The City of Woodstock Building Department issues building permits and carries out combination inspections for property inside city limits. Applications, fee payments and inspection requests go through the City’s BS&A Online account.
What requires a building permit in Woodstock?
The City building permit application covers new construction, alterations, additions, accessory structures and repairs, residential and commercial. Electrical, plumbing, HVAC, pools, signs and similar work need separate permits.
Site disturbance can create an additional City permit. Woodstock’s Land Development Code requires a land development permit before site work where the disturbed area is greater than 0.1 acre, or 4,356 square feet. Projects below that threshold can still be required to follow the land-development process at the discretion of Community Development.
Who issues permits in Woodstock?
Property in unincorporated Cherokee County is permitted by Cherokee County, not the City.
| Detail | Information |
|---|---|
| Building Department | 12453 Highway 92, Suite 105, Woodstock, GA 30188 |
| woodstockbuilding@woodstockga.gov | |
| Phone | 770-592-6054 |
| Online service | City of Woodstock BS&A Online |
Short on time to read all of this?
Get a free quote →Woodstock permit types and BS&A filing
Woodstock’s BS&A Online account lets applicants apply for a permit, apply for a planning, zoning or engineering process, search Building Department records, pay Building Department fees and schedule inspections.
Residential plan review needs two sets of plans and house location plans, or three sets for a single-family attached home or a home in the Downtown District. Commercial projects, attached multifamily homes and attached single-family homes must include a completed Fire Department review application.
Permit costs and fees in Woodstock
Commercial projects pay an upfront plan review fee based on construction value: $25 for $5,000 or less, $100 for $5,000.01 to $50,000, $200 for $50,000.01 to $150,000 and $300 above $150,000.
Electrical, plumbing, mechanical and fire coordination
Separate permits are needed for electrical, plumbing, heating, ventilation and air conditioning, pools and signs. New single-family homes list their electrical and other subcontractors on the application, with subcontractor affidavits.
Application documents and plan review
The building application asks for two sets of building plans and site plans with a detailed scope of work, the plan submittal checklist, a driver’s licence, business licence, proof of water meter payment where applicable, the state contractor’s licence where applicable, an Authorized Permit Agent form if the applicant is not the licence holder, and an owner-builder affidavit for homeowners acting as general contractor.
Not sure this scope needs a permit?
Get a free quote →The residential checklist asks for a cover sheet with current codes and design loads, floor, electrical, elevation and structural plans, a square footage table, and a house location plan sealed by a registered land surveyor. The applicant certifies that no work has begun before the permit is issued.
For land-development work, the City code requires approved site plans before an LDP is issued, and a pre-construction meeting is required before land-development permit issuance.
How to apply: 6-step Woodstock process
Make sure the parcel is inside Woodstock city limits rather than unincorporated Cherokee County.
Assemble the application, 2 plan sets/site plans, detailed scope, credentials and project-specific affidavits.
Create or use the City BS&A account to apply, search records, pay fees and manage inspections.
Respond to Building Department, fire and any planning/engineering or land-development requirements associated with the scope.
The City performs combination inspections; the general contractor is responsible for scheduling them through BS&A.
Pass all required inspections for the permit.
Rather talk it over?
Call 1-855-478-4290 →Woodstock inspections
Woodstock performs combination inspections, and the general contractor is responsible for scheduling all of them through BS&A Online. Inspections scheduled by 6:00 p.m. are completed the next business day or on the requested date.
If someone must be present, they should be available between 8 a.m. and 4 p.m. Staff cannot give an estimated arrival time for inspectors.
Site-work inspections follow a separate rule set. The Land Development Code states that Public Works and Community Development conduct inspections for site work and can require corrections or issue a stop-work order when work does not match approved plans or City requirements.
Local Woodstock details that matter
0.1-acre land-disturbance trigger: The City code requires an LDP when disturbed area is greater than 4,356 square feet, and smaller projects can still be routed through land development at the City’s discretion.
Rather not deal with the building department?
Get a free quote →Pre-construction meeting: A pre-construction meeting is required before issuance of a land-development permit.
Georgia building code
Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes
Official Woodstock permitting resources
These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.
- Georgia DCA current state minimum codes
- Woodstock Land Development Code
- Woodstock inspection scheduling
- Woodstock building permit application
- Woodstock BS&A Online
Want this handled start to finish?
Get a free quote →Woodstock permit FAQs
Does Woodstock issue its own building permits?
Yes. The City Building Department administers building permits for work inside Woodstock city limits.
Can permit work be handled online?
Yes. Woodstock’s BS&A Online account handles permit applications, record searches, fee payments and inspection scheduling.
Who schedules inspections?
The general contractor schedules all of the City’s combination inspections through BS&A Online.
When is a land-development permit required?
The City code requires an LDP before site work disturbing more than 0.1 acre, or 4,356 square feet; smaller projects can also be required to use the process.
Are trade permits separate?
Yes. The City building application states that electrical, plumbing, HVAC, pools, signs and other specialty work require separate permits.
Inspections are where schedules slip.
Get a free quote →Simplify Woodstock permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Woodstock sooner?
Let Alliance prepare, file, and track your Woodstock permits while your crew stays on the job.