In the City of Streator, permits come from the Community Development / Planning & Zoning Department at City Hall, 204 South Bloomington Street (815-672-2517), led by Planning & Zoning Administrator Gary Bird, with the city’s own building, plumbing and electrical inspectors. You file the fillable application for the job at City Hall. The building permit fee follows the cost of the work, from $50 for jobs up to $1,000 to $750 for a $200,001 to $300,000 project, and every contractor must be registered with the city before a permit is issued.
What requires a building permit in Streator?
The city’s general application covers new buildings, additions, alterations, foundations, moving a building, pools and repairs or replacements, and separate forms cover accessory buildings, electrical, plumbing, fences, roofs, demolition, sewer connections, signs and work in the right-of-way. The application’s cost rules show where the line falls: replacing windows with no structural change needs no permit, but if you change a window’s size and add framing, the permit covers both the windows and the framing. When part of a contract is maintenance and part needs a permit, the permit is taken out for the whole contract amount.
Permit needed
- New buildings, additions, alterations and foundations
- Moving a building, and repairs or replacements that need a permit
- Garages, sheds and carports
- Electrical work, including solar panels
- Plumbing work, counted by fixture opening
- Fences
- Roofs
- Swimming pools, above-ground or in-ground
- Demolition of a structure of any kind
- Sewer connections and signs
No permit
- Replacing windows in the same openings with no structural change
- Maintenance work, unless it is part of a contract that includes permitted work
Other approvals are flagged on the application: boiler, curb or sidewalk cut, elevator, furnace, grading, oil burner and storm water under Section 15.46 of the Municipal Code.
What Streator decides and what the state holds
Streator adopts its codes and fees in its own Municipal Code, published on Municode; the plumbing permit cites Chapters 3.48 and 15.36, and the sewer permit Chapters 3.48 and 13.04. The electrical permit form asks solar installers to certify that the main panel meets the 2020 National Electrical Code. State law still governs who may do some work: roofers must be licensed under the Illinois Roofing Industry Licensing Act, and commercial plumbing needs a state license.
Streator building department: who handles permitting
The Community Development / Planning & Zoning Department runs building permits and inspections, zoning administration, code enforcement, site plan and development review and support for the Plan Commission. It is led by the Planning & Zoning Administrator and staffed by a building inspector, a plumbing inspector and an electrical inspector. The Zoning Board of Appeals hears variances. Streator lies in both LaSalle and Livingston counties; land outside the city limits is permitted by the county, which on the LaSalle side is the LaSalle County Land Use Department in Ottawa.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Community Development / Planning & Zoning, City Hall, 204 South Bloomington Street, Streator, IL 61364 |
| Phone and fax | 815-672-2517; fax 815-672-7566 |
| Department head | Gary Bird, Planning & Zoning Administrator |
| Inspectors | Building, plumbing and electrical inspectors on city staff; reach them through City Hall |
| Unincorporated LaSalle County | LaSalle County Land Use Department, 119 West Madison Street, Room 107, Ottawa, 815-434-8666 |
Streator permit types
All forms are fillable PDFs on the city’s document download page. The general application asks for the location and zoning district, the type of improvement, ownership, the proposed use, the cost of the improvements with electrical, plumbing and HVAC listed separately, and building details such as frame type, heating fuel, sewage disposal, water supply, stories, floor area and, for homes, bedrooms and bathrooms. A contractor table records the general contractor’s city registration number, the plumbing and roofing contractors’ state license numbers, the electrical contractor’s registration number and where it was issued, and the city registration numbers of the drywall, carpentry, insulation, concrete, HVAC, excavating and masonry contractors.
Residential permits
- Site plan. Drawn to scale with straight lines, showing north, the lot and its dimensions, bordering streets and alleys, every structure with its distances to lot lines and to the main building, the new work and a drainage plan. Rough sketches are not accepted. Property lines are proven either by a survey from an Illinois licensed surveyor (valid if nothing has been added or removed since) or by a city inspector sighting the surveyor’s monuments, and the city may require a survey when you build close to a setback.
- Plans. Blueprints are required for houses; they may come from the builder or a plan service if a specification sheet with a materials list is included and all utilities are shown with their distribution and capacities.
- Garages, sheds and carports. A site plan before any review, property lines marked before the site inspection, and an electrical permit if the building will have power.
- Pools. Above-ground permanent, storable or in-ground. The site plan shows distances to the house, accessory buildings, each lot line and the ComEd line, with the electrical, fence and deck applications attached where they apply; every pool deeper than 24 inches needs a ladder or steps in the shallow end.
- Fences. A site plan to scale showing the fence and the house in relation to the lot lines. Pallets are not allowed as fencing.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
Commercial, industrial and institutional plans must be submitted under the approval of an Illinois licensed architect or engineer. Their site plans vary with size and use but always show bordering streets and alleys and any building within 30 feet of the new construction. Applications are reviewed for building, plumbing, electrical, engineering and public works as each job requires. A sewer connection discharging more than 1,500 gallons a day also needs written proof on whether an Illinois EPA sewer connection permit is required.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning relief. Variances go to the Zoning Board of Appeals, which votes separately on each required condition (light and air, reasonable use, a hardship unique to the land and not self-created). The notarized application asks whether the lot is in a floodplain or floodway.
- Other zoning petitions. Rezoning, special use and annexation each have their own application.
- Street and sewer work. A sewer connection needs a Construction or Excavation Permit from Public Works and a scaled drawing locating the tap, with an as-built drawing if the location changes; encroachment and right-of-way modification permits cover other work in the street.
Streator permit costs and fees
Building permit fees are based on the reasonable cost of the improvement, labor and materials at fair market value. Without a bona fide contract, the Code Enforcement Officer sets the value from the area and type of construction. The general construction schedule is printed on the building application and on the swimming pool application updated May 27, 2026.
| Cost of work | Permit fee |
|---|---|
| $0 to $1,000 | $50 |
| $1,001 to $5,000 | $75 |
| $5,001 to $10,000 | $100 |
| $10,001 to $20,000 | $125 |
| $20,001 to $40,000 | $150 |
| $40,001 to $60,000 | $210 |
| $60,001 to $100,000 | $330 |
| $100,001 to $150,000 | $450 |
| $150,001 to $200,000 | $600 |
| $200,001 to $300,000 | $750 |
| $300,001 to $600,000 | $1,200 |
| $600,001 to $1,000,000 | $1,800 |
| $1,000,001 to $1,500,000 | $2,700 |
| Over $1,500,001 | 0.18% of the cost |
Rather talk it over?
Call 1-855-478-4290 →Separate fees printed on the other forms:
- Electrical: $55 in the R-1A, R-1B and R-2 residential districts and $100 in all other districts (listed on the form as a registration fee).
- Plumbing: $15 per opening in a single-family home, $25 per opening in multi-family, commercial or industrial buildings.
- Fence: $50, or 3 cents a lineal foot for fences of 1,667 feet or more.
- Roof: $25 residential, $100 commercial.
- Demolition: $50.
- Sewer connection: $2,000.
- Contractor registration: $100 a year.
- Variance: $100 for a single-family lot, $300 for multi-family land under one acre, $750 for residential land of one acre or more, plus the cost of legal notices; the form lists non-residential variances at both $100 and $300, so confirm that one at City Hall.
Worked example from the schedule: a $30,000 detached garage falls in the $20,001 to $40,000 band, so its building permit is $150; a $250,000 house falls in the $200,001 to $300,000 band, for $750. Demolition done under the city’s own demolition project carries no fee.
Trade permits and who may pull them
Streator runs its own electrical and plumbing permits and inspections, and it ties both to contractor registration: an electrical permit is not issued without the contractor’s registration number, and a plumbing permit is not issued without one either. Registration is yearly at $100, and the city needs a certificate of liability insurance naming the City of Streator as certificate holder before it issues the registration.
- Roofers: must hold an Illinois roofing license; the contractor’s state license number goes on a sign on the property facing the road, and an unlicensed roofer is ordered to stop until a licensed one takes over.
- Plumbers: commercial plumbing requires the state license on the registration form, and the building application asks for the plumbing contractor’s state license number. Plumbing must be inspected before underground and rough-in work is covered, and the city makes a final inspection before approval.
- Electricians: the building application asks where the electrical contractor’s registration was issued; solar installers also certify the main panel.
- Fence and demolition contractors: a fence permit is not issued unless the contractor is registered, and demolition contractors must be registered and insured.
Rather not deal with the building department?
Get a free quote →The roof form has a line for work done by someone other than the owner, but the city’s forms do not otherwise describe homeowner permits; ask at City Hall if you plan to do your own work.
How to apply for a Streator building permit
Check that the property is inside Streator, using the LaSalle County GIS linked from the department page if needed.
Each contractor files the yearly registration with proof of insurance naming the city.
Download the fillable application for the job from the document download page and complete every required section.
Add a scaled site plan with proven property lines, the drainage plan and, for houses, blueprints with a materials list.
Bring the packet to 204 South Bloomington Street with the fee from the schedule.
For accessory buildings, have the property lines marked before the site inspection.
Review, corrections and what causes delay
Incomplete applications are returned, which delays approval. Rough sketches, property lines that cannot be proven near a setback, a missing drainage plan or an unregistered contractor are the usual reasons. Projects that need engineering or public works review, or a sewer connection with its excavation permit, take longer than a simple residential job.
Inspections and certificates in Streator
Call City Hall at 815-672-2517 to reach the building, plumbing or electrical inspector. Plumbing is inspected before underground lines and rough-in are covered and again at the end. Accessory buildings get a site inspection once the property lines are marked. Before a demolition the contractor notifies every utility (Illinois American Water, NICOR, ComEd, Frontier, Mediacom and the city sewer), foundation walls come out to at least one foot below finished grade, basements are backfilled with clay fill or an approved substitute, and a house that is not replaced takes its garage and sheds with it.
The building application records the date a certificate of occupancy is issued once the building inspector signs off, and the sewer permit needs an as-built drawing if the connection does not match the approved drawing.
Illinois building code in Streator
Streator enforces the codes adopted in its Municipal Code. FEMA’s Community Status Book lists the City of Streator (community 170408, under Livingston and LaSalle counties) as participating in the National Flood Insurance Program, with a current flood map dated July 18, 2011; the city is not in the Community Rating System.
Want this handled start to finish?
Get a free quote →Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Streator building permit FAQs
How much is a building permit in Streator?
It depends on the cost of the work: $50 up to $1,000, $150 for $20,001 to $40,000, $750 for $200,001 to $300,000, and 0.18% of the total cost for projects over $1.5 million.
Do I need a permit to replace windows?
Not if the openings stay the same size; changing the size and adding framing needs a permit for the whole job.
How much is a roof permit?
$25 for a home and $100 for a commercial building; any contractor hired for the roof must be licensed under the Illinois Roofing Industry Licensing Act.
Do contractors register with the city?
Yes, every year for $100, with liability insurance naming the City of Streator.
How much is a fence permit?
$50, from a registered contractor; pallets may not be used as fencing.
What does a sewer connection cost?
$2,000 for the city permit, plus a Construction or Excavation Permit from Public Works.
Streator permit search and official resources
Ask Community Development at City Hall about the status of a permit or inspection. Copies of permit records are requested from the City Clerk under the Freedom of Information Act, on the city’s FOIA form by e-mail, mail, fax or in person; the city answers within five working days unless it takes one of the extensions the Act allows. City Council and committee packets are posted on the agendas page.
Inspections are where schedules slip.
Get a free quote →- Community Development / Planning & Zoning
- Document download page (all permit forms)
- Building permit application and fee schedule
- Accessory building permit application
- Contractor registration application
- Electrical permit application
- Plumbing permit application
- Fence permit application
- Roof permit application
- Swimming pool permit application
- Demolition permit application
- Sewer connection permit application
- Variance application
- FOIA request form
- Agendas, minutes and packets
- LaSalle County Land Use Department (unincorporated areas)
- FEMA Community Status Book, Illinois
Simplify Streator permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Streator sooner?
Let Alliance prepare, file, and track your Streator permits while your crew stays on the job.
More Illinois permitting guides
LaSalle County
Read guide →Ottawa
Read guide →Livingston County
Read guide →Sycamore Building Permit Guide
Read guide →Taylorville Building Permit Guide
Read guide →Tazewell County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Streator permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.