Peach County, Georgia Building Permit Guide

In unincorporated Peach County, building and trade permits are issued through the Chief County Marshal’s Office, with plan review and inspections handled for the County by Bureau Veritas. Applications are filed in the County’s MyGov portal or on its published forms.

Authority: Peach County Chief County Marshal’s Office (Bureau Veritas building services)Code: Georgia State Minimum Standard Codes (2024)Phone: 478-825-2799 · 902 Campus Drive, Fort Valley, GA 31030
Authority
Chief County Marshal’s OfficeUnincorporated county; Fort Valley, Byron, Perry and Warner Robins issue their own
Apply
MyGov public portal or County formsBuilding, trade, fence, pool, sign, demolition and manufactured home permits
Inspections
706-768-0751 or inspectionsga@bureauveritas.comGiven within 48 hours of the request
Re-inspection
$85Charged when work is not ready or the site is locked

For property in unincorporated Peach County, building, electrical, plumbing and HVAC permits come from the Chief County Marshal’s Office at 902 Campus Drive, Fort Valley (478-825-2799), and Bureau Veritas carries out plan review and inspections for the County. Inspections are given within 48 hours of a request, and an inspection that is not ready costs $85 to repeat.

What requires a building permit in Peach County?

The County’s MyGov portal and its document library list these permits for the unincorporated county:

Residential

  • New homes
  • Additions
  • Accessory buildings
  • Electrical, mechanical/HVAC and plumbing work
  • Fences
  • Pools
  • Demolition
  • Manufactured homes, including pre-owned homes moved into the county

Commercial

  • New commercial buildings
  • Commercial electrical, mechanical and plumbing work
  • Fences and pools
  • Signs
  • Demolition

Variances, special exceptions and minor plat reviews are also applied for in the portal. Under the County’s land development resolution, the zoning compliance permit for a project can be issued as part of the building permit.

Who handles permitting in Peach County?

The Chief County Marshal’s Office, led by Chief Marshal Todd Shepherd, runs zoning, subdivision, development regulation and building permits for the unincorporated county. Building services are provided through Bureau Veritas: the portal lists Emory Yarbrough of Bureau Veritas as Building Official/Inspector, and Bureau Veritas staff also handle plats and zoning administration.

ItemPeach County
OfficeChief County Marshal’s Office, 902 Campus Drive, Fort Valley, GA 31030
Phone478-825-2799
Building OfficialEmory Yarbrough (Bureau Veritas)
Inspection requests706-768-0751 or inspectionsga@bureauveritas.com
ApplyMyGov public portal or the forms on the Marshal’s Office Documents page

Short on time to read all of this?

Get a free quote →

The City of Fort Valley and the City of Byron each publish their own building and trade permit applications, so property inside either city’s limits is permitted by that city.

Perry and Warner Robins lie mainly in Houston County, with small parts in Peach County. The Peach County Service Delivery Strategy (amended December 2007) records that each city runs its own code enforcement and inspection services. Perry’s permits come from its Community Development department, 741 Main Street, Perry (permit technician 478-988-2726); Warner Robins’ come from the City’s Building Inspection Department, 610B Watson Boulevard (478-302-5508 or 478-302-5507).

Peach County permit applications and online filing

The MyGov public portal sorts applications into residential building, commercial building, planning and zoning and other permits, and also handles contractor credentials for general contractors, electrical, plumbing and pool work. The same applications are posted as PDF forms on the Marshal’s Office Documents page:

  • New Single Family Residential Building Permit Application, with a checklist that must be returned with the submittal
  • Residential Addition and Residential Accessory Building applications
  • Commercial Building Permit Application and the Commercial and Industrial Plan Submittals procedures
  • Electrical, Plumbing and HVAC/Fuel Gas permit applications
  • Demolition, Fence, Sign and Manufactured Home applications
  • Homeowner Affidavit, notarised and given to the Building Official before a permit is issued to an owner acting as their own contractor

Permit costs and fees in Peach County

The County’s application forms work out a project valuation from heated and unheated square footage multiplied by a valuation multiplier, and the total is made up of an administrative fee, the building permit fee, a plan review fee and a Certificate of Occupancy fee. The portal has an Estimate Fees tool.

  • Re-inspection: $85 when the work is not ready, or the site is locked or inaccessible, when the inspector arrives.
  • Pre-owned manufactured home: a refundable $150 guarantee-of-condition bond or cash deposit, plus a permit and inspection fee based on the home’s assessed value that covers the first inspection and one follow-up.

All fees and unpaid re-inspection fees must be paid before the final inspection for the Certificate of Occupancy.

Not sure this scope needs a permit?

Get a free quote →

Electrical, plumbing and HVAC permits in Peach County

Electrical, mechanical/HVAC and plumbing permits are separate residential and commercial applications in the MyGov portal, with matching PDF forms for electrical, plumbing and HVAC/fuel gas work. The new-home application names the general, plumbing, electrical and HVAC/gas contractors with their Georgia licence numbers, and the checklist asks for each subcontractor’s state licence card, business licence and driver’s licence. A manufactured home permit needs a completed electrical subcontractor permit, with plumbing and HVAC permits added where they apply.

For commercial buildings, stamped and sealed sprinkler plans (3 sets) are submitted when a fire suppression system is required, and Title 25 occupancies send construction documents to the State Fire Marshal’s office.

Application documents

New home

  • Completed building permit application and checklist
  • Contractor and subcontractor licensing documentation
  • GSWCC Level 1A certification (Blue Card)
  • 2 sets of scaled drawings: foundation plan and detail, floor plan of each level, elevations and wall details, plus one 8½ x 11 in copy
  • House location plan showing setbacks and erosion and sediment control
  • GSWCC-approved erosion control plans for secondary and tertiary permit holders
  • Verification of 911 addressing
  • Septic permit or water/sewer application, as applicable
  • Recorded deed and recorded plat

Commercial

  • Building and trade applications with a detailed description of work
  • 6 paper sets of plans on bound ARCH D (24 x 36 in) sheets, plus 1 digital set
  • Architect or engineer seal and handwritten signature for assembly, educational, institutional and multi-family buildings and single-storey buildings over 5,000 sq ft
  • Cover sheet with occupancy group, occupant load, construction type, sprinkler status, height and areas
  • Sheets marked “For Construction”

After commercial plans are reviewed, the application approved and the fees paid, the Building Inspector holds a pre-construction meeting with the contractor, returns 2 sets of plans and issues the permit. Work may not start before then.

Rather talk it over?

Call 1-855-478-4290 →

Fence permits need a site plan showing property lines, existing structures and the fence and gates. Demolition applications ask where debris will go, whether asbestos or mold mitigation is needed and whether the work is within 200 ft of state waters.

How to apply: 6-step Peach County process

1. Check the address

Make sure the parcel is in unincorporated Peach County and not inside Fort Valley or Byron, which permit their own projects.

2. Pick the application

Choose the residential, commercial, trade, fence, pool, sign, demolition or manufactured home application in MyGov, or download the PDF from the Marshal’s Office Documents page.

3. Assemble the checklist

Attach licences, drawings, the house location plan, 911 address verification, septic or sewer approval and the recorded deed and plat. Owner-builders add a notarised Homeowner Affidavit.

4. Pay and collect the permit

Pay the administrative, permit, plan review and CO fees. Commercial permits are handed over at a pre-construction meeting.

5. Set up the site and post the permit

Install the construction exit, erosion control and toilet, mark the lot lines and post the permit in a weatherproof box at the street.

6. Call for inspections

Request each inspection at 706-768-0751 or by email when the work is 100% ready, through to the final and Certificate of Occupancy.

Peach County inspections

Request inspections from the office at 706-768-0751 or inspectionsga@bureauveritas.com; inspectors in the field do not take requests. Give the permit number, inspection type, jobsite address and the contractor’s name and number. Inspections are given within 48 hours of the request, at the inspector’s discretion.

Rather not deal with the Peach County building department?

Get a free quote →

Before the first inspection the site needs a 50 x 20 ft construction exit of geotextile mat and gravel, erosion control, a toilet for workers and the front and side lot lines marked with string and stakes. Inspectors do not handle keys or lock combinations, and a locked or inaccessible site fails.

A new home is inspected at these stages:

  • Foundation: footings at least 12 inches below undisturbed grade, with setbacks checked
  • Foundation wall steel for basement and retaining walls over 4 ft
  • Under-slab plumbing and slab cover
  • Framing/sheathing rough once the house is dried in
  • Moisture barrier and MEP rough, which can be called in together
  • Insulation, before drywall is stocked
  • Temporary power, which releases the meter for up to 30 days of testing
  • Final, including landscaping, site stabilization and drainage

No home may be lived in before the Certificate of Occupancy, and the County does not issue temporary occupancy for single-family or multi-family dwellings.

Local Peach County details that matter

Pre-owned manufactured homes: a permit is required to bring one into the unincorporated county. The owner provides a signed affidavit that the home meets the County’s health and safety standards, interior and exterior photographs, the $150 bond or deposit and the fee; the County issues the permit within 30 days of receiving everything, and the home must comply with the HUD Code before it gets a Certificate of Occupancy.

Owner-builders: the County’s Homeowner Affidavit is for owners building for their own use or occupancy who have not sold a building they contracted within the previous 24 months. The owner is responsible for requesting inspections and being on site for them.

Planning and zoning: variance and special exception requests are filed in MyGov, and the County has up to 5 working days to check an application is complete before it is placed on an agenda.

Georgia building code

Georgia's State Minimum Standard Codes apply statewide: the 2024 International Building, Residential, Plumbing, Mechanical, Fuel Gas, and Swimming Pool and Spa Codes and the 2023 National Electrical Code, with Georgia Amendments, in force since 1 January 2026; the energy code is still the 2015 IECC with Georgia supplements. The Georgia State Minimum Standard Codes

Want this handled start to finish?

Get a free quote →

Peach County permit search and official resources

These are the primary sources behind this guide. Codes, fee schedules and procedures change — confirm the position for your filing date.

Inspections are where schedules slip.

Get a free quote →

Peach County permit FAQs

Who issues building permits in Peach County?

The Chief County Marshal’s Office issues permits for the unincorporated county, with Bureau Veritas providing the Building Official, plan review and inspections. Fort Valley, Byron, Perry and Warner Robins handle permits inside their city limits.

How do I apply for a permit in Peach County?

Apply in the County’s MyGov public portal or on the PDF applications posted on the Marshal’s Office Documents page, with the checklist documents attached.

How do I schedule an inspection?

Call 706-768-0751 or email inspectionsga@bureauveritas.com with the permit number, inspection type, address and contractor contact. Inspections are given within 48 hours.

What does a failed inspection cost?

If the work is not ready or the site is locked when the inspector arrives, the inspection fails and an $85 re-inspection fee is charged.

Can a homeowner pull a permit?

Yes, for a building for your own use or occupancy, if you have not sold a building you contracted in the last 24 months. Submit the notarised Homeowner Affidavit before the permit is issued.

Do I need a permit for a fence or pool in Peach County?

Yes. Residential and commercial fence and pool permits are separate applications in the portal, and a fence application needs a site plan.

Can I move into a new house before the final inspection?

No. The County does not issue temporary occupancy for homes, so the final inspection and Certificate of Occupancy must come first.

Simplify Peach County permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in Georgia. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Peach County sooner?

Let Alliance prepare, file, and track your Peach County permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Peach County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.