Statesboro, Georgia Building Permit Guide

To get a building permit in Statesboro, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

How building permits, applications and inspections work in the City of Statesboro.

Authority: City of Statesboro Planning & DevelopmentCode: Georgia State Minimum Standard Codes (2024)
Authority
City of Statesboro Planning & DevelopmentBuilding permitting and project management
Apply / Intake
CommunityCoreRegister before applying
Inspections
Building InspectionsVertical construction inspections

Inside Statesboro city limits, building, electrical, plumbing and HVAC permits all come from the City’s Planning & Development Department, and applications are filed online through CommunityCore. A new home is charged $0.46 per square foot plus a 5% plan review fee and $35 per inspection, and plan review generally takes about 2 weeks.

What requires a building permit in Statesboro?

The City’s Vertical Construction Packet lists the projects that need a permit inside city limits. Electrical, mechanical and plumbing or gas work is permitted separately for homes and for commercial buildings.

Residential

  • New single-family homes, townhomes and duplexes
  • Additions and alterations
  • Accessory structures
  • Re-roofs
  • Demolition
  • Electrical, mechanical and plumbing/gas work
  • Solar
  • Manufactured homes

Commercial

  • New buildings, including multi-family
  • Additions, alterations and accessory structures
  • Re-roofs and demolition
  • Electrical, mechanical and plumbing/gas work
  • Solar
  • Occupancy
  • Stand-alone and wall signs
  • Cell towers

The packet also lists permits for pools and hot tubs, foundation installation, foundation repair and preliminary site plans. Demolition, site review, small cell wireless and sign work each have their own City application, and a building permit does not replace a site review or zoning approval when the project needs one.

Statesboro building department: who handles permitting

Planning & Development handles permits for property inside Statesboro city limits. Its Building Inspections division reviews construction plans, verifies contractor licensing, issues structural, electrical, plumbing and HVAC permits, inspects the work and issues the Certificate of Occupancy. Robbie Jordan is the Chief Building Official.

For development projects, the City has designated a Project Manager as the single point of contact between City staff and the developer during the building permit process.

Statesboro permitting contact
DetailInformation
DepartmentPlanning & Development / Building Inspections
Phone912-764-0630
Emailplanning.development@statesboroga.gov
Address50 East Main Street, Statesboro, GA 30458
ApplyCommunityCore (account required)
Chief Building OfficialRobbie Jordan, 912-764-0645

Short on time to read all of this?

Get a free quote →

Statesboro permit types and online filing

All building permit applications go through CommunityCore: register for an account first, then use Apply for Permit. The same portal is used to request inspections. Paper copies can be sent to ATTN: Planning & Development, 50 East Main Street, Statesboro, GA 30458.

Forms the City publishes next to the online application:

  • Contractor Listing, naming the contractor and subcontractors on the job.
  • Authorized Permit Agent Form, the state licensing board’s notarised form that lets a licensed contractor’s qualifying agent name another person to pull permits. One original form is needed per permit, with copies of the qualifying agent’s and company’s licences and the agent’s photo ID.
  • Affidavit for Self Contractors, for owners acting as their own contractor. The City accepts it only when the permit is for your primary residence.
  • Special and Third Party Inspections Application, for projects that need special or third-party inspections.

Permit costs and fees in Statesboro

Fees come from the City’s adopted FY2027 Schedule of Fees, Rates and Fines. Building permit fees are charged by square footage, and plan review and inspection fees are added on top.

Statesboro building permit fees (FY2027)
ProjectFee
New single-family home or townhome$0.46 per sq ft
Accessory structure$0.16 per sq ft or $50, whichever is greater
New commercial building with build-out$0.67 per sq ft
Commercial shell building$0.22 per sq ft
Commercial alteration$0.45 per sq ft
Plan review (all permits)5% of the building permit fee
Demolition$75 per structure
Moving a structure$100 per structure

For example, a new 2,000 sq ft home has a building permit fee of $920 and a plan review fee of $46, before inspection and trade permit fees.

Not sure this scope needs a permit?

Get a free quote →

Each inspection costs $35. If an inspection has to be repeated, the second visit costs $50, the third $75, and the fourth and later visits $100. All open fees must be paid before final certificates are issued. The City’s January 2026 Vertical Construction Packet still lists accessory structures at $0.46 per sq ft, so confirm that figure with the City before you budget.

Electrical, plumbing and HVAC permits in Statesboro

Building Inspections issues electrical, plumbing and HVAC permits for work inside city limits, at these FY2027 rates:

Statesboro trade permit fees (FY2027)
PermitFee
Electrical, 60–100 A main switch$31.50
Electrical, 101–200 A$52.50
Electrical, 201–400 A$84
Electrical, 401–600 A$115.50
Electrical, each circuit in use$3 on top of the service fee
Plumbing$6 per fixture
HVAC, up to 49,999 BTU heating$9 per ton
HVAC, 50,000–100,000 BTU$20, plus $20 for every additional 100,000 BTU

Each trade permit has a $35 minimum, and larger electrical services are priced on the City’s fee schedule. Fire inspections are carried out by the Statesboro Fire Department’s fire prevention office (912-764-3473).

Application documents and plan review

Everything must be uploaded in CommunityCore before plan review starts. Check the submittal against the City’s list first, because resubmittals with redactions are not accepted.

Rather talk it over?

Call 1-855-478-4290 →

New home

  • Completed building permit application, listing the contractor and subcontractors
  • Plans drawn to the current adopted codes with Georgia Amendments
  • Foundation plan with details (monolithic, stem wall, crawl space or pier)
  • Floor plan for each storey with dimensions, window sizes and total square footage
  • Roof framing plan and exterior elevations
  • Wall sections and details, including fire wall details and UL listings for duplexes and townhomes
  • Engineered or structural designs stamped by a PE or RA on every page, where the project needs them

New commercial

  • Completed building permit application
  • Contractor Listing
  • Complete architectural and structural plans to the current adopted codes
  • Plans stamped by a Georgia RA or PE
  • Life safety plans with the plan set

If the occupancy is under the Georgia State Fire Marshal’s jurisdiction (O.C.G.A. 25-2-13), the plans also go to the State Fire Marshal, and the City will not issue the building permit until it has the State Fire Marshal’s approved set.

Each City department generally reviews and redlines plans within about 2 weeks, and can take up to 30 days.

How to apply: 6-step Statesboro process

1. Check the address

Make sure the site is inside Statesboro city limits rather than unincorporated Bulloch County.

2. Book a Right Start meeting for development projects

New businesses and developments can meet all City development departments at once before drawing up formal plans; annexations and rezonings must have one.

3. Register in CommunityCore

Create an account before starting the online application.

4. Apply and upload

Submit the application, Contractor Listing and plans, plus the Authorized Permit Agent Form or Self Contractor Affidavit where it applies.

5. Answer redlines

Revise the plans in response to each department’s comments; review generally takes about 2 weeks.

6. Pay, build and book inspections

Pay the open fees, then request each inspection in CommunityCore until the final inspection and Certificate of Occupancy.

Rather not deal with the building department?

Get a free quote →

Statesboro inspections

Book inspections in CommunityCore, by phone at 912-764-0630 or by email to planning.development@statesboroga.gov. Inspections requested before 4:00 p.m., Monday to Friday, are generally carried out the next business day. Finish the work before you book, and note that a requested morning or afternoon slot is not guaranteed.

The City’s Residential Inspection Checklist sets out the steps and requirements for residential inspections. Before a Certificate of Occupancy is issued for a home, the inspector checks that the Georgia Residential Energy Code Compliance Certificate is posted on or near the electrical panel or air handler.

Local Statesboro details that matter

Right Start meetings: held on Thursday mornings from 9:00 a.m., by reservation only, with staff from Engineering, Fire, Natural Gas, Planning, Public Works and Water & Sewer. Since September 2024 a Right Start meeting has been required before any annexation or rezoning, and it stays valid for one year. Send building or site plans and the description of work form in advance. The Senior Planner schedules them (912-212-2392).

Consultation meetings: before applying for a rezoning, variance, special exception, annexation or subdivision, you can meet Planning & Development staff to identify problems and the documents the application will need.

Utilities: the City’s building packet lists Georgia Power and Excelsior Electric Membership Corporation for electric service, and the City’s own Public Utilities Department for natural gas, water and sewer.

Data centers: City Council approved Unified Development Code amendments for technological facilities and data centers on June 2, 2026.

Permit activity: Planning & Development publishes a monthly Building Permit Issuance Report on its Permits & Applications page.

Georgia building code

Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes

Want this handled start to finish?

Get a free quote →

Statesboro permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Statesboro permit FAQs

Who issues building permits in Statesboro?

The City of Statesboro Planning & Development Department issues building, electrical, plumbing and HVAC permits for property inside city limits, and its Building Inspections division inspects the work.

How much is a building permit for a new house in Statesboro?

$0.46 per square foot, plus a plan review fee of 5% of the permit fee and $35 for each inspection. For a 2,000 sq ft house that is $920 plus $46, before inspection and trade permit fees.

Inspections are where schedules slip.

Get a free quote →

How long does plan review take?

The City says each department generally reviews and redlines plans within about 2 weeks, with up to 30 days allowed.

Can someone else pull the permit for my contractor?

Yes. The contractor’s qualifying agent signs a notarised Authorized Permit Agent Form for each permit, naming the person who will apply, and that person brings copies of both licences and photo ID.

Can I pull my own permit as a homeowner?

Only for your primary residence. Submit the Affidavit for Self Contractors with the permit application in CommunityCore.

When will my inspection happen?

Requests made before 4:00 p.m. on a weekday are generally inspected the next business day.

What is the Planning & Development phone number?

912-764-0630. The department email is planning.development@statesboroga.gov.

Simplify Statesboro permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Statesboro sooner?