Municipal Guide Georgia Stonecrest · DeKalb County

Stonecrest Building Permit — Filed & Tracked For You

Everything contractors, builders, and developers need to pull a Stonecrest building permit — the CitizenServe portal, the ten-business-day internal review, the DeKalb County fire marshal routing for life safety, special inspection reporting, and the prosecution warning on the application itself.

Authority: City of Stonecrest Building and Permitting DivisionCode: 2024 Georgia State Minimum Standard CodesSubmission: CitizenServe Permitting Portal
Authority
Building & PermittingCity limits since 2017
Portal
CitizenServeOnline payment only
Review
Ten business daysAfter other agencies approve
Life safety
DeKalb CountyFire is not a city function

Stonecrest building permits come from the Building and Permitting Division, responsible for administering and enforcing the Georgia State minimum standard code and the related permitting and inspection procedures within the city, which incorporated in 2017.

Filing is entirely electronic. Applications and payments are no longer accepted by mail, and payment is accepted online only through CitizenServe, which also carries licensing, planning and zoning, and code enforcement.

Applies inside the Stonecrest city limits. Unincorporated DeKalb County, Lithonia, and neighbouring Rockdale County each permit their own work — and life safety inspections run through the DeKalb County Fire Marshal.

The application carries a criminal warning. Signing acknowledges that a permit may be revoked for misrepresentation of a material fact, and that knowingly false statements subject the applicant to possible prosecution under the Georgia Criminal Code.

What requires a permit in Stonecrest?

Stonecrest incorporated in 2017, one of the last of the DeKalb County new cities. The Building and Permitting Division is responsible for the administration and enforcement of the Georgia State minimum standard code and the related procedures for permitting and inspection of buildings within the city, reviewing plans and inspecting all residential and commercial structures built or remodelled inside it.

Filing is entirely electronic. Applications and payments are no longer accepted by mail, and payment is accepted online only, through the CitizenServe portal that also handles licensing, planning and zoning, code enforcement, and general requests.

Fire is not a city function here, which distinguishes Stonecrest from some of its neighbours. Life safety inspections are scheduled with the DeKalb County Fire Marshal's office, on a routing sheet issued by the city's Planning and Zoning division — so a business occupancy in Stonecrest involves the county as well as the city.

The enforced code is the Georgia State Minimum Standard Codes — the 2024 International Building Code and 2024 International Residential Code with Georgia Amendments, alongside the 2024 International Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code with the 2026 Georgia Amendments. Georgia turned its codes over on January 1, 2026. The Board of Community Affairs, acting on the recommendation of the State Codes Advisory Committee, adopted the 2024 editions of the building, residential, plumbing, mechanical, fuel gas, and swimming pool and spa codes, together with the 2023 National Electrical Code carrying the 2026 Georgia Amendments. A project drawn to the previous editions is drawn to a superseded code, and the Georgia Amendments — not the base I-Code text — are what the plan reviewer reads. Stonecrest also references the National Green Building Standard with Georgia Amendments, one of the state's permissive codes. Georgia splits its codes into mandatory and permissive. The mandatory codes apply to all construction in the state whether or not the local government enforces them — a jurisdiction with no inspection department does not become a jurisdiction with no code. The permissive codes (property maintenance, existing building, and the national green building standard) bind only where a city or county has adopted them. Ask which list your jurisdiction is working from before assuming a requirement does or does not attach.

Permit required

  • Residential and commercial construction and remodelling within the city
  • Electrical, plumbing, and mechanical work
  • Land disturbance, including an initial erosion control inspection where applicable
  • Right-of-way encroachment, on its own permit
  • Special inspections under Chapter 17 of the building code, where design professionals are involved
  • Business occupancy, which requires a life safety inspection through the county
  • Zoning confirmation, obtained at a pre-application meeting

Typically exempt

  • Painting, flooring, and other cosmetic work
  • Ordinary repairs that do not touch structure or a regulated system
  • Work outside the city limits — unincorporated DeKalb, Lithonia, and Conyers all differ
  • Like-for-like replacements that do not alter a regulated system
⚠️ The application carries a criminal warning, not just a civil one. By signing, the applicant acknowledges that a permit may be revoked for false statements or misrepresentation as to a material fact, and that knowingly false statements in the permit application subject the applicant to possible prosecution under the Georgia Criminal Code. Valuation figures and scope descriptions are sworn statements here.

Stonecrest building department: who handles permitting

The city works from 3120 Stonecrest Boulevard, Stonecrest, GA 30038, with every division on 770-224-0200 and hours of 8:30am to 4:30pm Monday to Friday. The Building Department, Planning and Zoning, Business Licensing, and Code Enforcement each have their own email address at the same location.

Review timing is published and conditional. Internal reviews — those done by City staff — take up to ten business days upon approval by other required agencies. That last clause matters: the ten days start after the outside approvals land, not when you upload, so an outstanding agency review does not run concurrently with the city's clock.

Submittals are digital and size-limited: one digital PDF of plans with a 50 MB maximum individual file size. Where design professionals are involved, construction must comply with the special inspection provisions of the building code, and the special inspections listed on the plans cover page are turned in to the city building official.

Stonecrest permitting contact
DetailInformation
AuthorityCity of Stonecrest Building and Permitting Division
ScopeInside the Stonecrest city limits — incorporated 2017
Address3120 Stonecrest Boulevard, Stonecrest, GA 30038
Phone770-224-0200 — all divisions
HoursMonday to Friday, 8:30am to 4:30pm
PortalCitizenServe — permits, licensing, zoning, code enforcement
Internal reviewUp to ten business days after other agencies approve
Life safetyScheduled with the DeKalb County Fire Marshal's office
💻

All inspection requests must be made via the CitizenServe Permitting Portal. That includes the initial erosion control inspection on a land disturbance project, which is scheduled through the portal or by calling the city — but not by emailing an inspector directly.

Stonecrest borders unincorporated DeKalb County, Lithonia, and Rockdale County, and its business licensing interacts with DeKalb County's: existing licence holders can renew online with the city only where the existing licence was issued by Stonecrest rather than by DeKalb County.

Stonecrest permits: record types and what each covers

Stonecrest's records run through one portal but reach two governments, because life safety sits with the county. These are the records you will file:

Residential permit types

Residential permit types in Stonecrest
Permit typeWhat triggers itReview pathFee basis
New constructionNew dwellings, additions, and accessory structures above the local size thresholdFull plan review against the 2024 IRC with Georgia Amendments, plus zoningValuation-based
Renovation / alterationStructural changes, layout changes, or added plumbing, mechanical, or electricalPlan review scaled to scope; existing-building provisions apply only where locally adoptedValuation-based
ReroofRoof covering replacement, recover, and structural deck repairDry-in and deck inspection; plan review rarely requiredValuation or squares
Solar photovoltaicRooftop or ground-mount arrays, with or without battery storageElectrical review led, with structural review of the attachmentFlat or system-size based
Battery energy storageWall or floor-mounted storage added to a dwellingElectrical review plus fire separation and location checkFlat or per-permit minimum
ElectricalService changes, panel upgrades, new circuits, EV chargers, and rewiringTrade review; filed as its own record under a Class I or Class II licencePer-permit minimum or per-device
PlumbingNew piping, repipes, fixtures, gas piping, and water heater replacementTrade review under a Journeyman or Master licencePer-permit minimum or per-fixture
Mechanical / HVACChangeouts, new ductwork, and refrigerationTrade review; conditioned air licence class keyed to system capacityPer-permit minimum or per-unit
Deck and porchNew decks, screened porches, and structural rebuildsFooting and framing review against the residential codeFlat or valuation-based
Pool and spaIn-ground and above-ground pools, spas, barriers, and bondingStructural, barrier, and electrical bonding review under the 2024 ISPSCValuation-based
Accessory structureSheds, detached garages, and carports above the local size thresholdZoning first, then structural review where applicableFlat or valuation-based
DemolitionFull or partial demolition of a structureUtility disconnect verification and asbestos notificationFlat
Land disturbanceClearing, grading, and any disturbance above the local thresholdErosion and sedimentation review on its own statutory clockPer-acre or valuation-based
Initial erosion control inspectionLand disturbance projects where applicableScheduled through CitizenServe or by calling the citySet by the city
Right-of-way encroachment permitWork affecting the public right of wayInstructions published with the permit application packetSet by the city

Commercial permit types

Commercial permit types in Stonecrest
Permit typeWhat triggers itReview pathFee basis
New constructionGround-up commercial, industrial, and multifamily buildingsFull multi-discipline review; sealed plans requiredValuation-based
Tenant build-outInterior fit-ups and suite build-outs in an existing shellConcurrent building, trade, and fire reviewValuation-based
Renovation / alterationStructural, envelope, or system changes to an existing buildingPlan review scaled to scope; accessibility triggers attachValuation-based
Change of occupancyConverting a building from one occupancy classification to anotherLife-safety, accessibility, and zoning reviewValuation or flat
Shell buildingA building permitted without a known tenant or useShell review only; no certificate of occupancy until a build-out closesValuation-based
ReroofCommercial roof covering replacement or recoverStructural check on added dead load; fire review where applicableValuation or squares
Solar photovoltaicCommercial rooftop, carport, and ground-mount arraysStructural, electrical, and fire access reviewValuation or system-size based
ElectricalService, distribution, and branch circuit workTrade review; separate record from the building permitValuation or per-device
PlumbingSupply, waste, vent, grease, and gas systemsTrade review; backflow and grease interceptor sign-offs attachValuation or per-fixture
Mechanical / HVACRooftop units, ductwork, exhaust, and refrigerationTrade review; energy compliance documented against the 2015 IECCValuation or per-unit
Fire protectionSprinkler, standpipe, alarm, hood, and suppression systemsFire review under the state Safety Fire Commissioner's adopted codesValuation or per-device
SignWall, monument, and illuminated signageZoning review plus electrical where illuminatedFlat or per-sign
Land disturbanceSite clearing, grading, and stormwater installationErosion and sedimentation review as a Local Issuing AuthorityPer-acre or valuation-based
Special inspection reportsConstruction involving design professionalsListed on the plans cover page and turned in to the building officialPaid to the inspection agency
Life safety inspectionBusiness occupancyScheduled with the DeKalb County Fire Marshal on a city routing sheetSet by the county

Residential

  • Single-discipline review in most cases
  • Trade records filed separately under Chapter 14 licences regardless of job value
  • State licence required once the work exceeds the statutory threshold, per project
  • A private professional provider may be engaged to shorten the review path

Commercial — multi-discipline

  • Concurrent review across building, trades, fire, and zoning
  • Signed and sealed plans across every affected discipline
  • Land-disturbance review runs on its own statutory clock under Title 12
  • Accessibility and life-safety review attach to any change of occupancy

Records you will actually see in Stonecrest

Stonecrest record catalog
RecordWhat it covers
Residential building permitNew homes and remodelling inside the city
Commercial building permitCommercial construction and tenant work
Trade permits (E/P/M)Filed as their own records under Chapter 14 licences
Land disturbance permitIncluding an initial erosion control inspection where applicable
Right-of-way encroachment permitWhere work affects the public right of way
Special inspection reportsListed on the plans cover page and submitted to the building official
Life safety inspectionRouted to the DeKalb County Fire Marshal on a city-issued routing sheet
Business licenceApplied for through the same portal, with life safety documentation attached

Solar permits in Stonecrest

Solar is filed as its own record across Georgia rather than as a line item on a building permit, and it is reviewed on two tracks at once: the electrical side (conductors, overcurrent protection, rapid shutdown, labelling, and the service or supply-side connection, all against the 2023 National Electrical Code with the 2026 Georgia Amendments) and the structural side (attachment detail, rail spacing, and whether the existing framing carries the added dead load).

Solar in Stonecrest is filed through CitizenServe like every other record, and the inspection is requested there too. Where design professionals are involved, check whether special inspections appear on the plans cover page — those reports go to the city building official as they are completed.

The covenant question comes up on nearly every residential array, and Georgia answers it less generously than several neighbouring states. Georgia's Solar Power Free-Market Financing Act (O.C.G.A. § 44-3-113 and Title 46, Chapter 3, Article 8) makes third-party solar financing lawful and limits a property owners' association's ability to prohibit solar outright, but Georgia gives homeowners materially less protection than North Carolina or Florida do: an association retains real authority over placement and appearance, and a covenant restricting where panels may sit on the roof will usually stand. Read the covenants before designing the array, not after.

Utility interconnection runs on its own clock alongside the permit. Georgia Power and the state's electric membership corporations each set their own application, meter, and witness-test sequence, and permission to operate is not something the building department controls — plan for the two tracks to finish at different times.

Roofing permits in Stonecrest

A roof covering replacement needs a permit across most of Georgia. The permit is usually quick, but it is not optional, and the inspection that matters happens before the covering goes on rather than after.

Because Georgia enforces a statewide minimum code, there is no state product-approval database to search and no approval number to cite on the application. The assembly has to comply with the adopted code and the manufacturer's listed installation instructions, and that pairing is what the inspector checks — which makes the manufacturer's instructions a document worth having on site.

Reroofs in Stonecrest are city permits filed and paid for online; there is no mail route. Plan the submittal as a single digital PDF within the city's individual file size limit rather than a set of separate sheets.

Sequencing is where reroofs go wrong. The deck and dry-in condition has to be visible when the inspector arrives, so covering it first means opening it back up. Where a previous layer has been torn off, expect attention to deck fastening and to any sheathing replaced along the eaves.

Record types, document sets, and fee structures are set by local ordinance and change without notice. Confirm the current catalog against the official portal before you file.

Stonecrest permit cost

Stonecrest takes payment online only. Applications and payments are no longer accepted by mail, so the portal is both the filing route and the checkout. Fees are assessed after the application and supporting documents are uploaded.

The review clock is the thing to plan around rather than the fee. Internal reviews take up to ten business days upon approval by other required agencies — so on a project needing county, state, or utility sign-off, the city's ten days queue behind those rather than running alongside them.

Business occupancy adds a county cost and a county timeline. Life safety inspections are performed by the DeKalb County Fire Marshal's office on a routing sheet the city issues, and the completed inspection document is uploaded with the business licence application.

How Stonecrest fees are structured
Fee componentHow it works
Building permitAssessed after upload; payment accepted online only
By mailApplications and payments are no longer accepted
Internal reviewUp to ten business days after other agencies approve
Plan filesOne digital PDF, 50 MB maximum individual file size
Life safetyPerformed and charged by the DeKalb County Fire Marshal
Special inspectionsArranged by the applicant and reported to the building official
🧮

Want a precise number for a specific Stonecrest project? Send us the scope and we will price the permit path before you file.

Stonecrest trade permits

Stonecrest sequences the trades through one portal and one phone number, with the fire piece handled by the county and the special inspections handled by the applicant.

Everything goes through the portal

All inspection requests must be made via the CitizenServe Permitting Portal, including the initial erosion control inspection on a land disturbance job.

Inspections run in sequence

The application requires the applicant to acknowledge that all required inspections must be performed in an established sequence, and that work done in violation of the codes must be corrected or may be ordered removed.

Special inspections are yours to arrange

Where design professionals are involved, the special inspections shown on the plans cover page are arranged by the applicant and turned in to the city building official.

Fire runs through the county

Life safety inspections are scheduled with the DeKalb County Fire Marshal's office using a routing sheet issued by the city, rather than with a city fire marshal.

🧢 Georgia's contractor licensing threshold is $2,500, which is far lower than most states and catches work people assume is too small to regulate. Under O.C.G.A. § 43-41-2 a state licence is required once the value of the work — or the contractor's compensation, whichever is higher — exceeds that figure, and the test is per project, not per invoice. The State Licensing Board for Residential and General Contractors sits under the Secretary of State and issues four tiers: Residential-Basic (detached one- and two-family homes and townhouses up to three stories); Residential-Light Commercial (adding multifamily and light commercial under four stories and under 25,000 square feet); General Contractor (all building types, no dollar cap); and General Contractor Limited Tier (the same scope capped at $1,000,000 per contract). The consequence of getting this wrong is not just a fine. Under O.C.G.A. § 43-41-17 a contract for work requiring a licence, entered into with a contractor who does not hold one, is unenforceable in law or in equity by that contractor — who also cannot file a mechanic's lien and cannot make a bond claim. An unlicensed contractor on a Georgia job has no collection mechanism at all. The trades are licensed separately under O.C.G.A. Title 43, Chapter 14 through the divisions of the Construction Industry Licensing Board, and those licences are required regardless of project value — the $2,500 floor does not apply to them. Electrical runs Class I (restricted to low-voltage and single-phase installations not exceeding 200 amperes) and Class II (unrestricted). Conditioned air runs Class I (not exceeding 175,000 BTU heating and 60,000 BTU cooling) and Class II (unrestricted). Plumbing runs Journeyman, Master Class I (one- and two-family dwellings and commercial structures not exceeding 10,000 square feet), and Master Class II (unrestricted). Senate Bill 553, enacted as Act 472, repealed and reenacted the whole of Chapter 14 effective July 1, 2026. A year of full-time experience now means 2,000 documented hours, applicants submit sworn affidavits and consent to fingerprint background checks they pay for, and lending, leasing, renting, or assigning a licence to an unlicensed person — or conspiring to evade the chapter — is now expressly a disciplinary offence. Licences renew biennially with a 31-day late window.

Stonecrest permit application: how to apply step by step

Here is how to get a building permit in Stonecrest, from confirming the requirement through to close-out. Each step below corresponds to a real decision point where projects commonly stall.

1. Confirm you are inside Stonecrest

Stonecrest incorporated in 2017 and permits its own work. Unincorporated DeKalb County, Lithonia, and neighbouring Rockdale County all permit separately.

2. Take the pre-application meeting

Planning and Zoning offers a pre-application meeting for zoning and land use confirmation, and issues a life safety inspection routing sheet where the project needs one. Starting there prevents a business occupancy stalling later.

3. Register on CitizenServe

Register on the portal, then apply, view review status, pay fees, and schedule inspections through it. Applications and payments are no longer accepted by mail and payment is online only.

4. Prepare a compliant plan submittal

Submit one digital PDF of plans with a 50 MB maximum individual file size. Where design professionals are involved, comply with the special inspection provisions and make sure the special inspections appear on the plans cover page.

5. Allow for the sequencing of reviews

Internal reviews by City staff take up to ten business days upon approval by other required agencies — so outside approvals come first and the city's clock follows. An application is treated as incomplete until the required material is in.

6. Book inspections in the portal, and fire through the county

All inspection requests go through CitizenServe, including the initial erosion control inspection. Life safety inspections are scheduled with the DeKalb County Fire Marshal's office on the city's routing sheet, and the completed document is uploaded with the business licence application.

Inspections in Stonecrest

Every inspection request in Stonecrest goes through the CitizenServe portal, which also carries review status, fee payment, and permit history. The city publishes an inspection information form and a portal help guide alongside the application packet.

The application binds the applicant to sequence. By signing, you acknowledge that all required inspections must be performed in an established sequence, and that any work done in violation of the codes must be corrected or may be ordered to be removed. That is a stronger formulation than most Georgia cities use, and it sits next to the criminal warning about false statements.

Georgia also lets an applicant bring a private professional provider to the plan review itself. Once the permit application and the provider's affidavit are both in, the building official has 30 days to issue the permit or give written notice identifying the specific plan features that do not comply and the specific code chapters and sections behind each. If that written notice does not arrive inside 30 days, the application is deemed approved as a matter of law and the permit shall be issued. A timely notice tolls the 30 days; when revisions come back, the official has the remainder of the tolled period plus five business days (O.C.G.A. § 8-2-26(g)).

Keep the permit and approved plans on site throughout, and keep the special inspection reports moving to the building official as they are completed. a Georgia building permit generally becomes invalid if work does not begin within 180 days of issuance, or if work is suspended or abandoned for 180 days after commencing, under the administrative provisions of the adopted International Building and Residential Codes — local ordinance may set a different period, and extensions are usually available in writing on request.

Stonecrest permit search and official resources

Stonecrest publishes its permit application packet, portal guides, and division contacts through the city website, with CitizenServe handling every transaction.

Frequently asked questions

Who issues building permits in Stonecrest, GA?

The City of Stonecrest Building and Permitting Division, at 3120 Stonecrest Boulevard. The division administers and enforces the Georgia State minimum standard code and the related permitting and inspection procedures within the city.

Can I apply or pay by mail in Stonecrest?

No. Applications and payments are no longer accepted by mail, and payment is accepted online only through the CitizenServe portal.

How long does review take in Stonecrest?

Internal reviews — those done by City staff — take up to ten business days upon approval by other required agencies. The city's clock therefore starts after outside approvals rather than alongside them.

How do I request an inspection?

All inspection requests must be made via the CitizenServe Permitting Portal. That includes the initial erosion control inspection on a land disturbance project, which can also be arranged by calling the city.

Who does fire and life safety inspections in Stonecrest?

The DeKalb County Fire Marshal's office. The city's Planning and Zoning division issues a routing sheet, and the completed life safety inspection document is uploaded with the business licence application.

What is the plan file size limit?

One digital PDF of plans with a 50 MB maximum individual file size.

What happens if I put wrong information on the application?

The application states that a permit may be revoked for false statements or misrepresentation as to a material fact, and that knowingly false statements in the application subject the applicant to possible prosecution under the Georgia Criminal Code.

Do I need special inspections?

Any construction requiring design professionals must comply with the special inspection provisions of the building code. The special inspections found on the plans cover page are turned in to the city building official.

What are the city's hours?

Monday to Friday, 8:30am to 4:30pm. City Hall, the Building Department, Planning and Zoning, Business Licensing, and Code Enforcement all operate from 3120 Stonecrest Boulevard on 770-224-0200.

Can I renew my business licence with the city?

Existing licence holders can renew online with Stonecrest provided the existing licence was issued by the City of Stonecrest rather than by DeKalb County.

Does Stonecrest enforce the green building standard?

The city references the National Green Building Standard with Georgia Amendments. That is one of Georgia's permissive codes, meaning it binds where a local government has adopted it rather than automatically statewide.

When is a Georgia contractor licence required?

Once the value of the work, or the contractor's compensation, exceeds two thousand five hundred dollars, tested per project rather than per invoice. Trade licences under Title 43, Chapter 14 are required regardless of job value.

Simplify Stonecrest permitting with Alliance Permitting

Stonecrest is fully digital, clearly documented, and split across two governments at exactly the point where a business occupancy needs to move: the city permits the building, the county inspects the life safety. Add a review clock that only starts once other agencies have approved, and sequencing is everything. A permit expediter for Stonecrest keeps both tracks moving so the ten-day clock actually starts.

250K+Permits approved
All 50States covered
21 YearsJurisdictional depth
Done-for-youWe file, you build

Trusted by leading builders, developers, and national contractors — 21 years of filing in the jurisdictions we write about.

Contractors and builders choose Alliance for Stonecrest because the work is done by people who have stood at the counter:

  • Outside approvals first — because the city's ten business days begin only once other required agencies have approved.
  • Fire routed early — the county routing sheet obtained at pre-application rather than discovered at business licensing.
  • Complete oversight — every Stonecrest permit, special inspection report, and county sign-off tracked in one place.

Alliance Permitting is a permit documentation and expediting service. We are not a law firm and do not provide legal advice, and we are not the permitting authority.

Ready to break ground in Stonecrest sooner?

Let Alliance prepare, file, and track your Stonecrest permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Stonecrest permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.

Expedite Your Permits Today!

Free Quote1-855-478-4290