Municipal GuideCaliforniaRosemead · Los Angeles County

Rosemead, California Building Permit Guide

To get a building permit in Rosemead, confirm which office issues permits for the property’s address, then submit the application with your plans and required documents, pay the permit fees, and pass inspections before final approval. Alliance Permitting can prepare, file and track the permit for you and schedule the inspections.

Rosemead’s Building and Safety Division at City Hall, 8838 E. Valley Boulevard, checks plans, issues permits and inspects construction in the city, after the Planning Division has signed off on the project.

Authority: Rosemead Building and Safety DivisionPhone: (626) 569-2130Hours: Mon–Thu 7–6
Authority
City Building and Safety8838 E. Valley Blvd, Rosemead
Start
Planning DivisionProjects are submitted to Planning first
Fee basis
LA County fees + 50%Municipal Code Section 15.04.030
Inspections
Request by 3:30 p.m.For next-day consideration

Building permits in Rosemead are issued by the city’s Building and Safety Division at City Hall, 8838 E. Valley Boulevard ((626) 569-2130), open Monday to Thursday from 7 a.m. to 6 p.m. Development projects start with the Planning Division, plan check takes about 2 to 3 weeks per full review under the city’s process chart, and building plan check and inspection fees are Los Angeles County’s Title 26 fees plus 50%, as set by Section 15.04.030 of the Municipal Code.

What requires a building permit in Rosemead?

Rosemead regulates the construction, use and occupancy of buildings, and its plan check covers structural, architectural, grading and fire safety review. The city’s permit worksheet shows the work it permits and counts for fees:

Building

  • New homes, additions and accessory buildings
  • Alterations and repairs
  • Grading (the worksheet asks for cubic yards of soil disturbed)
  • Pools, spas and hot tubs
  • Commercial buildings and tenant spaces

Trades

  • Electrical: services, panels, circuits, outlets, fixtures and appliances
  • Mechanical: furnaces, A/C compressors, ducts, fans and hoods
  • Plumbing: fixtures, water heaters, gas, backflow devices and repiping
  • Sewer connections and private disposal systems
  • EV chargers and rooftop solar

The city does not post a list of work that needs no permit; ask the division before starting. When a residential addition, alteration or repair is valued at more than $1,000, the city’s owner certification form explains that smoke and carbon monoxide alarms must be brought up to code.

What Rosemead decides and what the state holds

The city sets its zoning, its design review program for single-family homes and multi-family projects, its own fee add-on to the county building fees, and development impact fees. Its Planning page lists the Single Family Residential Design Guidelines, the Garvey Avenue Specific Plan, the Freeway Corridor Mixed-Use Overlay and the Downtown Rosemead Design Guidelines among its land use documents. The single-family guidelines, in effect since July 12, 2007 and last amended by Ordinance No. 933 on October 22, 2013, combine standards that are mandatory for all new homes and remodels, incentives that allow modest extra floor area for preferred features, and optional recommendations; where they differ from the zoning code, the stricter rule applies, and Planning offers informal reviews while plans develop. The state sets the building code and licenses contractors.

Rosemead building department: who handles permitting

The City of Rosemead issues its own building permits. The Building and Safety Division is part of the Community Development Department, which also includes Planning, Economic Development and Housing and is led by Director of Community Development Lily Valenzuela. Public Works handles engineering, stormwater (LID) review and encroachment permits.

Short on time to read all of this?

Get a free quote →
Rosemead permit contacts
DetailInformation
OfficeBuilding and Safety Division, Rosemead City Hall, 8838 E. Valley Boulevard, Rosemead, CA 91770
PhoneBuilding and Safety (626) 569-2130; City Hall (626) 569-2100
HoursMonday to Thursday, 7 a.m. to 6 p.m.; payments must be processed by 5:30 p.m.
Planning Division(626) 569-2140
Public Works(626) 569-2150; plans to pwengineer@cityofrosemead.org; encroachment permits to pwpermit@cityofrosemead.org
Business license(626) 569-2121
Emailbuildinginfo@rosemeadca.gov (solar submittals)

Rosemead permit types

Most applications start with the city’s plan check and permit worksheet, which records the owner, the contractor’s state license number and workers’ compensation policy, the estimated value, construction type and added square footage, and counts each electrical, mechanical, plumbing and sewer item. Completed forms go to the Building and Safety Division at City Hall.

Residential permits

  • Single-family homes and additions. They go through Planning first. The fee schedule lists design review for a single-family home at $1,115, and residential site plan review is $313 per dwelling unit for up to three reviews; projects with no new square footage pay $97.
  • Fences, hardscape and equipment. Planning charges $34 each for a fence plan review, a lot coverage review (landscape and hardscape) and a mechanical elements review.
  • Oak trees. An oak tree permit is $617.
  • ADUs. The fee schedule includes a $111 accessory dwelling unit covenant.
  • Rooftop solar. Licensed contractors on the SolarAPP+ eligibility list submit the design to SolarAPP+ ($35 processing fee, subject to change), then email the SolarAPP+ permit, checklist and city permit application to buildinginfo@rosemeadca.gov and return the signed permit once processed.
  • EV chargers. The city’s electric vehicle charging checklist, filed with the building permit application for homes, apartments, condominiums, businesses, mixed-use sites or the public right-of-way, asks for the charger level and rating, the service and panel ratings, the existing load and the conductor size (charger amps times 1.25). Once the checklist is deemed complete a permit is issued, unless the installation may have a specific adverse effect on public health or safety and needs more verification.

Commercial permits

Commercial projects follow the same Planning-first route. Non-residential site plan review is $860 and design review for new non-residential buildings $1,733. Before issuance, staff check that outside agencies have signed off: the Los Angeles County Fire Department (fire flow form), Los Angeles County Public Works industrial waste and sanitation, the county health department, the school district and the South Coast AQMD, where they apply. Commercial permits are valid for 6 months unless extended, against 1 year for residential permits.

Not sure this scope needs a permit?

Get a free quote →

What comes before the building permit

  • Administrative review. Projects that need only staff approval get comments or approval within about 2 to 3 weeks, with about a week for each resubmittal.
  • Discretionary review. Projects heard by the Planning Commission take about 30 days for completeness review, notices go out 10 days before the hearing, and approved applicants file a notarized acceptance of conditions within 10 calendar days. Before the hearing, Planning, Building and Safety and Public Works staff meet with the applicant, and plan changes typically take about 30 days. A project that is not exempt from CEQA goes through environmental review, which the chart puts at 6 to 12 months. Decisions can be appealed to the City Council within 10 days.
  • Pre-application. An optional pre-application review is $697.
  • Public Works. The engineer or architect completes a stamped Low Impact Development (LID) checklist, plans are emailed to Public Works for a 2 to 3 week plan check, and work in the street needs an encroachment permit.

Rosemead permit fees

Rosemead does not publish its own building fee table. Under Section 15.04.030 of the Municipal Code, quoted in the FY 2025–26 Comprehensive Fee Schedule (effective July 1, 2025), fees for plan check, inspection and other building services are the current Los Angeles County Title 26 fees increased by 50%. Counter staff set the plan review fee during a completeness check of 0 to 3 days after you submit. The city’s other user fees were set by Resolution 2022-56, adopted October 11, 2022 after a Willdan cost study, and rise with the Consumer Price Index each July 1.

Selected Rosemead fees, FY 2025–26 schedule and forms
ItemFee
Building plan check and inspectionLos Angeles County Title 26 fee + 50%
State seismic (SMIP) and green building feesSet by the state
Temporary certificate of occupancy / extension$256.20 / $170.55, plus $46.65 issuance each
Design review, single-family home / multi-family$1,115 / $1,394
Residential site plan review$313 per dwelling unit
Residential improvement, no new square footage$97
Fence, lot coverage or mechanical elements review$34 each
Conditional use permit / single-family variance$1,635 / $1,358
Minor exception / administrative use permit$418 / $697
Zoning verification letter, residential$83
Public Works construction permit issuance$140
Appeal to Planning Commission or City Council$857

Rather talk it over?

Call 1-855-478-4290 →

Development impact fees apply to new units and floor area: in single-use zones $6,500 per single-family unit and $5,197 per multi-family unit, and per 1,000 square feet $1,365 for retail, $1,997 for office and $1,250 for industrial; mixed-use zones are slightly lower ($6,388 and $5,126 per unit). They come from the Impact Fee Study approved June 9, 2015 and, under Resolution 2015-07, adjust each July 1 with the Engineering News Record construction cost index. Because the building fee depends on the county’s current table, ask the counter for the figure on your filing date.

Trade permits and who may pull them in Rosemead

Electrical, mechanical, plumbing and sewer work is permitted by the Building and Safety Division on the same worksheet, item by item: receptacles and fixtures, service panels by amperage, furnaces and A/C units by BTU rating, air handlers by airflow, each plumbing fixture, water heaters, gas pressure, backflow devices and house sewer connections. Fees follow the county-based schedule.

  • Contractors. The worksheet asks for the state license number, license type and expiry, and the workers’ compensation policy number and expiry.
  • Solar installers. SolarAPP+ permits are open only to licensed contractors added to the program’s eligibility list.
  • Special inspectors. Projects needing special inspection file the city’s special inspector form.
  • Business license. Every business in Rosemead needs either a business license or a no-cost business registration, depending on its classification, under Title 5 of the Municipal Code; both are renewed every year, and the city’s business guide advises clearing zoning with Planning before signing a lease. Call (626) 569-2121 to ask which applies to your work. Regulated industries must show stormwater (NPDES) enrollment under SB 205 before a license is issued.
  • Homeowners. The city’s pages do not describe an owner-builder process; ask the counter what an owner must provide.

Rather not deal with the building department?

Get a free quote →

How to apply for a Rosemead building permit

1. Submit to Planning

Development projects start with a Planning Division submittal, administrative or discretionary.

2. Review submittal requirements

After Planning approval, check the Building and Safety submittal list and complete the permit worksheet.

3. File for plan check

Submit the application and full construction documents; counter staff check completeness and set plan review fees.

4. Answer corrections

Full review takes 2 to 3 weeks and each resubmittal 1 to 2 weeks.

5. Restamp and clear agencies

Approved plans go to Public Works and Planning for restamping, and outside agencies must be satisfied.

6. Pay and issue

Pay at City Hall before 5:30 p.m. and collect the permit.

Review, corrections and what causes delay

The city’s development process chart (revised April 2021) makes clear that resubmittal time depends on the applicant: each round continues until the application is ready for approval. A building application with full construction documents stays valid for 1 year unless extended. Outside agency sign-offs (fire flow, industrial waste, sanitation, health, school district and AQMD) are checked at the end, just before the permit is issued.

Inspections in Rosemead

Inspections are requested on the city’s online form or by email to the Building Division, with the address, permit number, inspection type, preferred date and a.m. or p.m., and a contact name and phone number. A request must be in by 3:30 p.m. to be considered for the next day, subject to availability, and the requested day and time are not guaranteed. The daily inspection list, with time frames, is posted on the Building Division webpage at 6:15 p.m.

When the inspector cannot get normal access to the interior of a home, the owner signs the city’s smoke and carbon monoxide alarm certification. If a building is ready to use before every item can be signed off, the Building Official can grant a temporary certificate of occupancy for full occupancy, stocking and training only or part of the building ($256.20, plus $46.65 issuance); it becomes void on its expiration date.

California building code in Rosemead

Rosemead ties its building fees to the Los Angeles County Building Code fee table (Title 26) through Municipal Code Section 15.04.030. FEMA’s Community Status Book lists Rosemead (community 060153) as participating in the National Flood Insurance Program, with no special flood hazard area shown on its current map.

California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments

Rosemead building permit FAQ

Where do I apply for a building permit in Rosemead?

At the Building and Safety Division, Rosemead City Hall, 8838 E. Valley Boulevard, after the Planning Division has reviewed the project. Call (626) 569-2130 with questions.

Want this handled start to finish?

Get a free quote →

How are Rosemead building permit fees calculated?

Plan check and inspection fees are Los Angeles County’s current Title 26 fees plus 50%, under Municipal Code Section 15.04.030. Staff set the plan review fee when you submit.

Does a new house need design review?

The single-family design guidelines are mandatory for new homes and remodels, and the fee schedule lists design review for a single-family home at $1,115, alongside residential site plan review at $313 per unit.

How long does plan check take?

About 2 to 3 weeks for a full review and 1 to 2 weeks for resubmittals, according to the city’s process chart.

What is the inspection cut-off?

Requests must be in by 3:30 p.m. for next-day consideration; the inspection list is posted online at 6:15 p.m.

How long is a permit valid?

One year for residential permits and 6 months for commercial permits, unless extended, according to the city’s process chart.

Are there impact fees for a new home?

Yes. A new single-family unit in a single-use zone pays $6,500 under the FY 2025–26 schedule, adjusted each July 1.

Can solar be permitted online?

Yes, for licensed contractors using SolarAPP+; the approved SolarAPP+ permit, its checklist and the city application are emailed to the Building Division, and SolarAPP+ charges its own $35 processing fee.

Rosemead permit search and official resources

Permit and inspection questions go to the Building and Safety Division at (626) 569-2130; the daily inspection schedule is posted on the Building Division webpage. For copies of past permits, ask the division at the City Hall counter.

Inspections are where schedules slip.

Get a free quote →

Simplify Rosemead permitting with Alliance Permitting

250K+Permits approved
All 50States covered
21+ YearsJurisdictional depth
Done-for-youWe file, you build

Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.

Ready to break ground in Rosemead sooner?