Building permits in the City of West Sacramento come from the Building & Permitting Division of the Community Development Department, 1110 West Capitol Avenue, 2nd floor ((916) 617-4645, option 1). Plans go in electronically by email, through the Citizen Access portal or on a flash drive at the counter, and simple jobs such as water heaters, re-roofs and panel changes are over-the-counter permits. The building fee schedule effective November 1, 2025 sets fixed fees for common work ($368 for a re-roof) and floor-area fees for new homes and additions, with plan review at 65% of the building fee.
What requires a building permit in West Sacramento?
The Building & Permitting Division publishes a list of common projects that need a permit and a shorter list that does not. If you are unsure, the division makes the call (916-617-4683), and the Planning Division should be asked before any significant spending because not every project is allowed in every zone.
Permit required
- New homes, commercial buildings and accessory buildings; additions and alterations; moving or demolishing a building
- Occupying an existing commercial building for a new commercial use
- Fences over 7 feet; masonry fences and walls over 4 feet
- Patio covers, open or enclosed; decks more than 30 inches above grade, attached to the home or over 200 square feet
- Re-roofs, siding, pools and hot tubs, garage conversions and signs (signs also need Planning)
- Water heaters and softeners, furnace or air conditioner replacement and any electrical, heating or plumbing alteration; kitchen and bathroom alterations
No building permit
- A single-story detached tool or storage shed, playhouse or similar building with no more than 120 square feet of roof area
- Retaining walls up to 4 feet, measured from the bottom of the footing
- New flooring, carpet, tile or wood floors
- Painting, papering and similar finish work
Exempt projects still have to meet the Planning Division’s setbacks. Work done without a required permit is treated as illegal construction with no statute of limitations: a change of ownership does not legalize it, and bringing it into compliance means meeting the current codes, whenever the work was done.
What West Sacramento decides and what the state holds
The city sets its fee schedule, impact fees, zoning and setback rules, and its tree, recycling and engineering requirements; the City Council approved the current user fees for Building, Planning, Development Engineering and Fire Prevention. The 2025 California building codes have applied since January 1, 2026, and contractors are licensed by the state.
West Sacramento building department: who handles permitting
The city’s Building & Permitting Division, part of the Community Development Department, reviews building permit applications for compliance with state and local codes (structural, electrical, mechanical, plumbing and energy) and inspects all building work in West Sacramento. Roxanna Recinos-Serna is the Chief Building Official. Fire permits, inspections and engineering permits are handled by the city’s Fire Prevention and Development Engineering staff on separate applications.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building & Permitting Division | Community Development Department, 1110 West Capitol Avenue, 2nd floor, West Sacramento, CA 95691 |
| Phone and email | (916) 617-4645, option 1; buildingpermits@cityofwestsacramento.org |
| Office hours | 8 a.m. to 5 p.m., Monday to Friday; phones closed noon to 1 p.m. |
| Walk-in counter | Monday to Friday, 9 a.m. to noon and 1 to 4 p.m., first come; appointments by email otherwise |
| Building inspections | (916) 617-4691; bldginsp@cityofwestsacramento.org |
| Commercial fire inspections | (916) 617-4600; CRRDinspections@cityofwestsacramento.org |
| Engineering inspections | (916) 617-4692 |
The counter handles permit questions, in-person payments and over-the-counter applications. For a longer conversation, email the division and ask for a virtual counter meeting: a permit technician sends a Microsoft Teams link for a time during business hours.
West Sacramento permit types
The Citizen Access portal (ACA) takes over-the-counter permits, which usually need no or only basic plan review: dry rot repair without framing work; electrical panel changes, rewiring, home EV chargers and batteries without trenching; HVAC, heat pump and mini-split installs or change-outs; water, sewer, drain and gas line work; in-kind kitchen and bathroom remodels and window change-outs; re-roofs; stucco replacement; and water heaters.
Residential permits
- New homes, additions and ADUs: single-family homes, duplexes, ADUs and JADUs (including garages, patio covers and porches) are priced by floor area, plus 65% plan review, a percentage for each trade and energy compliance fees.
- Solar: apply 24/7 through SolarAPP+ in ACA (permit type Residential General), through ACA with plans, or by email; with plans, plan check takes about 10 to 15 business days. The fee is $450 per dwelling up to 15 kW, plus $15 for each kW above.
- Fixed-fee jobs: re-roofs, demolition, dry rot, an in-kind kitchen remodel and lath-and-plaster stucco are $368 each; a kitchen with bathrooms $520; one to five retrofit windows $215 (six or more $291); an inground pool or spa $891.
- Pre-manufactured homes and tiny homes on wheels: $1,739 per pre-manufactured dwelling; tiny home on wheels fees are calculated at intake.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
New multi-family, commercial and industrial buildings, additions and tenant improvements are priced by valuation, with plan review at 65%, energy compliance plan review of $775 (multi-family) or $465 (commercial), $608 energy inspections and an $873 fire life safety review. Tenant improvement applications need the city’s tenant improvement notice, and commercial projects can ask for a temporary certificate of occupancy before full completion. Since July 26, 2023 the Yolo-Solano Air Quality Management District must clear commercial re-roof overlays, so bring the completed air quality survey or pre-approval when you apply.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning: zoning and setback questions go to the Planning Division; planning plan review on a residential permit is $116 for an addition or remodel and $174 for a new single-family home.
- Development Engineering: grading, onsite, connection and encroachment permits are separate applications and fees, and each needs a pre-site inspection before building inspections begin.
- Yolo County Environmental Health: projects that need its approval file the Environmental Health Land Use Survey with the building application.
- Trees: a tree disclosure form goes with any application where trees are present.
- Air district: projects that need Yolo-Solano AQMD approval file its questionnaire.
- School fees: Washington Unified School District charges $5.17 per square foot for residential and $0.84 for commercial or industrial space, effective August 26, 2024.
West Sacramento building permit fees
Building fees come from the Building Permit Fee Schedule effective November 1, 2025, part of the user fee update the City Council approved for Building, Planning, Development Engineering, Code Enforcement, Sustainability and Fire Prevention; the posted copy was last revised on July 24, 2026. Development impact fees and fees collected for other agencies, such as the school district and Yolo County, were not part of that update. New homes, duplexes, ADUs and additions are priced by floor area:
| Floor area | Building/inspection fee |
|---|---|
| Up to 500 sq ft | $215.90 base; $268.93 per 100 sq ft above 250 |
| 501–1,000 sq ft | $888.21 base plus $225.75 per 100 sq ft above 500 |
| 1,001–2,000 sq ft | $2,016.94 base plus $30.43 per 100 sq ft above 1,000 |
| 2,001–3,000 sq ft | $2,321.22 base plus $97.66 per 100 sq ft above 2,000 |
| Over 3,000 sq ft | $3,297.81 base plus $48.83 per 100 sq ft above 3,000 |
Rather talk it over?
Call 1-855-478-4290 →On top of the building/inspection fee come plan review at 65% (three review cycles included, then hourly), mechanical, electrical and plumbing at 10%, 20% or 30% of the building fee for one, two or three trades, energy compliance plan review ($310) and inspection ($152), and set review fees: construction and demolition recycling $133, engineering $85, fire life safety $218 and planning $116 to $174. A General Plan maintenance fee of 13% and a technology fee of 12% are added, along with the state’s seismic (SMIP) and Building Standards fees. The 65% plan review fee is paid in full once the application is deemed complete.
The city’s worked example: a 750-square-foot single-family addition is $888.21 plus 2.5 × $225.75 ($564.38), a $1,452.59 building fee. Plan check at 65% is $944.18, three trades at 30% are $435.78 and energy compliance is $462, for $3,294.55. That example leaves out the percentage add-ons, review fees, state fees and agency fees, which are charged where they apply.
| Item | Fee |
|---|---|
| A/C, furnace or gas water heater replacement | $215 |
| Electric or heat pump water heater or other equipment change | $293 |
| Miscellaneous electrical or plumbing / mechanical | $368 / $215 |
| EV charging station / energy storage system / generator | $293 / $445 / $445 |
| Fence over 7 ft / concrete or masonry fence over 7 ft | $445 / $597 |
| Re-inspection or additional inspection | $152 |
| Inspection outside business hours, weekday (2-hour minimum) / weekend | $608 / $1,216 |
| Expedited “Fast Track” plan review | 140% of the building/inspection fee |
| Additional plan review, per hour | $155 |
| Permit extension / building research / pre-application fee estimate | $63 each |
| Work without a permit | 100% of the building permit fee |
| Temporary certificate of occupancy, building / fire | $591 / $582 |
Alterations, remodels, repairs and detached accessory structures not listed as fixed fees use a separate valuation table that starts at $177.86 for work up to $2,000, and valuations must come from a contractor’s signed, itemized bid or contract, subject to the Chief Building Official’s approval. Since April 15, 2026 an interim City Council program scales impact fees down for tiny homes on wheels used as primary residences and allows payment over time.
Rather not deal with the building department?
Get a free quote →Trade permits and who may pull them in West Sacramento
The Building & Permitting Division issues electrical, mechanical and plumbing permits, either as stand-alone fixed-fee permits or as a percentage of the building fee on new construction. Electrical panels, rewiring, EV chargers, HVAC change-outs, plumbing lines and water heaters are over-the-counter permits in ACA. Fire sprinkler, fire alarm and underground fire line permits are separate applications with their own fees.
A homeowner, the homeowner’s agent or a contractor licensed by the State of California can obtain a building permit. Owner-builders attach the city’s owner-builder package to the two-page building permit application. The city recommends a licensed contractor and points applicants to the Contractors State License Board ((800) 321-2752) to check a contractor’s license.
How to apply for a West Sacramento building permit
Ask the Planning Division whether the project is allowed in the zone before spending heavily on design.
Complete pages 1 and 2 of the building permit application, plus the owner-builder, tree disclosure, Environmental Health land use survey or air district forms that apply.
Use ACA for over-the-counter permits, or email plans to buildingpermits@cityofwestsacramento.org; counter submittals must be on a USB flash drive or CD.
The 65% plan review fee is due in full once the application is deemed complete.
The construction and demolition recycling plan, Part 1, must be in before the permit is issued.
Check status and pay in the West Sac Services Portal without logging in.
Submit recycling Part 2 once debris is disposed of, and pass engineering, fire and building finals.
Review, corrections and what causes delay
Three plan review cycles are included in the plan review fee; a fourth and later rounds are billed at $155 an hour, so a complete first submittal matters. Associated engineering permits run on their own track and need a pre-site inspection before any building inspection. A permit expires 12 months after issuance, or if no inspection has been made within 12 months; the city has an extension request form, and an extension is $63.
West Sacramento building inspections
Building inspections can be requested online in ACA, by phone at (916) 617-4691 or by email to bldginsp@cityofwestsacramento.org. Online requests need the ACA account linked to the permit; call (916) 617-4645, option 1, or email the division to link it. Requests can be made up to 10 business days ahead for Monday to Friday, excluding city holidays, and if the requested day is full the inspection goes to the next available business day. The division does not call back or confirm, so check ACA for the scheduled date.
Want this handled start to finish?
Get a free quote →A phone or email request should give the permit number, the type of inspection, the site address, the requested date, a morning or afternoon preference and an on-site contact’s name and phone number. The inspector needs access to the work, including a ladder. Re-inspection fees ($152) can be charged for no access, no approved plans on site or repeated corrections. To cancel or reschedule, call (916) 617-4645, option 1, before 8:30 a.m. on the day.
For a new single-family home, the solar, sprinkler and building final inspections are scheduled together. On commercial projects the fire final must pass before the building final, and on any project with grading, onsite, connection or encroachment permits the engineering final comes before the building final; engineering inspections need at least two working days’ notice. Special inspections follow the city’s Special Inspection and Testing Agreement and its list of approved agencies.
California building code in West Sacramento
The 2025 California building codes, including the energy code and CALGreen, have been in effect in the city since January 1, 2026. The division posts a notice for commercial applicants on disability access requirements, and existing buildings can ask for an unreasonable hardship exception when access upgrades in the area of work would be an unreasonable hardship. FEMA’s Community Status Book lists the City of West Sacramento (community 060728) as participating in the National Flood Insurance Program, with a current flood map dated January 19, 1995, and in the Community Rating System at class 8 (a 10% flood insurance discount).
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
West Sacramento building permit FAQs
Can I drop off paper plans?
No. Since June 2022 plans are accepted only electronically: by email, online, or at the counter on a USB flash drive or CD.
How much is a re-roof permit?
$368 per structure under the schedule effective November 1, 2025.
Do I need a permit for a fence?
Only for fences over 7 feet, or masonry fences and walls over 4 feet.
Inspections are where schedules slip.
Get a free quote →How do I schedule an inspection?
In ACA with your account linked to the permit, by phone at (916) 617-4691, or by email to bldginsp@cityofwestsacramento.org, up to 10 business days ahead.
Can a homeowner pull a permit?
Yes. A homeowner, an agent or a state-licensed contractor can obtain one; owner-builders attach the owner-builder package.
How much are school fees?
Washington Unified School District charges $5.17 per square foot for residential space and $0.84 for commercial or industrial space.
How do I get old permit plans?
File a public records request. Stamped plans are copyrighted, so copies need the designer’s permission; staff can arrange a viewing instead.
West Sacramento permit search and official resources
The ACA portal shows which permits have been taken out on a parcel and their status. Approved plans and permit documents are requested through the city’s public records request process.
- Building & Permitting Division
- Building applications and forms
- Building fees page
- Building Permit Fee Schedule, effective Nov. 1, 2025 (PDF)
- California Building Standards Code (Title 24)
- FEMA Community Status Book, California
Simplify West Sacramento permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in West Sacramento sooner?
Let Alliance prepare, file, and track your West Sacramento permits while your crew stays on the job.
More California permitting guides
Yolo County
Read guide →Woodland
Read guide →Davis
Read guide →Westminster Building Permit Guide
Read guide →Whittier Building Permit Guide
Read guide →Wildomar Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about West Sacramento permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.