Inside the Town of Chesterton, permits come from the town’s own Building Department at 1490 Broadway, Suite 5 (219-926-2610), led by Building Commissioner Mark O’Dell; Porter County’s department does not permit work in town. Applications are PDF forms returned by email, fax or in person, and every contractor must register with the town first. Ordinance 2025-29, in force since January 1, 2026, prices a new single-family home at $0.32 per square foot (minimum $400) plus a $200 application fee.
What requires a building permit in Chesterton?
Chesterton’s rule is written in Section 5-42 of the Town Code as rewritten by Ordinance 2025-29. You need a permit before you dig, build, alter or repair any building or structure when the work changes the use, adds lot coverage, or costs more than $1,000. Plumbing and electrical work is treated more strictly: it needs a permit whatever it costs and whether or not anything else changes.
Town permit forms
- Decks, new or replacement
- Driveways, sidewalks, patios and exterior steps
- Fences, new or replacement
- In-ground and above-ground pools
- Occupancy permits for a business opening or changing occupancy
- Repairs and general maintenance work
Priced in the fee ordinance
- New houses, additions, remodels and accessory buildings
- Commercial, industrial and multi-family construction
- Demolition, signs, temporary structures and cell towers
- Furnaces, air conditioners, water heaters and other equipment
- Commercial parking lots and seal coating
- Zoning permits for one- and two-family (Class 2) projects
For a permit type not on the forms page, the department supplies the form. Starting work before the permit is issued brings a stop work order and a 50% increase in the permit fee, on top of any fine. Emergency repairs escape the surcharge if a permit is applied for within three business days.
What Chesterton decides and what the state holds
The town adopts the state building rules by reference, and Ordinance 2025-29 says state code compliance alone is not enough: local forms, design standards and inspection conditions must also be met or the inspection fails. Chesterton also sets its own fees, zoning, site plan and as-built survey rules, sodding and tree requirements, and contractor registration. A Class 1 building still needs the state Construction Design Release, and the applicant signs an Affidavit on Plan Authentication swearing the plans filed with the town are identical to the state-released set.
Chesterton building department: who handles permitting
The Building Department handles building, zoning, plumbing and electrical permits, inspections, code enforcement and property maintenance complaints for the town. The Building Commissioner issues every permit; fees are paid to the Clerk-Treasurer. The Fire Chief helps inspect fire suppression, detection and alarm systems and reports back to the Building Commissioner.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Department, 1490 Broadway, Suite 5, Chesterton, IN 46304 |
| Phone / fax | 219-926-2610 / 219-929-1428 |
| building@chestertonin.org | |
| Hours | Monday to Friday, 8:00 a.m. to 4:30 p.m. |
| Building Commissioner | Mark O’Dell |
| Town Hall (meetings) | 726 Broadway; Clerk-Treasurer 219-926-1641 |
| Flood insurance | Participating in the NFIP (community 180201); current map dated September 29, 2022 |
Chesterton permit types
Each form asks for the parcel, the registered contractor and the job cost, and most ask whether the lot is in a floodplain; if it is, a Floodplain Development Permit Application goes in too.
Residential permits
- New houses and additions. The application needs the approved zoning permit, a site plan, the sanitary sewer permit required by the utility, and plans showing elevations, floor plans and all plumbing and electrical work with dimensions. New subdivisions must have street name and regulatory signs installed before building permits are issued.
- Decks. The plan must show the ledger (at least 2x8), joists, two-board beams, footings, stairs and railings; guards are required 30 inches above grade and spindles may be no more than 4 inches apart. Decks may not sit in an easement or a side or rear setback.
- Fences. Submit a survey plat with the fence drawn on it and a signed easement agreement. Fences beside public rights-of-way (not alleys) are limited to 4½ feet, and 6-foot fences may not stand in the front building plane or within 5 feet of an alley in a residential zone.
- Pools, flatwork and repairs each have their own short form.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial, industrial and multi-family buildings are priced by square foot with higher minimums, and their site plans must also show dimensioned parking, accessible spaces, landscaping, grease traps, backflow devices and hydrants. A business opening or changing occupancy files the occupancy permit form, which carries a $40 fee and asks you to book the inspection with 24 hours’ notice. Plans for a Class 1 building must match the set released by the state, sworn on the plan authentication affidavit.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning permit (Class 2). For one- and two-family projects the zoning permit comes first; the Building Commissioner checks it against the zoning ordinance (Appendix A of the Town Code) for lot area, setbacks and lot coverage.
- Site plan. On 11x17 paper at 1 inch to 10 or 20 feet, showing lot lines, setbacks, easements, contours, footing and floor elevations, storm water handling, lot coverage, erosion control and utilities. A professional engineer licensed in Indiana must prepare any site plan in or next to a floodplain.
- Plan Commission. The Advisory Plan Commission approves subdivision plats and site plans and advises the Town Council on rezoning, planned unit developments and the Comprehensive Plan.
- Board of Zoning Appeals. Developmental standard variances (setbacks, height, lot coverage, parking) and use variances go to the BZA.
- State release. Class 1 work needs the state Construction Design Release before construction.
Not sure this scope needs a permit?
Get a free quote →Chesterton permit costs and fees
Fees are set by Section 5-44 of the Town Code as rewritten by Ordinance 2025-29, which the Town Council adopted in December 2025. The ordinance took effect on January 1, 2026, and its higher building permit fees took effect 90 days after publication. Square footage counts the living area, basement, garage and crawl space, and every fee is paid before the permit is issued.
| Work | Fee |
|---|---|
| Single-family new construction | $0.32 per sq ft; minimum $400 |
| Residential addition / remodel | $0.30 per sq ft, minimum $100 / $0.25 per sq ft, minimum $50 |
| Residential repair or replacement | $0.02 per dollar of job cost, maximum $1,000; minimum $50 |
| Residential accessory structure | $0.25 per sq ft |
| Commercial or multi-family new construction / commercial addition | $0.40 per sq ft; minimum $750 / minimum $300 |
| Commercial remodel / repair or replacement | $0.30 per sq ft, minimum $250 / $0.05 per dollar of job cost, maximum $2,000, minimum $250 |
| Application fee at submission (new construction) | $200 residential; $400 multi-family; $500 commercial or industrial |
| Class 2 structure: inspection fee / plan review / private provider convenience fee | $200 primary, $50 accessory / $50 / $100 |
| Decks / fences / in-ground pool / above-ground pool | $120 / $80 / $200 / $50 |
| Residential driveway / sidewalk, steps, patio / demolition | $50 / $50 / $200 |
| Mechanical or plumbing equipment | $50 fee, plus $8 per unit after six units; minimum $100 |
| Signs / zoning permit | $2.00 per sq ft, minimum $50 / $50 |
| Occupancy permit / temporary occupancy | $40 / $25, then $25 a day past expiry |
| Reinspection / extra inspection | $80 residential, $100 commercial / $50 each beyond the 14 standard inspections |
| Permit renewal / work started without a permit | 50% of the original fee / fee raised by 50% |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the schedule: a new house with 2,400 square feet of counted area (living space, basement, garage and crawl space together) is 2,400 × $0.32 = $768 for the building permit line, plus the $200 application fee paid when the plans go in, or $968. The schedule lists the Class 2 inspection and plan review fees and the plumbing and electrical charges as separate lines, so ask the department which of them apply to your file.
The department’s Required Inspections sheet still prints reinspection fees of $50 for residential and $85 for commercial work. The adopted ordinance sets $80 and $100, and the ordinance governs.
Trade permits and who may pull them
Chesterton requires every contractor, including general, electrical, plumbing, HVAC, roofing, concrete and specialty trades, to register with the Building Department before applying for permits or starting work. Registration costs $100 new and $50 to renew, and lasts one year. It needs a certificate of insurance naming the Town of Chesterton with at least $500,000 combined single limits, proof of Indiana workers’ compensation compliance or a clearance certificate, and either a bond to the town or a $5,000 Porter County Unified Bond stamped by the Porter County Recorder. Plumbing contractors add their Indiana plumbing license, and an LLC or corporation must hold the corporate state license.
| Item | Fee |
|---|---|
| One- and two-family: temporary, 100 amp or 200 amp service | $50 application + $80 inspection |
| One- and two-family: 400 amp or other service | $100 application + $100 inspection |
| Multi-family, business, industrial: temporary service | $70 application + $50 inspection |
| Multi-family, business, industrial: 100 or 200 amp / 400 amp | $50 + $100 / $80 + $200 |
| Service upgrades up to 200 amp / 200-400 amp | $50 + $80 / $100 + $100 |
| Plumbing | $50 application + $8 per fixture; $50 minimum for all plumbing |
| More than four electrical or plumbing inspections | $100 for each extra inspection |
The four standard electrical and plumbing inspections are underground, service, rough and final. The registration page and forms do not set out a separate homeowner route, so an owner doing their own work should ask the department before filing.
Rather not deal with the building department?
Get a free quote →How to apply for a Chesterton building permit
File the registration form with the insurance certificate, workers’ compensation proof and bond, and pay the fee; registration must be approved before any permit is issued.
For a one- or two-family project, obtain the zoning permit; take variances to the BZA and plats or site plans to the Plan Commission first.
Download the deck, flatwork, fence, pool, occupancy or repair form, or ask the office for the form for new construction or other work.
Attach the 11x17 site plan, construction plans, sewer permit, survey plat or estimate the form asks for, and the floodplain application if the lot is in a floodplain.
Send the application to building@chestertonin.org, fax it to 219-929-1428, or bring it to 1490 Broadway, Suite 5.
Pay the application fee at submission and the permit fee before the permit is issued.
Review, corrections and what causes delay
The Building Commissioner reviews every application for code compliance and checks new construction and major repairs for flood safety before a permit is issued. Unregistered contractors, a missing zoning permit, an incomplete site plan or an unanswered floodplain question are the most direct causes of delay, and a false statement on an application or plan lets the Building Commissioner revoke the permit. The BZA and Plan Commission petition packets are being reissued and are handed out by the office on request.
Inspections and occupancy in Chesterton
The contractor or owner books inspections by calling the Building Department at 219-926-2610 at least 24 hours ahead, and must schedule each one before work is covered. The standard sequence is stake (lot corners staked and erosion control in place before digging), footing, foundation wall, foundation backfill, electric service, underground plumbing, rough (electrical, plumbing, framing and mechanical exposed), insulation, public sidewalk and final. Before the foundation wall inspection a land surveyor must submit a signed and sealed statement of the top of footing elevation at every corner and break in the wall. When the electric service passes, the department notifies NIPSCO.
At the final, the inspector looks mainly at smoke detectors, stair handrails, GFCI outlets and the garage separation, house numbers, and the two front-yard trees the zoning ordinance requires. Before an occupancy permit is issued for a new building you also need a surveyor’s as-built site plan, sod in the parkway (or at least 8 feet of sod between the curb and the building), lot corners marked with steel rods or pipes by a registered surveyor, a blower door certificate for new homes, and silt fence or other perimeter controls kept until 70% of bare ground has permanent vegetation. Homes with manufactured floor or roof systems need “F”, “R” or “RF” tags from the department on the utility meter. Temporary occupancy permits expire at 11:59 p.m. on May 15 unless the Building Commissioner sets another date.
Want this handled start to finish?
Get a free quote →Indiana building code in Chesterton
Chesterton’s Building Department enforces the state building, residential, electrical, plumbing, mechanical, fuel gas, fire, energy and swimming pool rules adopted by the Fire Prevention and Building Safety Commission, together with the Chesterton Town Code. New Class 2 homes with a fireplace, attached garage or fuel-burning appliance need at least one carbon monoxide detector per unit.
Before construction starts on a Class 1 structure — one used by the public, by three or more tenants, or by anyone working as another’s employee — Indiana requires a state Construction Design Release, unless the work is exempt under 675 IAC 12-6-4. One- and two-family dwellings and qualifying townhouses are Class 2 and are permitted locally where an ordinance requires it. Indiana enforces the 2014 Indiana Building Code and the 2020 Indiana Residential Code. Class 1 and Class 2 in Indiana
Chesterton building permit FAQs
Do I need a permit to replace a fence or deck in Chesterton?
Yes. The town has separate permit forms for new and replacement fences ($80) and decks ($120), and the contractor must be registered with the town.
How much is a building permit for a new house in Chesterton?
$0.32 per square foot of living area, basement, garage and crawl space, with a $400 minimum, plus a $200 application fee; 2,400 square feet comes to $968 before trade and inspection lines.
How long is a Chesterton permit valid?
New residential and commercial construction has 18 months, remodels and additions 12 months, and other permits 6 months from issue; renewal costs half the original fee.
Does a small repair need a permit?
Work over $1,000, work that adds lot coverage or changes the use does, and any plumbing or electrical work does whatever it costs; use the repair and general maintenance form.
What does a contractor need to register in Chesterton?
A registration form, $100 fee, a $500,000 insurance certificate naming the town, workers’ compensation proof and a $5,000 bond, plus a state license for plumbers.
When does the Plan Commission meet?
At 6:30 p.m. on the third Thursday at Town Hall, 726 Broadway; petitions are due 17 days before, by 10:00 a.m.
Chesterton permit search and official resources
To look up an old permit, inspection or occupancy record, use the town’s online Public Records Request form or ask the Building Department directly. The Advisory Plan Commission will hold a public hearing at 6:30 p.m. on Thursday, November 19, 2026 at Town Hall on a new Comprehensive Plan to replace the plan adopted on December 6, 2010; written objections filed with the commission’s secretary before the hearing will be considered.
Inspections are where schedules slip.
Get a free quote →- Chesterton Building Department
- Permit forms and expiration periods
- Ordinance 2025-29: building permits and fees
- Required inspections and occupancy requirements
- Contractor registration
- Deck permit application
- Fence permit application
- Repair and general maintenance permit application
- Occupancy permit application
- Advisory Plan Commission
- Board of Zoning Appeals
- Storm Water Management Board
- Comprehensive Plan public hearing notice
- Public records request form
- Town staff directory
Simplify Chesterton permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Indiana. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Chesterton sooner?
Let Alliance prepare, file, and track your Chesterton permits while your crew stays on the job.
More Indiana permitting guides
Porter County
Read guide →Valparaiso
Read guide →LaPorte County
Read guide →Clay County Building Permit Guide
Read guide →Clinton County Building Permit Guide
Read guide →Connersville Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Chesterton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.