The City of Fort Lupton Building Department issues building and electrical permits for all construction in the city and accepts applications only through CommunityCore; SAFEbuilt reviews the plans and performs the inspections. A fee schedule adopted by Resolution No. 2026R020 took effect May 1, 2026: one-stop permits such as a re-roof, furnace or residential fence cost $150, and plan review is 65% of the permit fee, paid up front.
What requires a building permit in Fort Lupton?
The City publishes its own lists and says they are not all-inclusive, so contact the Building Department before starting anything that is not named.
Permit required
- Additions, accessory dwelling units, interior remodels and tenant finishes
- Basement finishes
- Garages and carports (fabric canopies are not permitted)
- Decks, patios, balconies, enclosed patios and covered porches of any height
- Concrete flat work inside the property lines, including a concrete patio
- New fences, and replacement of more than 50% of a fence
- Sheds, pergolas and gazebos over 200 sq ft
- Roofing, siding and stucco
- Windows and doors that are not like for like
- Air conditioners, furnaces, water heaters, fireplaces and pellet stoves
- Minor electrical repairs
- Radon mitigation systems, swimming pools and hot tubs
- Retaining walls over 4 ft tall
- Steps and ramps, awnings, signs and construction trailers
- Demolition of a structure on footings
No building permit
- Fence repair or replacement of less than 50% of an existing fence
- Repairing or replacing less than 1 square (100 sq ft) of shingles
- One-story detached tool sheds, storage sheds and playhouses of no more than 200 sq ft
- Landscaping (keep the sight triangle clear) and sprinkler repairs
- Demolition of a structure that is not on footings
Emergency equipment replacements and repairs may go ahead, but the permit application has to reach the Building Official on the next business day. The fee schedule sets the violation fee for unpermitted work at 2 times the permit fee.
Who issues building permits in Fort Lupton?
The Building Department, part of Planning and Building, issues the permits and enforces the codes. Fort Lupton partners with SAFEbuilt for plan review and building inspections, and the permit remains a City permit. Jose Gonzalez is listed as the Building Official.
| Detail | Information |
|---|---|
| Office | 1200 Dexter Street, Unit W13, Fort Lupton, CO 80621 |
| Mailing address | 130 S McKinley Ave, Fort Lupton, CO 80621 |
| Phone | 720-928-4003 |
| SAFEbuilt (submittal and inspection questions) | 970-305-3161 |
| Applications, licences and inspection requests | CommunityCore |
Short on time to read all of this?
Get a free quote →Office move pending: Fort Lupton’s new City Hall at 9th Street and College Avenue received its Certificate of Occupancy in the week of October 5, 2026; staff move in over the following weeks and the grand opening is October 29, 2026. The Planning and Building listing still shows the Dexter Street office, so phone 720-928-4003 before a visit in person.
The City suggests checking its zoning map before applying, to be sure the property is in Fort Lupton’s jurisdiction; land outside the city limits in unincorporated Weld County is the county’s. Commercial and industrial permits are not issued without approval from both City staff and the Fort Lupton Fire Department (303-857-4603), and fire suppression permits are filed with the Fire Department separately. Driveway, sidewalk and right-of-way permits come from Public Works.
Fort Lupton permit types, CommunityCore and licences
Applications are accepted only in CommunityCore. Register as a contractor or as a community member, follow the emailed link, then create the permit, upload every document and press submit. Staff cannot see an application until it has been submitted. A kiosk is available in the office for people without a computer, and paper applications are provided on request, though the permit is still processed in CommunityCore and needs a valid email address.
- Contractor licences: General Contractor $150, Building Contractor $75, Mechanical Contractor $75, Plumbing Contractor $75 (state certification required), Electrical Contractor no annual fee (state certification required), Tree Trimmer or Landscaper $5. Apply and renew in CommunityCore and pay for each licence type. The City asks for a current ICC exam or a current licence from another municipality, plus general liability and workers’ compensation certificates naming the City of Fort Lupton, 130 S McKinley Ave, as certificate holder.
- No licence, no permit: an expired licence blocks new applications, and a business name that does not appear in the portal is not licensed by the City.
- Extensions: a permit is good for 180 days and each inspection extends the end date. One extension is allowed, applied for before the expiry date.
- Revisions: an amendment to an issued permit costs a flat $85 per submittal and has to be filed before the permit expires.
- Master plans: production builders file under the Master Plan permit type; a repeat master plan review is $500.
Permits are not transferable. To cancel one, write to the Building Department; refunds are requested within 30 days of payment.
Fort Lupton building permit fees
City Council passed Resolution No. 2026R020 on March 17, 2026, and its Building Permit Fee Schedule has applied since May 1, 2026. The permit fee is read from total valuation.
| Total valuation | Permit fee |
|---|---|
| $1 to $500 | $24 |
| $501 to $2,000 | $24 for the first $500 plus $3 for each additional $100 or fraction |
| $2,001 to $40,000 | $69 for the first $2,000 plus $11 for each additional $1,000 or fraction |
| $40,001 to $100,000 | $487 for the first $40,000 plus $9 for each additional $1,000 or fraction |
| $100,001 to $500,000 | $1,027 for the first $100,000 plus $7 for each additional $1,000 or fraction |
| $500,001 to $1,000,000 | $3,827 for the first $500,000 plus $5 for each additional $1,000 or fraction |
| $1,000,001 to $5,000,000 | $6,327 for the first $1,000,000 plus $3 for each additional $1,000 or fraction |
| $5,000,001 and over | $18,327 for the first $5,000,000 plus $1 for each additional $1,000 or fraction |
Not sure this scope needs a permit?
Get a free quote →Valuation. For work under the residential code, the City compares the labor and material cost you provide with its own per-square-foot values and uses the greater: $160 for above-grade floors, $55 for a garage, $50 for unfinished foundation area, $90 for foundation with finished basement, $45 for a basement finish, $35 for a deck, $65 for a covered deck, $70 for a covered porch, $50 for a covered patio or carport, $25 for a crawlspace and $10 for patio or flat work. These values set the valuation; they are not the fee. Use tax is calculated on 50% of the valuation or on the stated material cost, whichever is greater.
Plan review. The plan review fee is 65% of the building permit fee for residential, non-residential and manufactured home projects, and since May 1, 2026 it is collected up front and is non-refundable once review has begun. For example, a 300 sq ft deck valued at $10,500 has a permit fee of $69 plus 9 × $11, which is $168, and a plan review fee of $109.20.
| Item | Fee |
|---|---|
| Residential A/C, furnace or water heater replacement | $150 each |
| Residential re-roof | $150 |
| Residential gas meter or gas test | $150 |
| Demolition | $150 |
| Fence | $150 residential, $500 commercial |
| Flat work | $150 residential, $500 commercial |
| Solar | $500 residential; $1,000 commercial under 2 MW |
| Re-inspection | $110 per inspection |
| Additional plan review | $110 per hour |
| Inspections outside normal hours | $250 per hour |
| Temporary Certificate of Occupancy | $600 |
| Temporary construction trailer | $500 |
Rather talk it over?
Call 1-855-478-4290 →Pay online in CommunityCore, in person or by phone. Card payments carry a 3.95% processing fee and e-checks a $1 fee; cash, check and money order payments made after 3:30 pm post the next business day. New development also pays water and sewer investment fees, Colorado-Big Thompson water dedication, Fort Lupton Fire Protection District impact fees and Weld RE-8 School District fees, each under its own adopted schedule.
Electrical, plumbing and mechanical permits in Fort Lupton
Electrical permits are City permits with their own table in the fee schedule, and electrical and plumbing contractors need state certification to hold a City licence. Mechanical and plumbing replacements such as a furnace or water heater are one-stop permits at $150.
| Work | Fee |
|---|---|
| New living space, 1,000 sq ft or less | $200 |
| New living space, 1,001 to 1,500 sq ft | $250 |
| New living space, over 1,500 and up to 2,000 sq ft | $300 |
| New living space, over 2,000 sq ft | $300 plus $15 per 100 sq ft or fraction over 2,000 |
| All other electrical, valuation of $2,000 or less | $200 |
| All other electrical, valuation over $2,000 | $300 plus $15 for each additional $1,000 |
| Permanent or temporary electrical meter inspection | $110 each |
| Electrical plan review | 65% of the electrical permit fee |
Utility releases are split: the City releases gas service to Xcel, and SAFEbuilt releases temporary, permanent and solar power to United Power. Fire Department plan reviews run on a separate system from CommunityCore.
Application documents and review times
Review times run from a complete submittal: 24 to 48 hours for over-the-counter and one-stop permits, 7 to 10 business days for residential building plans and 20 days for commercial plans. A Certificate of Occupancy is released in 48 to 72 hours.
New single-family home
- Proof of ownership, such as the recorded deed
- Agent affidavit if the applicant is not the owner
- Plot plan with distances to each lot line, utilities, driveway and north arrow
- Site grading plan matching the subdivision’s development plan
- Architectural plans: wall sections, floor plan, truss and joist layouts, insulation R-values and window U-values
- Engineered foundation and structural drawings that reference the soils report
- Energy code compliance documents (prescriptive, REScheck, ERI or HERS)
- Manual J, S and D
- Soils report for the lot
Commercial or industrial
- Cover sheet naming the architects and engineers and listing the design criteria
- Site plan with property lines, easements, utilities, parking, drainage and a topographical survey
- Geotechnical report
- Exterior elevations, foundation plan and floor plans
- Drawings, specifications and calculations coordinated by the registered architect or engineer
- Fort Lupton Fire Department approval
Rather not deal with the building department?
Get a free quote →Before any new development, the owner submits the Pre-Application Review Questionnaire and attends a pre-application meeting on land use requirements. Smaller projects need a simple site plan, typically at 1 inch to 20 ft, showing property lines, existing and proposed footprints, distances to lot lines and other structures, driveways and easements. On a new home, an open hole letter is required before the foundation is poured, and an Improvement Location Certificate and the engineer’s grading certificate before the Certificate of Occupancy.
How to apply: 7 steps in Fort Lupton
Confirm the address is inside Fort Lupton, and book the pre-application meeting if the project is new development.
Contractors license first; residents register as community members.
Upload all required documents and press submit so staff can see the application.
A separate invoice is emailed once the fee is calculated, and it must be paid before review is completed.
Online, in person or over the phone.
The permit, inspection card and all stamped documents stay on site for the whole project.
Request each inspection on the permit card in CommunityCore until the permit is finaled.
Fort Lupton inspections
Every building inspection is requested online in CommunityCore. A request made before 4:00 PM is carried out the following business day, typically between 7:00 am and 5:00 pm, and inspections that need access to the inside of a house can be given a 2 hour window. Public Works inspections are booked by email with that department.
- Approved plans and the permit must be on the job site, and the applicant provides access.
- Set and secure ladders whenever one is needed.
- Remote video inspections are offered for re-roofing projects, for residents and contractors alike.
- SAFEbuilt holidays do not count as business days; request by 4:00 PM on the business day before a closure to be inspected on the first business day after it.
- A missed appointment can be charged for the inspector’s time, and a re-inspection costs $110.
Want this handled start to finish?
Get a free quote →New homes need the City’s Energy Compliance Certificate, with duct and building envelope leak test reports, ready for the inspector at the final inspection and before the Certificate of Occupancy. The permit or property owner is responsible for requesting every inspection on the permit card; leaving a permit unfinaled can bring a violation or citation.
Local Fort Lupton details that matter
2024 codes: Fort Lupton moved from the 2018 to the 2024 International Codes, with the 2023 National Electrical Code, effective March 28, 2026. Master plans approved under the old code have until March 28, 2027; a building permit not approved by that date needs a revised master plan set. The City’s codes page marks the 2023 NEC “State Mandated”: Municipal Code Section 18-71, as published, makes the City’s edition the one the State Electrical Board has adopted and begins enforcing a new edition 1 year after the State adopts it. The Board adopted the 2026 NEC in May 2026 and has applied it to State permits since August 1, 2026, so the 2023 edition remains the City’s until that year has passed.
Frost depth: 30 inches below grade.
Fences and small structures: gazebos and pergolas on a concrete pad must keep a 5 ft setback from rear and side property lines. A shed over 200 sq ft, a garage or a commercial fence may need an Improved Land Certificate.
Water: the City’s supply comes from the Colorado-Big Thompson project, and every new construction project must dedicate water shares or pay the dedication cost in addition to the other fees. The price follows the market and can change without notice.
HOAs and metro districts: the City does not enforce covenants or district rules, and it recommends checking with them before pulling a permit.
Permit records: building permits can no longer be viewed by the public directly; copies go through a public records request to the City Clerk.
Colorado building code
Colorado has no statewide building code for private buildings: each city and county decides whether a code applies and which edition, while the state sets electrical and plumbing rules, a minimum energy code on any update, and a wildfire code for the mapped wildland-urban interface. Building codes in Colorado
Inspections are where schedules slip.
Get a free quote →Official Fort Lupton permit resources
- City of Fort Lupton Building Department
- Fort Lupton Permit Information (CommunityCore steps, permit lists, time frames)
- Fort Lupton building permit application form
- Fort Lupton Payment & Fee Information
- Fort Lupton Building Permit Fee Schedule, Resolution No. 2026R020
- Fort Lupton Inspections & Plan Review
- Fort Lupton current adopted codes
- Fort Lupton New Construction Requirements
- Fort Lupton Contractor Licensing Information
- Fort Lupton ICC building guides and handouts
- Fort Lupton Building Q & A
Fort Lupton building permit FAQs
Who issues building permits in Fort Lupton?
The City of Fort Lupton Building Department at 1200 Dexter Street, Unit W13 (720-928-4003). SAFEbuilt reviews plans and inspects for the City.
How much is a building permit in Fort Lupton?
One-stop permits such as a re-roof, furnace, water heater or residential fence are $150. Other permits follow the valuation table: a $10,500 project pays $168, plus 65% for plan review.
Do I need a permit for a fence in Fort Lupton?
Yes for a new fence or when replacing more than 50% of an existing one. Replacing less than 50% needs no permit.
Do I need a permit for a shed in Fort Lupton?
Only if it is more than 200 sq ft; larger sheds are treated as accessory buildings.
How long does plan review take in Fort Lupton?
From a complete submittal, 24 to 48 hours for one-stop permits, 7 to 10 business days for residential plans and 20 days for commercial plans.
How do I schedule an inspection in Fort Lupton?
In CommunityCore. Requests made before 4:00 PM are inspected the next business day.
How long is a Fort Lupton permit valid?
For 180 days, extended each time an inspection is called in. A permit is voided if work has not started within 180 days of issuance.
Simplify Fort Lupton permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in Colorado. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Fort Lupton sooner?
Let Alliance prepare, file, and track your Fort Lupton permits while your crew stays on the job.
More Colorado permitting guides
This guide is provided by Alliance Permitting for general information about Fort Lupton permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.