Randolph County, Illinois Building Permit Guide

To get a building permit in Randolph County, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Randolph County’s Land Resource Management Office in the Chester courthouse issues building permits and zoning certificates for rural land and for towns without their own zoning.

Authority: Land Resource Management OfficeOffice: Courthouse, Room 207, ChesterPhone: 618-826-5000, ext. 228
Zoning certificate
$35Waived for agricultural use
Building fee
$1 per $1,000Of value, $5 minimum, per application form
Permit life
1 yearFrom approval
New septic permit
$350Randolph County Health Department

In Randolph County, building permits and initial certificates of zoning compliance come from the Land Resource Management Office, Room 207 of the courthouse at 1 Taylor Street, Chester (618-826-5000, ext. 228). It covers every structure built or placed in unincorporated areas and in any municipality without its own zoning ordinance, and it says that every new structure needs a permit regardless of size. A typical house pays a $35 zoning fee plus $1 per $1,000 of its value, and the permit expires one year after approval.

What requires a permit in Randolph County?

County Code Section 6-2-1 says no structure may be erected, and no existing structure enlarged, extended, altered or relocated, and no mobile home located or relocated, until a Randolph County building permit is issued. The Land Resource Management Office’s answers to common questions show how far it reaches:

Permit needed

  • New homes and additions
  • Sheds, pole barns and garages, including portable buildings and carports
  • Structures smaller than 8 by 10 feet
  • Structures costing under $500, even if built from used material
  • Decks and porches not attached to a house
  • Grain bins
  • Mobile homes, which must be HUD-approved, 1976 or newer
  • Solar and wind farms, on their own application

Separate approvals

  • Private sewage and well permits from the Health Department
  • Variances, special uses, map amendments and appeals before the Zoning Board of Appeals
  • Deed approval for parcel splits under ordinance 07-16
  • Work inside a city or village that has its own zoning

The office’s answers to common questions add rural rules: only one dwelling may stand on a lot, except that extra single-family homes are allowed on an agricultural lot of record for relatives of the owners by birth, marriage or adoption; and a mobile home needs a permanent foundation that extends below the frost line, with no vinyl skirting.

Setbacks the site plan must meet

Under the zoning code’s district table, principal buildings in the Agricultural and R-1 districts sit at least 50 feet from the front lot line and 25 feet from side and rear lines; in R-2 the minimums are 25 feet front, 7 feet side and 25 feet rear, and the Industrial district matches the 50- and 25-foot figures. R-1, R-2 and commercial buildings are limited to 35 feet in height. Where a home relies on a septic system with a soil absorption field, the minimum lot is one acre. Accessory buildings may not stand in a required front yard in residential or agricultural districts, must stay 7 feet from side and rear lines in residential districts, and may never be used as a dwelling.

Short on time to read all of this?

Get a free quote →

What the county decides and what the state holds

The Board of Commissioners adopts the zoning, subdivision and flood plain codes and the fee resolutions. Ordinance 25-01, adopted January 17, 2025, made the 2018 International Building Code the official code for construction, alteration and demolition in unincorporated Randolph County. Private sewage systems follow the state’s private sewage disposal act and code, plumbing follows the state plumbing code, and plumbers and roofers hold state licenses.

Randolph County building department: who handles permitting

The Land Resource Management Office, led by Director Danny Valleroy, administers the county’s zoning, flood plain and subdivision ordinances, issues building permits and certificates of zoning compliance, takes applications for the monthly Zoning Board of Appeals meeting, approves deeds before recording, assigns 911 addresses and maintains the county GIS and tax maps.

Randolph County offices for building projects
OfficeContact
Land Resource Management (building permits, zoning, flood plain)Courthouse, 1 Taylor Street, Room 207, Chester, IL 62233; 618-826-5000, ext. 228 or 130; Monday to Friday 8 a.m. to 4 p.m.
Randolph County Health Department (septic, wells)2515 State Street, Chester; 618-826-5007; Sparta office, 211 N. Hasle Street, 618-443-2995
Highway Department (county roads)609 S. Chester Street, Sparta, IL 62286; 618-443-3213

Cities and villages

The zoning code applies throughout the county except inside municipalities that have adopted their own zoning codes, and the office also issues permits in towns without one. Randolph County has 14 municipalities: Chester (6,847), Sparta (4,022), Red Bud (3,761), Steeleville (1,883), Percy (905), Coulterville (825), Tilden (745), Evansville (533), Prairie du Rocher (510), Ellis Grove (324), Baldwin (313), Ruma (313), Rockwood (32) and Kaskaskia (22). Whether a given town has its own zoning ordinance decides which office you file with, so call the town hall or Land Resource Management before applying.

Randolph County permit types

One application covers both the initial certificate of zoning compliance and the building permit. The initial certificate confirms the work meets the zoning ordinance, the building permit records the structure, and a final certificate of compliance follows inspection.

Residential permits

  • Houses: dimensions and square footage, bathrooms, attic or basement, plus the house plans and proof the Health Department approved the septic system.
  • Sheds, pole barns and garages: dimensions, eave height, water hook-ups, electric service, any living space and bathrooms.
  • Grain bins: dimensions, bushel capacity, and age if used or moved.
  • Mobile homes: dimensions, make, model, year, VIN and foundation type.
  • All applications: the zoning district, fire district, existing and proposed use, estimated cost, contractor, and a site plan showing the lot, structures, driveways, easements, parking, signs and utilities with distances to lot lines.

Not sure this scope needs a permit?

Get a free quote →

Commercial permits

Non-residential buildings use the same application, with the 2018 International Building Code adopted for construction in unincorporated areas. Solar and wind farms file a separate zoning compliance and building permit application. In May 2026 the county board adopted new solar energy facility, energy storage system and wind energy facility ordinances (26-06, 26-07 and 26-08, dated May 8, 2026), so large energy projects start with a conversation with the office.

What comes before the building permit

  • Septic: the zoning code bars a building permit until a private sewage permit is issued; the zoning code names the Monroe-Randolph Bi-County Health Department, while the current application asks for Randolph County Health Department approval.
  • Zoning Board of Appeals: five kinds of applications go to its monthly meeting, and state law requires a Randolph County Soil and Water Conservation District permit with any of them.
  • Flood plain: in a Special Flood Hazard Area, give the base flood elevation, the required flood protection elevation and the actual elevation, plus topography and the lowest floor and lowest adjacent grade elevations.
  • Address: a 911 address is assigned to a new home when its permits are issued.
  • Lot splits: deeds that split a parcel are checked against ordinance 07-16 for a $25 fee before recording.

Randolph County permit fees

Randolph County’s building fee appears in three documents that do not agree. The undated application form the office posts now gives the everyday fees: a standard $35 zoning fee for the initial certificate of compliance (not charged for agricultural purposes or when waived) and a building fee of $1 per $1,000 of the structure’s estimated value, with a $5 minimum. Both can go on one check to the Randolph County Land Resource Management Office.

Rather talk it over?

Call 1-855-478-4290 →
Randolph County permit and health fees
ItemFee
Initial certificate of zoning compliance$35 (agricultural: none)
Building permit (application form, undated)$1 per $1,000 of value, $5 minimum
Late filing (work started before permits)$25
Special use, map amendment, appeal or variance (zoning code Appendix A, May 26, 2023)$160 filing + $40 publication = $200
Deed approval for a parcel split$25
New septic system permit$350
Septic repair / holding tank$200 / $175
Well permit (construct, modify or abandon)$100
Closed-loop geothermal wells$350 per 5 boreholes
Real estate water and sewage inspection$300

Worked example: a house valued at $250,000 pays $250 for the building permit and $35 for the zoning certificate, $285 in all, plus $350 for a new septic permit and $100 for a well if needed.

The second version is County Code Section 6-2-1, from Resolution 6-1-89 of May 15, 1989: a $5 minimum plus $1 per $1,000 of value over $5,000, which gives the same $250 for the house above. The third is Appendix A to the zoning code, adopted by Ordinance 2023-07 on May 26, 2023 and headed “Large Scale Solar/Wind Fees”: it lists the building permit at $2 per $1,000 of total project cost, beside the $35 zoning fee, the $25 late fee and the $200 hearing fees shown above. Ask the office which rate applies to a large or unusual project. Zoning filing fees are non-refundable, and a building code violation is a petty offense with a fine of up to $1,000.

Trade permits and who may pull them

Randolph County’s permit materials show no separate electrical, plumbing or mechanical permits and no county contractor registration. The application names the contractor and is signed by the applicant and, if different, the owner.

  • Septic applications: every packet needs a drawing with the distances between the tank or aeration unit, lateral field, sand filter, well, cistern or water line, the buildings served, slope arrows and property lines within 500 feet, plus a soil evaluation by a certified soil classifier; percolation tests are not accepted. Holding tanks are approved only in the limited cases the state code allows, and a system that discharges may need an NPDES permit from the Illinois EPA.
  • Septic installers and soil classifiers: the Health Department posts a list of licensed Illinois sewage disposal contractors and soil classifiers, reviews plans, issues septic permits, inspects installation and monitors septic pumpers.
  • Well drillers: the department reviews plans and issues permits for private wells, monitors well sealing and offers coliform testing for new construction.
  • Geothermal: a permit from the health officer is required for any closed-loop well system, and staff inspect each system after installation to record measurements and plots.
  • Plumbing and roofing: plumbers and roofing contractors hold state licenses, and plumbing follows the state plumbing code.

Rather not deal with the Randolph County building department?

Get a free quote →

Inside a town with its own zoning and building rules, ask that municipality about trade permits and contractor rules.

How to get a Randolph County building permit

1. Confirm who has jurisdiction

Unincorporated land and towns without their own zoning file with Land Resource Management.

2. Get septic approval

For a new home, apply to the Health Department first; a new system permit is $350.

3. Draw the site plan

Show the lot, structures, driveways, easements and utilities, with setbacks from every property line.

4. Complete the combined application

Fill in the zoning compliance and building permit form, with house plans for a residence.

5. Pay and file

Bring or mail it to Room 207 with one check covering the $35 zoning fee and the building fee.

6. Build within a year

The permit expires one year after approval; call for the final inspection when done.

Review, corrections and what causes delay

The instructions stress two things: sign the form, and show the setback measurements from the front, back and side property lines on the site drawing. A residence without septic approval cannot get its permit, and projects that need a variance or special use wait for the monthly Zoning Board of Appeals meeting and the soil and water district’s permit. Starting work before filing adds the $25 late fee.

Inspections and the final certificate

The county issues a final certificate of compliance when an inspection shows the work authorized by the initial certificate has been completed in line with the approved plan. The code says no final certificate is issued until all final qualifications, including the sewage requirements, are met.

The Health Department inspects the construction and installation of septic systems and inspects closed-loop geothermal wells after they are installed. For a home sale, it inspects a private water and sewage system for $300.

Want this handled start to finish?

Get a free quote →

Illinois building code in Randolph County

FEMA’s Community Status Book lists Randolph County (community 170575, unincorporated areas) as participating in the National Flood Insurance Program; its first flood insurance rate map is dated June 3, 1986 and the current map August 5, 2020. The county’s flood plain code is Ordinance 20-05 of June 12, 2020.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Permit search and official resources

Permit and zoning files are kept by Land Resource Management. To request copies, use the county’s FOIA request form and send it to the FOIA office, Room 206 of the courthouse at #1 Taylor Street, Chester (618-826-5000, ext. 141, or foia79@randolphcountyil.gov), and keep a copy in case you need to ask the Public Access Counselor for review.

Inspections are where schedules slip.

Get a free quote →

Randolph County permit FAQs

Do I need a permit for a small shed in Randolph County?

Yes. The county says any new structure needs a permit regardless of size, including portable buildings and sheds under 8 by 10 feet.

How much does a Randolph County building permit cost?

Under the current application form, $35 for the zoning certificate plus $1 per $1,000 of the structure’s value, with a $5 minimum; farm buildings pay no zoning fee. Older code text and the 2023 solar/wind fee appendix give other building rates, so confirm with the office.

How long is a permit valid?

One year from approval.

Does the county issue permits in Chester or Sparta?

Only in towns without their own zoning ordinance; in a town with local zoning, ask the town hall.

How much is a septic permit?

$350 for a new system, $200 for a repair and $175 for a holding tank, from the Randolph County Health Department.

Can I put a mobile home on my land?

With a permit, if it is HUD-approved and 1976 or newer, on a permanent foundation below the frost line, and it is the only dwelling on the lot unless the farm-family rule applies.

What happens if I start before the permit?

A $25 late filing fee is added to the regular fees.

Simplify Randolph County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Randolph County sooner?

Let Alliance prepare, file, and track your Randolph County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Randolph County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.