To get a building permit in Wildomar, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Wildomar’s own Building and Safety Department, at City Hall on Clinton Keith Road, reviews plans and issues building, electrical, plumbing and mechanical permits inside the city. New applications go in by email only; rooftop solar goes through Symbium.

Authority: Wildomar Building & Safety DepartmentPhone: 951-677-7751Inspections: 951-677-5616, Mon–Thu
Authority
City Building & Safety23873 Clinton Keith Rd, Suite 110
Apply
Email bldgpermits@wildomar.govNo counter submittals; solar via Symbium
Time limit
12 months per application180 days plus two 90-day extensions
Inspections
Request by 4 p.m.Next business day, Monday to Thursday

Building permits in Wildomar come from the city’s Building and Safety Department at City Hall, 23873 Clinton Keith Road, Suite 110 (951-677-7751), where M. Scott Burns is the Chief Building Official. Applications and plans are emailed to the Building Permit Team; the counter does not take submittals. Valuation-based permits are priced from the fee schedule the city posts as approved in 2023: a 400 sq ft wood-frame addition works out to about $1,806 in permit, plan check, development review and administration fees before impact and school fees.

What requires a building permit in Wildomar?

The department issues building, electrical, plumbing, mechanical and associated permits for residential, commercial and industrial work in the city. Its fee schedule shows the range of work it permits, and the application form’s fixture sheet lists the trade items that need counting on a permit.

Permit needed

  • New homes, factory-built homes, ADUs and junior ADUs, additions, conversions and rehabilitation
  • Garages, barns, workshops, sheds, carports, pool houses, patio covers, decks and balconies
  • Re-roofs, retrofit windows and demolition, including demolition of swimming pools and spas
  • Swimming pools and spas (in-ground and above-ground), with the city’s pool barrier notice
  • Retaining walls, garden walls and fences over 7 feet tall
  • Water heaters, HVAC units, panel upgrades, sewer or septic repair, gas piping and repiping
  • Rooftop solar, battery storage and electric vehicle chargers
  • Commercial tenant improvements, change of tenancy, signs, cell towers and manufactured coaches

Published shortcuts

  • Block walls and patio covers can follow the city’s standard plans (block wall, retaining wall and March 2018 patio cover standard)
  • Eligible home solar and battery systems are permitted automatically in Symbium without manual review
  • ADUs can use the city’s pre-approved plan sets, free of charge

Work started without a valid permit is charged double the base permit fee. The department also handles complaints about unpermitted building work through its code compliance investigations.

What Wildomar decides and what the state holds

The city sets its own fee schedule, its 12-month limit on applications, its submittal method and its design criteria: wind speed 110 mph, seismic design category D2 to E, a 12-inch frost line, zero ground snow load and very heavy termite exposure. Its zoning rules sit in Title 17 of the Wildomar Municipal Code and the Development Code. Contractor licensing, the owner-builder exemption and the licensed-or-exempt declaration on the application are state law.

Wildomar building department: who handles permitting

Wildomar runs its own Building and Safety Department inside the city limits; the department reviews plans, issues permits, inspects work and investigates building code complaints. Riverside County permits only unincorporated land outside the city. Fire plan review and fire inspections for new development come from the Office of the Fire Marshal, provided through the city’s cooperative agreement with CAL FIRE/Riverside County Fire Department.

Short on time to read all of this?

Get a free quote →
Wildomar permit contacts
DetailInformation
OfficeBuilding and Safety Department, City Hall, 23873 Clinton Keith Road, Suite 110, Wildomar, CA 92595
Phone / email951-677-7751; applications to bldgpermits@wildomar.gov
CounterStaffed five days a week, 7:30 a.m. to 6:00 p.m., for questions and permit processing (no counter submittals)
Chief Building OfficialM. Scott Burns, ext. 249
Inspections951-677-5616 or bldginspect@wildomar.gov
Planning Division951-677-7751, planning@wildomar.gov; counter Monday to Friday, 7:30 a.m. to 6:00 p.m.; Community Development Director Robert Flores, ext. 213
Fire MarshalOffice of the Fire Marshal, 951-677-7751 ext. 8216
Septic approvalRiverside County Department of Environmental Health, 951-955-8980

Wildomar permit types

One Building and Safety Permit Application covers residential, commercial and manufactured-home work. It asks for the parcel number, the use, the square footage, a valuation and a description of work, with check boxes for multi-family units, attached or detached ADUs and junior ADUs, and a fixture-count sheet for electrical, mechanical and plumbing items. Fixed-fee permits carry the $111 issuance fee on top of the item fee; valuation-based permits are priced from the building’s size and ICC construction value.

Residential permits

Smaller home jobs are flat fees: a panel upgrade, a single-family HVAC change-out, a water heater, retrofit windows, a spa or pool. Additions, new houses, garages, sheds, patio covers, decks and re-roofs are valuation-based. Rooftop solar and battery systems for homes must go through Symbium, which checks the design against state and local rules, confirms the contractor’s state and business licenses and issues the permit automatically when the system qualifies. For ADUs the city publishes a 2026 guidebook with checklists and free pre-approved plan sets; ADUs under 750 square feet pay no city impact fee.

Commercial permits

The schedule has separate lines for new commercial and industrial buildings, additions, tenant improvements with or without an occupancy change, change of tenancy without improvements, canopies, trash enclosures, light standards, signs and cell towers. Commercial work goes through the Office of the Fire Marshal for fire plan review. The city’s checklist for expedited electric vehicle charging station permits covers non-residential chargers.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Zoning. The Planning Division’s GIS Parcel Information Tool shows the zone and development standards for any address or parcel number. Planning applications are taken electronically only.
  • Planning approvals. Projects that need a plot plan, conditional use permit or variance go through Planning first; the Planning Commission or City Council hears the larger ones.
  • Engineering. Grading, encroachment, haul and oversized-load permits come from Development Engineering, which takes encroachment applications by email with its own checklist.
  • Septic and wells. Riverside County Environmental Health approves septic systems; the ADU guidebook puts its fee at $796 where a well or septic tank is proposed.
  • Utilities. Water and sewer come from Elsinore Valley Municipal Water District (951-674-3146), power from Southern California Edison and gas from SoCalGas.

Wildomar permit fees

The department’s fee document is posted as the Building Department Fee Schedule approved in 2023; the PDF itself is headed "Proposed Building User Fees" and shows each fee’s full cost, a "Current Fee" column and a "Proposed Fee" column. The figures below are from the proposed-fee column, which the city’s posting labels approved; no adopting resolution is printed. Valuation-based permits use a base fee of 0.00909 times the ICC construction valuation (2023 San Diego Area Chapter multipliers, for example $220.39 per sq ft for a wood-frame home addition and $184.32 for a new wood-frame dwelling). Plan check adds 75% of the base fee, development review 20% of the base fee, and general administration 15.58% of those three together. A job valued at $1,000 or less totals $233.32.

Wildomar building fees (2023 schedule)
ItemFee
Permit issuance (fixed-fee permits)$111
Technology / professional development (all permits)$11 / $7
Electrical fixtures, first 1–3 / each extra$109 / $5
Electrical panel upgrade$109
Single-family HVAC$176
Water heater installation or replacement$109 (plumbing line); $176 for a like-for-like replacement on the mechanical line
Residential solar, up to 15 kW$450, plus $15 per kW above 15 kW; no issuance fee
Battery, first / each extra$88 / $19
Electric vehicle charger$450; no issuance fee
Swimming pool or in-ground spa / above-ground spa$505 / $286
Retrofit windows$176
Demolition$287; no issuance fee
Re-inspection (1 hour) / extra plan review (hour)$147 / $188
Certificate of occupancy$170
Permit extension$144
MSHCP administration fee$54

Rather talk it over?

Call 1-855-478-4290 →

Worked example: a 400 sq ft wood-frame addition is valued at 400 × $220.39 = $88,156. The base fee is $801.34, plan check $601.00, development review $160.27 and administration $243.45, for $1,806.06; the technology and professional development fees bring it to $1,824.06 before the state seismic and building standards fees. For valuation-based permits, 80% of the plan check fee is refunded only if plan check has not begun, and 80% of the base permit fee only if no work has begun. Expired permits can be renewed for 75% of the original fees if no work started, 50% if half the work is done and 25% at 75% complete.

Impact fees are separate. The 2025 Development Impact Fee schedule (updated July 1, 2025 for a 5.56% cost index increase) totals $31,369 per house in the low-density residential category and $22,230 per 1,000 sq ft of commercial space. The ADU guidebook (fees as of November 2025) adds a Lake Elsinore Valley Unified School District fee of $6,204 for ADUs of 501 square feet and over, none below that, and notes that fees are updated each year. Planning fees rose 3.43% on July 1, 2026: an administrative plot plan is $15,155, a setback adjustment $1,320, a variance $12,254 and a zoning compliance letter $528.

Trade permits and who may pull them in Wildomar

Electrical, plumbing and mechanical work is permitted by the same department, either on its own fixed-fee permit or counted on the fixture sheet of a building application. Plumbing fixtures cost $109 for the first three and $5 each after that; gas piping is $123 for the first three gas fixtures; a sewer or septic connection or repair is $176; a grease interceptor is $109.

  • Contractors enter their state license number, class and expiration date and a business license number on the application, and complete the workers’ compensation declaration. Symbium checks contractor and business licenses automatically for solar jobs.
  • Owners may sign the owner-builder declaration on the application, choosing whether they will do the work themselves or hire licensed contractors; the form also carries the construction lending agency statement and a note that accessibility rules may apply.
  • Fire systems such as sprinklers and fire monitoring are marked on the application; the Office of the Fire Marshal reviews construction plans for fire safety.

The department’s forms page also carries a carbon monoxide and smoke detector notification, the pool barrier notice and a form for demolishing swimming pools and spas.

Rather not deal with the building department?

Get a free quote →

How to apply for a Wildomar building permit

1. Look up the parcel

Use the GIS Parcel Information Tool for zoning and standards, and call Planning if the project needs a plot plan or other approval.

2. Choose the route

Rooftop solar and batteries go through Symbium; ADUs can start from the pre-approved plan sets; everything else uses the standard application.

3. Prepare the package

Fill in the Building and Safety Permit Application with valuation, square footage and fixture counts, and attach plans, calculations and any standard plan used.

4. Email the submittal

Send the application and documents to bldgpermits@wildomar.gov; the counter does not accept applications.

5. Pay and answer comments

Pay plan check through the city’s online payment page, then revise and resend plans until every reviewer signs off.

6. Clear outside agencies

Pay school fees to Lake Elsinore Valley Unified, arrange water and sewer with EVMWD, and get Environmental Health approval for septic.

7. Collect the permit

Pay the remaining permit and impact fees and receive the permit before any work starts.

Review, corrections and what causes delay

Plans are reviewed by Planning, Building, Public Works, Engineering, Fire and Landscape. For ADUs the guidebook puts the first comment letter at about two weeks and says most applications get one or two comment letters before approval. Every application has 12 months: an initial 180 days plus two 90-day extensions. The city grants nothing beyond that, so an application that cannot be issued in 12 months expires. Plan reviews beyond those included in the fee are billed at $188 an hour, and approved plan revisions cost $178.

Inspections in Wildomar

Inspections run Monday to Thursday only. Email the completed inspection request form to bldginspect@wildomar.gov, or call 951-677-5616 and leave the permit number, address, inspection type, an onsite contact with phone number and any special instructions. Requests received by 4:00 p.m. go on the next business day’s schedule; a request made after 4:00 p.m. on Thursday is scheduled for the following Tuesday. Morning or afternoon requests are not guaranteed, and the daily inspection run sheet is posted on the department page.

  • Inspections follow the stages of the work, such as foundation, framing, electrical and final.
  • A re-inspection is $147 an hour; special or after-hours inspections are $476 for four hours.
  • A replacement job card costs $92, and the certificate of occupancy is issued for $170.

Construction is allowed Monday to Saturday from 6:30 a.m. to 7:00 p.m., with no work on Sundays or city holidays.

California building code in Wildomar

The department lists its current adoptions as the 2025 California building, residential, fire, plumbing, mechanical, energy, existing building, electrical and green codes, and publishes the design criteria that plans must meet. The Office of the Fire Marshal notes that Fire Hazard Severity Zone maps from the Office of the State Fire Marshal affect building rules, defensible space and real estate disclosures in Wildomar. FEMA’s Community Status Book lists Wildomar (community 060221) as participating in the National Flood Insurance Program, with a current flood map dated August 28, 2008.

Want this handled start to finish?

Get a free quote →

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Wildomar building permit FAQ

Who issues building permits in Wildomar?

The City of Wildomar Building and Safety Department, at 23873 Clinton Keith Road, Suite 110. Fire plan review is done by the Office of the Fire Marshal under the city’s agreement with CAL FIRE/Riverside County Fire.

Can I submit a permit application at the counter?

No. New applications are taken only electronically, by email to bldgpermits@wildomar.gov. Staff at the counter help with questions and processing.

How much does a building permit cost in Wildomar?

Flat fees cover small jobs, such as $109 for a panel upgrade or $176 for a home HVAC change-out plus the $111 issuance fee. Larger jobs are valuation-based: a 400 sq ft addition comes to about $1,824 including the technology and professional development fees.

How do I get a solar permit?

Since March 1, 2026 residential solar and battery applications must go through Symbium, which issues qualifying permits automatically. The solar fee is $450 for systems up to 15 kW.

How long is a permit application good for?

Twelve months: 180 days plus two 90-day extensions, with no further extension.

When are inspections done?

Monday to Thursday. Requests made by 4:00 p.m. are scheduled for the next business day; Thursday requests after 4:00 p.m. go to Tuesday.

Do ADUs pay impact and school fees?

ADUs under 750 square feet pay no city impact fee, and the guidebook shows no school fee for units of 500 square feet or less; larger units pay both.

Wildomar permit search and official resources

Applicants follow their own permits through the Building Permit Team by email or phone; ask Building and Safety at 951-677-7751 about older permits and final inspections for an address. The daily inspection run sheet shows the current day’s inspections.

Inspections are where schedules slip.

Get a free quote →

Simplify Wildomar permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Wildomar sooner?

Let Alliance prepare, file, and track your Wildomar permits while your crew stays on the job.

This guide is provided by Alliance Permitting for general information about Wildomar permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.