a new house?
$65 plus 0.462% of the table value, plus plan review; a 2,000-square-foot wood-frame house works out to $1,116.97 and $70.
Can I do my own electrical or plumbing work?
Yes, in a home you occupy or are about to occupy; rentals, apartments and commercial buildings need licensed contractors.
How fast can I get an inspection?
Ask by 4 p.m. for the next day’s schedule; the department aims for 24 to 48 hours.
Who handles septic and well permits?
The Health Department of Northwest Michigan, at 3434 Harbor-Petoskey Road, Suite A.
What happens if I start work without a permit?
The county adds a $200 fee; up to half may be waived for a homeowner who responds promptly, never for a contractor.
Simplify Emmet County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Michigan. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Emmet County sooner?
Let Alliance prepare, file, and track your Emmet County permits while your crew stays on the job.
More Michigan permitting guides
Charlevoix County
Read guide →Cheboygan County
Read guide →Mackinac County
Read guide →Emmett Charter Township Building Permit Guide
Read guide →Farmington Hills Building Permit Guide
Read guide →Fenton Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Emmet County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.