Inside the Village of Algonquin, building permits come from the Community Development Department at the Ganek Municipal Center, 2200 Harnish Drive. Residential applications go through the village’s online portal, by email to permits@algonquin.org or over the counter, and review can take up to five weeks. Fees are set in Appendix B of the village code: most small residential permits such as a fence, shed or patio cost $45, and a new house is charged per square foot of living and garage area or 0.75% of construction cost, whichever is greater.
What requires a building permit in Algonquin?
The village’s rule is broad: a permit is needed before anyone erects, constructs, enlarges, alters, repairs, moves, improves, removes, converts or demolishes a building or structure. Chapter 23 of the village code spells out the residential side. Roof coverings, siding, patios, decks, gazebos, porches, detached accessory buildings, sidewalks, driveways, fences, swimming pools and retaining walls all need a permit, as does any electrical, gas, mechanical or plumbing installation or replacement. A shipping container used for temporary storage needs one once it stays more than 14 consecutive days, and it may never stay more than 90.
Permit needed
- New homes, additions, finished basements and remodeling
- Roofing, siding, windows and doors, including a garage service door
- Gutters and downspouts
- Decks, patios, walks, driveways and fences
- Sheds, gazebos and detached garages
- Pools, hot tubs and storable pools
- Radon mitigation when a fan needs wiring
No permit
- Painting, wallpaper, tile, carpet and countertops
- Prefabricated pools that cannot hold 2 feet of water
- Retaining walls up to 2 feet that carry no surcharge
- Playground equipment at a one- or two-family home
- Repairing up to 2 fence panels and 3 posts
- Up to 200 square feet of roof or siding repair
- Driveway sealant, fish ponds and patio sitting walls under 24 inches
Portable fire pits do not need a permit but must sit 25 feet from the house. A prefabricated storage box of less than 100 cubic feet is exempt only if it stands in the rear yard and outside any easement. In the historic district, every exterior change, addition or demolition also needs a Certificate of Appropriateness.
What Algonquin decides and what the state holds
The village writes its own building code. Chapter 23, in the printing dated May 19, 2026, adopts the 2018 International Residential, Building, Fire, Mechanical, Fuel Gas, Existing Building, Property Maintenance and Swimming Pool and Spa codes, the 2017 National Electrical Code, the 2014 Illinois State Plumbing Code, the 2018 Illinois Accessibility Code and the 2024 International Energy Conservation Code with Illinois’ modifications (amended by Ordinances 24-O-28 and 26-O-21). Appeals of the building official’s decisions go to the Village Board. Plumbing work must follow the state plumbing code, and the roofing and plumbing licenses the village asks to see are state licenses.
Short on time to read all of this?
Get a free quote →Algonquin building department: who handles permitting
The Community Development Department handles plan review, permit issuance, field inspections and certificates of occupancy. Within it, the Building division also enforces the sign code and property maintenance rules and acts as the village’s floodplain administrator. Algonquin lies in both McHenry and Kane counties, but neither county permits work inside the village: the same office covers every address within the village limits.
| Detail | Information |
|---|---|
| Office | Community Development, Ganek Municipal Center, 2200 Harnish Drive, Algonquin, IL 60102 |
| Phone | 847-658-2700, option 3 (fax 847-658-2631) |
| permits@algonquin.org | |
| Hours | Monday to Friday, 8:00 a.m. to 5:00 p.m. |
| Online portal | css.algonquin.org (residential applications, payments and inspection requests) |
| Workload | 3,088 permits in 2025; 2,832 from January to October 2026 |
Algonquin permit types
The village publishes checklists for common projects that list the documents to submit, the fee and the inspection steps.
Residential permits
- Fences. A plat of survey with the fence highlighted, a description of the fence and the Property Owner Release and Waiver of Liability. Many subdivisions have stricter recorded fence rules, and the village warns that its permit does not override them, so written HOA approval is worth getting first.
- Finished basements. Building plans plus copies of the electrical, plumbing and roofing licenses of the trades involved; the fee is 0.75% of construction cost with a $45 minimum, plus trade and plan review fees.
- Windows and doors, irrigation, radon systems and demolition. Each has its own checklist on the Building division page.
- New houses and major additions. Drawings must be sealed by an Illinois-licensed architect or structural engineer. The same applies to additions above the first floor, changes to bearing walls, beams or the roof, retaining walls 5 feet or taller and other work the building official judges substantial. A plat of survey by an Illinois professional engineer or land surveyor must show the work, easements, any floodplain or wetland and, for a new dwelling, the proposed top of foundation.
- Certificate of occupancy. Anyone moving into a newly built home needs a certificate of occupancy permit first, requested on the village’s online form.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial work starts on the village’s commercial application form with one electronic set of plans; once approved, one paper set is stamped as the job-site copy. Separate guides cover tenant alterations, kitchen exhaust, suppression systems, fire alarm and sprinkler plan review and winter salt storage ($75 permit). A new or remodeled food establishment must first get plan review approval from the county health department (McHenry or Kane, by location) and include the approval letter. The building official may send plans or inspections to a third-party agency, and the owner reimburses those costs before the permit or certificate of occupancy is issued.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning relief. The Planning & Zoning Commission meets on the second Monday of each month. It hears appeals under the zoning ordinance, holds public hearings on variations, special uses and planned unit developments, reviews plats and sends recommendations to the Village Board. A single-lot residential request or a variation costs $600 in review fees, and a $3,000 escrow is collected for a variation or special use.
- Historic district. A Certificate of Appropriateness is required for exterior changes, and Historic Commission approval comes before plan review for everything except roof and interior permits.
- Stormwater and floodplain. The Building division is the floodplain administrator. The village charges a watershed protection fee of $250 per new home and $100 per 10,000 square feet of commercial or industrial building.
- Kane County road impact fee. New development on the Kane County side must attach its receipt for the Kane County Road Improvement Impact Fee to the building permit application.
Algonquin permit costs and fees
Permit fees are listed in Appendix B of the village code (Penalty, Salary, Bonds and Fees), most recently printed on May 19, 2026. The building fee for new construction is figured from floor area or as 0.75% of the construction cost on the application, whichever is greater, and trade, plan examination and occupancy fees are added on top. Fees are rounded up to the next dollar, and the fence checklist notes that its fee is not due until the permit is ready.
Rather talk it over?
Call 1-855-478-4290 →| Work | Fee |
|---|---|
| New one-family home with basement or crawlspace | $0.84 per sq ft of living area plus $0.30 per sq ft of garage, or 0.75% of construction cost if greater |
| New one-family home on a slab | $0.72 per sq ft of living area plus $0.30 per sq ft of garage, or 0.75% of cost if greater |
| Residential alterations and remodeling | 0.75% of construction cost, $45 minimum |
| Non-residential new building / interior build-out | $0.99 / $0.75 per sq ft, or 0.75% of cost if greater |
| Plan examination, new one-family home | $95 per dwelling unit |
| Plan examination, residential addition or alteration | 10% of the permit fee, $45 minimum |
| Deck, gazebo, dock or pier | $85 for the first 150 sq ft plus $20 per additional 150 sq ft |
| Fence, shed, patio, fireplace, hot tub, walk or driveway | $45 each |
| Re-roof, one-family home | $45 per dwelling |
| Window or door replacement | $10 per window, $45 minimum |
| Above-ground / in-ground pool | $150 / $300 |
| Demolition of a one-family house | $300 |
| Certificate of occupancy, one-family | $75 per unit ($100 for a temporary certificate) |
| Reinspection | $45 per inspection |
| Work started without a permit | Penalty equal to 100% of the permit fee |
Worked example from the deck rule: a 300-square-foot deck pays $85 for the first 150 square feet and $20 for the next 150, a $105 permit.
Permit extensions must be requested in writing and cost 25% of the permit fee for the first six months, 50% for the second and 100% for the third, each with a $45 minimum. A permit whose work has not started within six months of issuance is voided; if a permit is withdrawn or voided, part of the fee may be refunded on written request, but the plan review portion is kept and at least $45 is retained. New homes also pay the watershed protection fee, a $25-per-unit public art fee and water and sewer tapping fees that depend on the number of bedrooms and when the subdivision plat was approved; Ordinance 26-O-17 amended both tapping tables in 2026.
Trade permits and who may pull them
Algonquin licenses electrical contractors. Under Chapter 23 no one may run an electrical contracting business in the village without a license; a contractor licensed for the current year by another Illinois city or village shows proof of that license, and candidates must pass a written examination given by an Illinois municipality that administers one. The village’s Electrical Commission recommends electrical standards, permit rules and inspection fees. For finished basements and similar jobs the village asks for copies of the electrical, plumbing and roofing licenses of the trades on the job.
Rather not deal with the building department?
Get a free quote →Trade fees come from the same Appendix B schedule: new plumbing fixtures are $25 each with a $45 minimum, a water heater replacement is $10 and a water or sewer connection is $75. A furnace or air-conditioner replacement is $45 per residential appliance, a new 101-to-200-amp electric service is $175 and a whole-house generator or rooftop solar system on a house is $100.
How to apply for an Algonquin building permit
Find your project on the village’s permit pages and gather the survey, drawings and licenses it lists.
Clear subdivision covenants and, in the historic district, the Historic Commission before plan review.
Residential work goes through css.algonquin.org; you may also email permits@algonquin.org or file at the Ganek Municipal Center. Drawings larger than 11 by 17 inches go in as paper copies.
Use the village’s Plan Resubmittal Form to send revised plans.
Pay online or by check to “Village of Algonquin” by mail or in the municipal center drop box.
Do not start until the permit is issued, and keep it on the job site.
Review, corrections and what causes delay
The village warns that review may take up to five weeks. A plat of survey that does not show distances to lot lines, easements or a floodplain, unsealed drawings for work that needs a seal, and missing trade licenses are the usual reasons an application stalls. On a new house two more surveys are needed during construction: a foundation as-built survey, which must be approved before framing continues past the first floor deck, and a final as-built and grading plan before the certificate of occupancy. Chapter 23 requires work to be finished and finaled within 180 days of issuance, or one year for houses, townhouses and dwelling additions or alterations; the fence and basement checklists print a shorter six-month window, so ask which applies before scheduling a long job.
Inspections and certificates in Algonquin
Inspections are requested online only, through the village’s customer self-service site, where you can sign in with a Google, Apple, Microsoft or Facebook account. For five simple jobs the village accepts a self-inspection submitted through an online form: driveway final, fence final, roof ice and water shield, siding final and window or door replacement.
Construction sites need paved road access, an address sign with letters at least 3 inches high and a gravel construction driveway from the curb. Each failed inspection that has to be repeated costs $45. A new home cannot be occupied until the certificate of occupancy is issued after the final inspection and the approved final grading survey.
Want this handled start to finish?
Get a free quote →Illinois building code in Algonquin
Algonquin enforces the 2018 International codes, the 2017 National Electrical Code and the 2024 energy code adopted in Chapter 23. FEMA’s Community Status Book lists the Village of Algonquin (community 170474) as participating in the National Flood Insurance Program, with current flood maps dated August 3, 2009; the village is not in the Community Rating System. Building in a mapped floodplain starts with the Building division as floodplain administrator.
Illinois leaves building codes to local government, but since 1 January 2025 any local code must regulate structural design at least as strictly as baseline editions of the International Building, Existing Building and Residential Codes, and where no code was adopted the statute sets minimums for commercial buildings and new homes (Public Act 103-0510). Illinois codes and the statewide baseline
Algonquin building permit FAQs
How much is a building permit in Algonquin?
Small residential jobs such as a fence, shed, patio, driveway or re-roof are $45. Remodeling is 0.75% of construction cost with a $45 minimum, and a new house is charged per square foot of living and garage area or 0.75% of cost, whichever is greater.
Do I need a permit to replace my roof in Algonquin?
Yes, unless the repair covers 200 square feet or less of roofing in total. A re-roof on a one-family home is $45, and the ice and water shield can be passed by self-inspection.
Do I need a permit for a fence?
Yes. Replacing up to two panels and three posts is exempt, but anything more needs a $45 permit with a highlighted plat of survey and the owner’s release and waiver.
How long does Algonquin take to review a permit?
The village says review may take up to five weeks. Historic district projects need Historic Commission approval first, except roof and interior work.
How do I schedule an inspection?
Online only, through the village’s self-service portal. Fence, driveway, roof underlayment, siding and window or door finals can be done as self-inspections.
Does an electrician need an Algonquin license?
Electrical contractors must hold a license; one issued by another Illinois city or village for the current year is accepted with proof.
Does Kane County or McHenry County issue permits in Algonquin?
No. The village permits every address within its limits on both sides of the county line.
Algonquin permit search and official resources
The village’s customer self-service portal takes permit applications, payments and inspection requests. Monthly permit totals back to 2012 are posted in the village’s permit activity reports. For copies of permits, plans or inspection records, file a Freedom of Information Act request with the Village Clerk’s Office through the online request form on the village’s FOIA page.
Inspections are where schedules slip.
Get a free quote →- Algonquin permit information
- Building division and project checklists
- Chapter 23, Building Codes
- Appendix B, fee schedule
- Building permit process sheet
- Building inspections and self-inspection forms
- Algonquin customer self-service portal
- Fence permit checklist
- Finished basement permit checklist
- Commercial permit checklist
- Building permit activity reports
- Planning & Zoning Commission
- Freedom of Information Act requests
Simplify Algonquin permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Illinois. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Algonquin sooner?
Let Alliance prepare, file, and track your Algonquin permits while your crew stays on the job.
More Illinois permitting guides
McHenry County
Read guide →Cary
Read guide →Crystal Lake
Read guide →Alsip Building Permit Guide
Read guide →Alton Building Permit Guide
Read guide →Antioch Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Algonquin permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.