In Marshall County, building permits come from the Marshall County Building Department, Room 302 of the Marshall County Building at 112 West Jefferson Street in Plymouth (574-935-8531), where Adam Combs is Building Commissioner. The department covers the unincorporated county and acts as permit and inspection agency for the towns of Argos, Bourbon, Bremen, Culver and La Paz; Plymouth has its own building department. Applications go through the county’s online permitting portal, and fees follow Ordinance 2023-27, in force since January 1, 2024: a conventional house under 2,000 square feet costs $300.
What requires a building permit in Marshall County?
In the area the county zones, Section 11-060 of the Marshall County Zoning Ordinance says no structure may be put up, moved or enlarged without an Improvement Location Permit (ILP) issued by the Plan Director, and the ILP application includes the building permit where one applies.
Permit required
- Any structure over 120 square feet or on a permanent foundation, including towers, antennas and satellite dishes
- Additions to any structure, and exterior work that adds to or changes a building’s height
- Interior renovation of existing structures and roofs, whether shingles or metal
- Swimming pools, in-ground or above-ground
- Placing or replacing a manufactured or mobile home
- Demolition and removal of buildings
- Signs, temporary structures and temporary uses of land
- Parking lots, mineral extraction and telecommunication towers
- Adding or removing dwelling units or leased space in apartment or commercial buildings
- Fences in the L-1, T-1, C-1, C-2 and I districts
No ILP needed
- Fences, walls and hedges in the A-1, A-2 and A-3 agricultural districts
- Cosmetic, non-structural changes such as new windows in existing openings, new siding and repainting
Exempt work must still meet the zoning and subdivision rules.
What the county decides and what the state holds
The Marshall County Building Commission was set up by local ordinance to make sure buildings in unincorporated areas meet the state’s minimum standards, and the department enforces the building, heating, ventilation, air conditioning, electrical and plumbing rules. Locally the county sets its own fees, registers contractors, issues certificates of occupancy, runs the zoning and subdivision ordinances, and keeps a flood rule that puts the lowest floor of a house at least 2 feet above the base flood elevation. The Construction Design Release for Class 1 buildings is a state approval; the county lists it among the papers needed before a permit application, where one is required.
Marshall County building department: who handles permitting
The Building Department and the Planning Department share the third floor of the Marshall County Building. The Building Department handles permits, inspections, contractor registration and certificates of occupancy; the Planning Department, led by Plan Director Nicholas Witwer, handles ILPs, subdivisions, property splits, variances and addresses.
Short on time to read all of this?
Get a free quote →| Office | Details |
|---|---|
| Building Department | 112 W Jefferson St, Room 302, Plymouth, IN 46563; 574-935-8531; fax 574-935-8534; Monday to Friday 8:00 a.m. to 4:00 p.m. |
| Planning Department | Same address; 574-935-8540; ILPs, property splits, Plan Commission and BZA |
| Inspection requests | 574-935-8540, the number on the department’s Call for Inspection page |
| Health Department (septic) | 510 W Adams St, GL 30, Plymouth; 574-935-8565 |
| Highway Department (driveways) | 9675 King Rd, Plymouth; 574-936-2181 |
| Surveyor and Drainage Board | Marshall County Building, 112 W Jefferson St |
Which office covers each city and town
| Community | Building permits | Zoning |
|---|---|---|
| Unincorporated county | County Building Department | County Plan Commission |
| Plymouth (city) | City Building Inspection Department, 574-936-2824 | Plymouth Plan Commission |
| Argos, Bourbon, Bremen | County Building Department | Each town’s own Plan Commission |
| Culver | County Building Department, through the county portal | Culver Plan Commission; the town’s acting Building Commissioner covers the town and the Culver Zoning Area up to 2 miles out |
| La Paz | County Building Department | Not on the county’s list of separate plan commissions |
The county says the separate plan commissions of Plymouth, Argos, Bourbon, Bremen and Culver serve both incorporated and unincorporated areas, so land just outside those towns can fall under a town’s zoning rather than the county’s. Culver publishes its own permit and fee schedule, Ordinance 2023-020, and has stopped taking paper applications.
Marshall County permit types
The fee ordinance doubles as a list of permit types. The county takes applications through its online permitting portal, and each contractor and subcontractor on the job must already be registered with the county.
Residential permits
- New homes: conventional homes priced by floor area, modular homes, and Type A or Type B single-wide manufactured homes.
- Additions: one rate up to 1,000 square feet and a second above it.
- Accessory buildings: garages and pole barns from 120 square feet, priced in five size bands; decks, carports and open porches share one flat fee.
- Pools, roofs, fences, signs and demolition: each has its own line, and a demolition permit carries no fee.
- Interior renovation, electrical and plumbing: separate permits, with re-inspections charged at $50.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
New commercial buildings, additions and renovations are priced in four size bands, with separate commercial electrical, plumbing and mechanical permits and a $100 re-inspection fee. Communication towers, private wind turbines and meteorological towers have their own fees, and wind and solar farms go through the Board of Zoning Appeals. The Technical Review Committee, which meets at 9 a.m. on the first and third Thursday of the month, reviews site development plans for ILPs in the L-1, C-1, C-2, I-1 and I-2 districts, along with rezonings and planned unit developments.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Address and site plan. The property needs an assigned address and a site plan showing dimensions to the lot lines and other buildings.
- Septic or sewer. The ILP needs either a Marshall County Health Department septic permit approving one on-site system and one alternate location, or a sewer tap-on permit; city water and sewer tap fees are paid first where they apply.
- Driveway. A permit from the County Highway Department, or from the state on a state road. The county inspects the staked entrance and sets the culvert size; the owner buys and installs the pipe.
- Drainage and review boards. Drainage approval, Technical Review Committee approval and any Board of Zoning Appeals variance must be in hand.
- Floodplain. Flood hazard information goes with the ILP, and work in a floodway needs an Indiana Department of Natural Resources permit before the local permit.
- Farm areas. A new house in a district that allows farming needs a signed Notice of Agricultural Activity.
Marshall County permit costs and fees
Building, trade, Plan Commission and Board of Zoning Appeals fees are set by Ordinance 2023-27, which amended the fee section of the zoning ordinance (Article 11, Section 010 C). The Plan Commission held its hearing on September 28, 2023, the commissioners adopted it that fall, and the schedule took effect on January 1, 2024. It also takes in the BZA and Plan Commission fees of Ordinance 2023-13.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| Conventional home under 2,000 sq ft | $300 |
| Conventional home 2,000–3,000 sq ft | $325 |
| Conventional home 3,001–4,000 sq ft | $350 |
| Conventional home over 4,001 sq ft | $0.08 per sq ft, minimum $400 |
| Modular home / single-wide (Type A or B) | $180 / $150 |
| Home addition up to 1,000 sq ft / over 1,000 sq ft | $210 / $225 |
| Accessory structure 120–1,600 sq ft | $140 |
| Accessory structure 1,601–2,000 / 2,001–4,000 sq ft | $170 / $200 |
| Accessory structure over 4,001 sq ft | $0.05 per sq ft, minimum $250 |
| Decks, carports, open porches | $140 |
| Pool in-ground / above-ground | $140 / $110 |
| Roof (structural or shingles/metal) | $60 |
| Fence / sign / demolition | $25 / $110 / $0 |
| Interior renovation | $170 |
| Electric permit / plumbing permit / re-inspection | $50 each |
| Commercial building under 2,000 / 2,000–5,000 / 5,001–10,000 sq ft | $220 / $400 / $600 |
| Commercial building over 10,000 sq ft | $0.06 per sq ft, minimum $1,000 |
| Commercial electric, plumbing or mechanical permit | $50 each; commercial re-inspection $100 |
| Solar: micro / small / medium / large | $70 / $100 / $170 / $310; farms $25 per acre |
| Communication tower / private wind turbine / met tower | $300 / $70 per tower / $160 per tower |
| Rezoning / waiver / vacation | $200 / $150 / $150 |
| Subdivision minor / major / planned unit development | $500 / $750 / $1,200, plus $5 per lot |
| BZA appeal / use variance / development standard variance | $225 / $300 / $275 |
| BZA special use / flood hazard variance | $275 / $325 |
Worked examples at the schedule’s rates: a 2,500-square-foot conventional home falls in the 2,000 to 3,000 band and costs $325. A 4,500-square-foot home is charged $0.08 a square foot, which gives $360, so the $400 minimum applies. The bands skip the step between 4,000 and 4,001 square feet, so ask the department how a house of exactly that size is charged.
Trade permits and who may pull them
The Building Department enforces electrical, plumbing, heating and air-conditioning standards in its area, and each trade has its own permit on the fee schedule: $50 for a residential electric or plumbing permit and $50 for a commercial electric, plumbing or mechanical permit. Plumbing contractors also need the state plumbing contractor license. The department links the service requirements of NIPSCO, the REMC of Marshall County meter base guides and AEP.
Contractor registration
Every contractor and subcontractor paid to do work in the county’s area must register with the Building Department under Ordinance 2013-20; a homeowner who lives in the house may do the work without registering. Registration needs:
- a certificate of insurance showing at least $500,000 in liability cover;
- workers’ compensation insurance, or the Affidavit of Independent Contractor Certification issued by the State of Indiana;
- a $20,000 license and permit bond payable to Marshall County; and
- a $50 fee, paid online by card or at the office by cash, check, money order or card.
Rather not deal with the Marshall County building department?
Get a free quote →No classes or tests are required. Registration runs for the calendar year and ends on December 31, and a contractor whose bond or insurance lapses is moved to an inactive list and cannot pull permits until it is renewed.
How to apply for a Marshall County building permit
The county’s Beacon GIS shows the parcel and its zoning district.
Get the address, septic permit or sewer tap, driveway permit, drainage approval and any TRC or BZA approval first.
Every contractor and subcontractor listed on the application must hold a current county registration.
File the ILP and building permit through the county’s online permitting portal with the site plan, plans and contact details.
Pay online or in person at 112 West Jefferson Street, Room 302.
Start within six months and call 574-935-8540 at each required stage.
Review, corrections and what causes delay
The county warns that an application filed before every prerequisite is complete and approved will be delayed or denied. Commercial and industrial sites in the L-1, C-1, C-2, I-1 and I-2 districts wait for the Technical Review Committee, which meets twice a month. An ILP lapses if work has not started within six months or is not finished within two years; the Plan Director can grant up to two one-year extensions if asked within a month of expiry and the extension fee is paid.
Inspections and certificates in Marshall County
Request inspections on 574-935-8540. The department’s required inspections list sets the stages for each kind of job:
| Project | Inspections |
|---|---|
| New home or addition | Footing, foundation, underslab plumbing and heating, framing, electrical service entrance, final |
| Pole barn or frame building | Footing including post holes, any underground plumbing or electrical, framing, final |
| Deck, carport or open porch | Post hole or footing, final |
| Swimming pool | Electrical grounding once the pool is set, fencing |
| Roof structural change | Framing |
| Commercial project | Footing, foundation, underslab, rough electrical, plumbing and heating, framing, service entrance, final |
Under Section 11-070 a new or substantially remodeled building may not be used until it has an ILP, has passed every inspection including the final, and has a certificate of occupancy. The Plan Director issues the certificate once the Building Official confirms the building codes are met. The county also has an Unsafe Building Ordinance (2020-12) and an unsafe buildings board.
Want this handled start to finish?
Get a free quote →Indiana building code in Marshall County
FEMA’s Community Status Book lists unincorporated Marshall County (community 180443) as participating in the National Flood Insurance Program, with the current flood map dated November 16, 2011; the City of Plymouth has its own entry. In the county’s flood hazard areas a new or substantially improved house must have its lowest floor, basement included, at or above the flood protection grade of 2 feet above the base flood elevation, and other buildings must be elevated or floodproofed to that level. A flood hazard variance goes to the Board of Zoning Appeals for $325.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Marshall County building permit FAQs
Does the county issue permits inside Plymouth?
No. Plymouth has its own building inspection department (574-936-2824). The county issues building permits in the unincorporated area and in Argos, Bourbon, Bremen, Culver and La Paz.
How much is a permit for a new house?
$300 under 2,000 square feet, $325 up to 3,000, $350 up to 4,000, and $0.08 a square foot above that with a $400 minimum, under Ordinance 2023-27.
Do I need a permit for a shed?
Yes if it is over 120 square feet or sits on a permanent foundation; accessory buildings from 120 to 1,600 square feet cost $140.
Do I need a permit for a new roof?
Yes. Roofs, shingle or metal, need a permit, and the fee is $60.
Can I do my own work without registering?
Yes. A residential owner-occupant may do their own work; anyone paid to work on the job must be registered with the county.
What does contractor registration cost?
$50 a year, plus proof of $500,000 liability cover, workers’ compensation or a state exemption certificate, and a $20,000 bond payable to Marshall County.
Do I need a septic permit first?
Yes on a septic lot. The ILP needs a Marshall County Health Department permit approving one septic system and an alternate site, or a sewer tap-on permit.
Marshall County permit search and official resources
Permits, property splits and contractor registrations are filed and tracked in the county’s online permitting portal, and parcel and zoning details are on Beacon. The zoning ordinance requires the Plan Director to keep a copy of every ILP application and its plans as a permanent Plan Commission record, so older permit files can be requested from the Planning and Building offices in Room 302.
Inspections are where schedules slip.
Get a free quote →- Marshall County Building Department
- Online permitting and contractor registration portal
- Permit fee schedule, Ordinance 2023-27
- Required inspections
- Call for inspection
- Contractor registration requirements
- Building Department FAQs
- Marshall County Planning Department
- Marshall County Zoning Ordinance (effective July 1, 2026)
- Technical Review Committee
- Highway Department driveway permit
- Marshall County Health Department
- Surveyor and Drainage Board
- Town of Culver Building Commissioner
- FEMA Community Status Book, Indiana
Simplify Marshall County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Marshall County sooner?
Let Alliance prepare, file, and track your Marshall County permits while your crew stays on the job.
More Indiana permitting guides
Plymouth
Read guide →St. Joseph County
Read guide →Fulton County
Read guide →Merrillville Building Permit Guide
Read guide →Miami County Building Permit Guide
Read guide →Michigan City Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Marshall County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.