Justice, Illinois Building Permit Guide

To get a building permit in Justice, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

The Village of Justice Building Department at 8748 W. 82nd Place issues building, plumbing and electrical permits inside the village; you collect the three-part building application at its counter, and most permits are issued within 72 hours.

Authority: Justice Building DepartmentFees: Village Code ch. 13Phone: 708-458-2130
Authority
Building Department8748 W. 82nd Place, Justice
House permits
$0.60 per sq ft$100 minimum in R-1 and R-2
Contractors
$150 work permitInsurance and licenses on file
Hours
Mon–Fri 7:00–4:00Saturday by appointment

Inside the Village of Justice, building permits come from the village’s own Building Department at 8748 W. 82nd Place (708-458-2130), headed by Building Commissioner Edward Shilka; unincorporated land nearby is the Cook County Department of Building and Zoning’s job instead. The department hands out its three-part building application only at the counter, issues most permits within 72 hours, and charges $0.60 per square foot for new buildings and additions in the single- and two-family zones, with a $100 minimum, under Chapter 13 of the Village Code.

What requires a building permit in Justice?

Justice’s own permit list, revised April 6, 2023, reaches well past new buildings, including like-for-like window, siding and roof work and replacing a water heater or toilet.

Building Department permit

  • New houses, apartment buildings and commercial buildings, additions, remodeling and garages
  • Roofing, siding, soffit, fascia and gutters, and window and door replacement
  • Plumbing fixture replacements (water heaters with expansion tanks, toilets, sinks, tubs, showers), furnaces and air conditioning
  • Decks, porches, balconies, sheds of any material, pools above or in ground, fences and retaining walls
  • Asphalt and paver paving, and concrete driveways, sidewalks and patios
  • Electrical service upgrades (including hard-wired smoke detectors and GFCI receptacles), solar panels, signs, and fire, burglar and lawn sprinkler or alarm systems
  • Dumpsters and storage pods, demolition, moving a building, commercial satellite dishes, and fuel tanks

Other approvals

  • Public Works permit: street augering or street cuts, and sewer laterals
  • Cook County: a county demolition permit must be shown before the village demolition permit is issued
  • State agencies: installing or removing a fuel storage tank also needs EPA and State Fire Marshal permits
  • No permit: ordinary upkeep repairs that leave structure, exits, plumbing layout and wiring unchanged and add no fire hazard (Sec. 8-32(c)); re-shingling is not part of that exemption

If a project is missing from the list, call 708-458-2130. Starting work first costs a penalty of 50% of the permit fee on top of the fee itself, and electrical work begun before a permit pays twice the normal electrical fee.

What Justice decides and what the state holds

Justice is a non-home-rule village, as its sales-inspection form states. Section 8-31(e) of its code adopts the 2021 International Building, Residential, Existing Building, Mechanical, Energy, Fuel Gas and Swimming Pool and Spa codes, the 2018 Electrical Code of the City of Chicago, the 2014 Illinois Plumbing Code with local limits on allowable materials, the 2012 NFPA fire and life safety code, the 2021 property maintenance code and the State Fire Marshal’s rules. Its 2023 residential packet still lists a “2014 Chicago Plumbing Code”; the adopted code text names the Illinois Plumbing Code. Justice sets its own fees, contractor work permits, zoning and floodplain rules.

Justice building department: who handles permitting

The Building Department issues building, plumbing, electrical and mechanical permits for property inside the village and enforces the code through Building Commissioner and Code Enforcement Officer Edward Shilka. Its inspectors work part time and inspect by appointment. Floodplain decisions are made by the Building Commissioner together with the Village engineer. Parcels outside the village limits go to the Cook County Department of Building and Zoning.

Short on time to read all of this?

Get a free quote →
Justice permit contacts
DetailInformation
OfficeBuilding Department, 8748 W. 82nd Place, Justice, IL 60458
Phone / fax708-458-2130 / 708-458-3207
EmailPermits@villageofjustice.org
HoursMonday to Friday, 7:00 a.m. to 4:00 p.m.; Saturday by appointment only
Building CommissionerEdward Shilka, also Code Enforcement Officer
Zoning petitionsVillage Clerk, 7800 S. Archer Road, 708-458-2520
Fire protectionRoberts Park Fire Protection District tests sprinkler systems before occupancy

Justice permit types

Building work, apart from plumbing and electrical, goes on a three-part permit application that is available only at the Building Department counter. It asks for the date, the applicant’s name and address, a description of the work, the estimated cost, every contractor on the job and a signature. Sheds, new garages, pools, concrete, decks and foundation extensions also need a copy of the plat of survey. Plumbing, electrical, solar, sign, demolition and flood elevation requests use their own forms from the department’s web page.

Residential permits

  • New houses and tear-downs need a topographical survey with foundation and lot grades, three sets of drawings signed by a licensed architect, and, in a flood zone, an elevation certificate. Single-family homes that are new, or altered by 50% or more of their original floor area, must be fully sprinklered to NFPA 13D, with heads near the furnace and water heater and in any attached garage.
  • Garages may be up to 864 square feet, 36 feet long and 14 feet tall, set at least 10 feet from the rear lot line and 5 feet from the side.
  • Sheds are limited to one per lot, 12 by 12 feet, with 8-foot walls and a 10-foot overall height, and must be anchored as the Building Commissioner approves.
  • Fences may be 6 feet tall in rear yards and between buildings and 4 feet in front yards, or 8 feet where a home lot abuts commercial or industrial land.
  • Solar panels need the solar form plus an electrical application, with a 3-foot clear space at the ridge and sides of a house roof.

Commercial permits

Buildings in the R-3, B-1, C-1 and industrial districts are charged by floor area on a sliding scale. Plans must be prepared by licensed architects or structural engineers. Sprinkler plans go to the Building Department with the building plans, and the fire district tests the system before an occupancy permit is issued. Connections that need a Metropolitan Sanitary District permit carry a village review fee of at least $400.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning Board of Appeals. Rezoning, variances, special uses, consolidations and subdivisions use the zoning petition, filed notarized with the Village Clerk with a $2,200 non-refundable fee. Owners within 250 feet must be notified before filing.
  • Setbacks. The packet shows a 30-foot front yard, side yards of 10% of the lot width or 5 feet, whichever is greater, a 20-foot street side on corner lots, and a 30-foot height limit in R-1 and R-2.
  • Floodplain. The Building Commissioner and Village engineer decide whether a site lies in a flood fringe or floodway; buildings must be protected to one foot above the base flood elevation.
  • Streets and sewers. Street cuts and sewer laterals need a Public Works permit.

Justice permit costs and fees

Permit and inspection fees sit in Section 13-1, “Rates and Fees,” of the Village Code; the posted chapter is current through Ordinance 2026-18 of May 11, 2026. Most small permits are a flat fee plus a set number of $75 inspections.

Justice building permit fees (Village Code Sec. 13-1)
WorkFee
New buildings and additions, R-1 and R-2 zones$0.60 per sq ft; $100 minimum
New buildings and additions, R-3, B-1, C-1, I-1, I-1R, I-2$0.40 per sq ft up to 20,000 sq ft; larger buildings on a sliding scale
Residential garage$0.20 per sq ft, $60 minimum, plus at least 2 inspections
Roof, siding, gutters, soffit and fascia, windows and doors$100 plus at least 1 inspection
Tear-off re-roof, furnace, air conditioning, fireplace$100 plus at least 2 inspections
Flat roof / concrete flat work$0.05 per sq ft plus 2 inspections / $0.15 per sq ft
Shed / fence / pool$100 each, plus $75 per inspection
Demolition$0.30 per sq ft, $60 minimum, plus at least 2 inspections
Foundation permit / foundation bond$100 plus 2 pre-pour inspections / $1,000 bond
Building development fee (new home, tear-down, unit conversion)$3,000
Plan review$150 per hour, 1-hour minimum
Inspections and re-inspections$75 each
Driveway (single-family)$0.10 per sq ft, $200 maximum, plus $75 pre-pour inspection

Rather talk it over?

Call 1-855-478-4290 →

The square-foot rate makes the arithmetic simple: a 400-square-foot addition in an R-1 zone is 400 × $0.60, or $240, before inspections; a 5,000-square-foot commercial building is 5,000 × $0.40, or $2,000. Above 20,000 square feet the printed bands start from $2,400, a figure that does not follow on from the first band, so ask the department to price a large building.

The 2023 packet still shows a $50 re-inspection fee and $50 dumpster permits; the adopted Chapter 13 sets $75 and $100. Improvements needed for a disabled veteran’s accessibility are exempt from building permit fees under Sec. 8-32(h).

Trade permits and who may pull them

Every contractor working in Justice first needs a village work permit (Sec. 8-45): $150, non-refundable, valid one year, and carried on the person or in the vehicle. The application asks for a certificate of liability insurance of $100,000/$300,000 and workers’ compensation naming the Village as certificate holder (or a notarized letter from a sole proprietor), the federal lead-safe RRP certificates for pre-1978 buildings, and copies of state licenses for plumbers, roofers and alarm and sprinkler contractors.

  • Plumbing: only a holder of a valid Illinois plumber’s license may install or alter plumbing. Since Ordinance 2026-07 of March 9, 2026, homeowners may install fixtures or trim only, without moving or replacing pipes. Fees are $100 minimum, $15 per fixture and $5 per fire or lawn sprinkler head.
  • Electrical: work follows the City of Chicago electrical code, and the work permit form asks for “a copy of an Electricians License from the City of Testing.” Service fees run $100 for 100 amps, $200 for 200 amps and $400 for 400 amps; alarm and communication systems are $150; electrical plan review is $150 an hour.
  • Roofing: all roofing and waterproofing must be done by a State of Illinois licensed roofing contractor, except that an owner may re-shingle their own single-family home after signing a statement that only licensed roofers will be paid to help.
  • HVAC and sprinklers: furnace and air conditioning permits are $100 plus two inspections; sprinkler rough and final inspections are $100 each.

How to apply for a Justice building permit

1. Check the list and zoning

Compare the job with the permit list and the setbacks in the residential packet; file a zoning petition first if you need a variance.

2. Register your contractors

Each contractor files the work permit application with insurance certificates, licenses and the $150 fee.

3. Pick up the application

Collect the three-part building application at 8748 W. 82nd Place; download the plumbing, electrical, solar or sign form if the job needs one.

4. Attach plans and survey

Add the plat of survey, drawings (three sets signed by an architect for a new house) and, for new construction, a topographical survey.

5. Pass plan review

A licensed engineering firm chosen by the village reviews architectural plans; the fee is owed once review is under way.

6. Pay and post the permit

Pay the fees, then post the permit card on the street side of the building until 10 days after the final inspection.

Rather not deal with the building department?

Get a free quote →

Review, corrections and what causes delay

Simple permits are usually ready within 72 hours, but a project with plans waits for the Building Department, the Village Engineer and the structural engineer to approve them. You have 24 hours after submitting plans to stop the review without charge; after that the plan review fee is owed whether or not you build. Missing contractor work permits, an unpaid village bill or an open code violation can each block a permit under Sec. 8-32(i).

Inspections and certificates in Justice

Inspection request forms come with the permit. Date and sign each one and return it by mail, at the counter or in the silver box on the outside wall of the Building Department; the inspector then sets an appointment, usually within 72 hours. Someone must be home for interior work; a missed appointment costs a re-inspection fee.

  • Pre-pour: footings and foundation forms before concrete.
  • Spot survey: foundation elevations and location go to the Village engineer, and work stops until the survey is approved.
  • Underground and rough: underground plumbing, drain tile and electrical before the floor is poured, then rough plumbing, electrical, HVAC, sprinkler, insulation and framing before walls are closed.
  • Sewer and service: the plumbing inspector checks the sanitary sewer; each electrical service is inspected.
  • Final: building, plumbing, electrical, HVAC, sprinklers, alarms, driveways, sidewalks and lot grading; the fire district inspects just before the final.

No building may be occupied until the Building Commissioner issues a certificate of occupancy, and bonds are refunded only after every inspection passes. Buyers and new tenants of homes also need a certificate of housing inspection issued within the prior three months; it costs $150 for a house, condo or townhome, and either buyer or seller may make the listed corrections. Building work is banned between 9:00 p.m. and 7:00 a.m.

Illinois building code in Justice

Justice enforces the codes listed in Sec. 8-31(e) of its own Village Code and adds local rules, such as the single-family sprinkler requirement in Sec. 4-94. FEMA’s Community Status Book lists the Village of Justice (community 170112) as participating in the National Flood Insurance Program, with its current flood map dated August 19, 2008, and the village’s floodplain article applies in mapped flood areas.

Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline

Want this handled start to finish?

Get a free quote →

Justice permit search and official resources

To see past permits, plans or inspection records, send a Freedom of Information Act request on the village form by email to foia@villageofjustice.org, or deliver it in person to the Finance Department at 7800 Archer Road. The Building Department can say at 708-458-2130 whether an address has an open permit.

Inspections are where schedules slip.

Get a free quote →

Justice building permit FAQs

Do I need a permit to replace windows or a roof in Justice?

Yes. Window and door replacement, roofing, siding and gutters are all on the village permit list; each is $100 plus at least one $75 inspection, and a tear-off re-roof needs two.

How much is a building permit for a house addition?

In the R-1 and R-2 zones, $0.60 per square foot with a $100 minimum, so a 400-square-foot addition is $240 plus inspections and any plan review at $150 an hour.

Can a homeowner pull permits in Justice?

Owners may act as their own general contractor with the department’s help, and may re-shingle their own single-family home. Plumbing by an owner is limited to fixtures and trim, and every hired contractor needs a village work permit.

Does a new house need fire sprinklers?

Yes. New single-family homes, and homes altered by 50% or more of their original floor area, must be sprinklered throughout to NFPA 13D.

What does a contractor need before working in Justice?

A $150 village work permit, valid one year, backed by liability and workers’ compensation certificates naming the village and copies of the required licenses.

Is an inspection needed when I sell my home?

Yes. A certificate of housing inspection, $150 for a single-family home, must be issued within three months before a buyer or tenant moves in.

Simplify Justice permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Justice sooner?

Let Alliance prepare, file, and track your Justice permits while your crew stays on the job.