Inside Red Bluff, building permits come from the City’s Community Development Department, whose Building Division takes applications at 555 Washington Street (530-527-2605) and online through eTRAKiT. Fees follow the Building Department schedule the City Council adopted on May 7, 2024: a permit for $150,000 of work is $3,031.50, and 60% of the permit fee is paid as a deposit at submittal. Land outside the city limits is permitted by Tehama County Building & Safety.
What requires a building permit in Red Bluff?
The City’s permit process covers building, mechanical, electrical, plumbing, sign, demolition, grading, mobile home installation and occupancy permits, the list Chapter 5 of the City Code uses for its application and permit time limits. The Building Department fee schedule also prices building moving permits and occupancy permits, so new buildings, additions, remodels, trade work, signs, demolition and relocation of a building all go through the Building Division.
City permits listed
- Building permits, priced by project valuation
- Plumbing, mechanical and electrical permits
- Grading permits (by cubic yards moved)
- Demolition and building moving permits
- Mobile home and commercial coach installations
- Sign permits and occupancy permits
Other City approvals
- Planning Division zoning plan check and design review
- Flood plain plan and site review under Chapter 26
- Tree replacement plans for heritage and mature native trees
- Public Works encroachment permits for work in streets and sidewalks
Chapter 5 as the City posts it deals with application and permit time limits rather than an exempt-work list, so ask the Building Division (ext. 3058) whether a small project such as a shed, fence or patio cover needs a permit. Work started without a required permit costs $112 per hour, per violation, per day, plus three times the standard permit fees.
What Red Bluff decides and what the state holds
The City sets its own permit procedures and time limits in Chapter 5, design review in Chapter 7, zoning in Chapter 25 and flood damage prevention in Chapter 26, and its fees by Council resolution. Electric vehicle charging stations follow a City Council-approved EVCS checklist, and landscaping must meet the City’s water efficient landscape ordinance. Contractor licensing remains a state matter.
Red Bluff building department: who handles permitting
The Community Development Department’s Building Division handles plan review, permits and inspections inside the city, and the department’s Planning Division handles zoning and land use. Community Development Director Beth Moyer heads the department (ext. 3059). Plans are also routed to the Fire Department, Police Department and Public Works. Property outside the city limits, in unincorporated Tehama County, is permitted by Tehama County Building & Safety at 444 Oak Street, Room H (530-527-7002).
Short on time to read all of this?
Get a free quote →| Office | Contact |
|---|---|
| Building Division counter | Community Development Department, 555 Washington Street, Red Bluff, CA 96080; (530) 527-2605 |
| Building permit fees and administration | (530) 527-2605 ext. 3058 |
| Community Development Director | (530) 527-2605 ext. 3059 |
| 24-hour building inspection line | (530) 527-2605 ext. 3069 (messages only) |
| Public Works inspection line (encroachments) | (530) 527-2605 ext. 3055 or 3052 |
| Finance Department (business licenses) | (530) 527-2605 ext. 3010 |
| Unincorporated Tehama County | Tehama County Building & Safety, 444 Oak Street, Room H; (530) 527-7002 |
Permit types in Red Bluff
Only the property owner or a licensed contractor may sign for a permit. Every applicant fills out the preliminary permit application; owners add the owner-builder form, and contractors add the subcontractor list. Other forms on the City’s page include the smoke and carbon monoxide alarm affidavit, the mechanical service outlet requirements, the green building waste diversion handout and the Public Works site plan requirements.
Residential permits
Home projects are priced on the City’s valuation table, with separate unit fees for plumbing, mechanical and electrical work. The Community Development Department posts nine ADU plan sets in its Document Center, in small (Oak, Pine, Walnut), medium (Cedar, Elm, Hickory) and large (Ash, Sycamore, Willow) sizes. Residential design review for two to four units costs $283. A home-based business needs both a City business license and an occupancy permit.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial plans get Fire Department fire and life safety review, charged at 10% of the building plan review fee with a $188 minimum, and fire sprinkler systems are reviewed separately ($564 for a new NFPA 13 or 13R system of up to 100 heads). Non-residential design review runs $276 for buildings up to 2,500 square feet. Projects that need state or regional sign-offs may be returned for revisions after comments from agencies such as Caltrans, the Regional Water Quality Control Board or the state and federal wildlife agencies.
For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Zoning. The City suggests checking with the Planning Division first: Planning approvals are typically required before a building permit can be issued, and a use permit ($1,696) or administrative use permit ($339) adds time.
- Design review and trees. Design review under Chapter 7 and tree replacement plans under the tree ordinance are Planning items.
- Flood zones. Projects in a flood area need flood plain plan and site review under Chapter 26 ($276).
- Street work. Driveways, sidewalks, curb and gutter, and water or sewer connections in the public right-of-way need a Public Works encroachment permit.
- School fees. School fees are paid at the Red Bluff School District offices, and proof of payment is needed before the permit is issued.
- County health sign-off. Where required, the City’s Environmental Health approval form must carry the signature of Tehama County Environmental Health (633 Washington Street, Room 36; 530-527-8020) before the permit is issued.
Not sure this scope needs a permit?
Get a free quote →Red Bluff permit fees
Building fees are set by Exhibit F of the City’s Schedule of Fees and Charges, adopted after a public hearing on May 7, 2024 and in effect since July 1, 2024. Plan check is included in the building permit fee, but 60% of the permit fee is due as a deposit when the application and plans are submitted. Development impact fees, engineering and Planning fees may be added.
| Project valuation | Fee |
|---|---|
| $1 to $500 | $56 |
| $501 to $2,000 | $56 for the first $500, plus $7.27 per added $100 |
| $2,001 to $25,000 | $165 for the first $2,000, plus $33.30 per added $1,000 |
| $25,001 to $50,000 | $931 for the first $25,000, plus $24.04 per added $1,000 |
| $50,001 to $100,000 | $1,532 for the first $50,000, plus $16.66 per added $1,000 |
| $100,001 to $200,000 | $2,365 for the first $100,000, plus $13.33 per added $1,000 |
| $200,001 to $500,000 | $3,698 for the first $200,000, plus $13.33 per added $1,000 |
| $500,001 to $1,000,000 | $7,697 for the first $500,000, plus $11.31 per added $1,000 |
Worked example. For a $150,000 project, the fee is $2,365 for the first $100,000 plus 50 × $13.33 ($666.50), or $3,031.50. The deposit due at submittal is 60% of that, $1,818.90. The same exhibit carries a separate, higher table headed “Building with Demolition” ($2,745 for the first $100,000, plus $20.01 per added $1,000 to $200,000), so ask the Building Division which table applies when a project includes demolition.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Plumbing, mechanical or electrical permit | $112 for the first 3,000 sq ft served, plus $0.04 per added sq ft; $25 per water heater or appliance |
| Plan re-check | $112 per hour |
| Building reinspection | $180 per inspection |
| Occupancy permit without / with inspection | $54 / $77 |
| Mobile home or commercial coach installation | $285 |
| Building moving permit | $360, plus $112 per hour of extra time |
| Grading permit and plan check | $40 (up to 50 cu yd); $56 (51–100); $88 (101–1,000); $117 (1,001–10,000) |
| Zoning plan check (Planning) | $56 |
| Encroachment permit: no construction / sidewalk, curb, utility or water and sewer work / permanent | $56 / $141 / $283 |
| Fire sprinkler review, single-family (NFPA 13D) | $282 |
| Item | Fee |
|---|---|
| Preliminary plan review (each time) | $265 |
| Setback adjustment | $260 |
| Flood plain plan and site review (Chapter 26) | $276 |
| Tree replacement plan: heritage tree (Planning Commission) / mature native tree | $429 / $243 |
| Home occupation application review | $29 |
| Fire Department civil plan design review | $188 |
| Underground fire service line, per system | $376 |
Planning and Public Works fees on the same schedule were adopted June 5, 2012 (effective August 19, 2012) and Fire Department fees May 7, 2019 (effective July 6, 2019). Refunds are capped at 80% of the fee, less deductibles.
Trade permits and who may pull them
The Building Division issues plumbing, mechanical and electrical permits; the fee is based on the floor area the new installation serves, $112 for the first 3,000 square feet plus $0.04 for each added square foot, with $25 for each water heater or other plumbing appliance. The City posts a wire size table and mechanical service outlet rules for applicants.
A permit may be signed only by the property owner, who completes the state owner-builder form the City posts, or by a licensed contractor, who lists subcontractors on the City’s form; contractors set up their eTRAKiT account with their state license number as the user name. Anyone doing business inside the city limits, including contractors, needs a current City business license, renewed each January 1 through the Finance Department.
Fire sprinkler, underground fire service and hood suppression systems are reviewed and inspected by the Red Bluff Fire Department under its own fee table.
Rather not deal with the building department?
Get a free quote →How to apply for a building permit in Red Bluff
Ask the Planning Division whether the use is allowed in the zone and whether a use permit, design review or flood plain review is needed.
Complete the preliminary permit application plus the owner-builder form or the subcontractor list, and prepare plans and a site plan that meets the Public Works requirements.
File at the Building Division counter, 555 Washington Street, or create an eTRAKiT account and submit online.
Pay 60% of the building permit fee with the submittal; staff calculate fees at the counter or at ext. 3058.
Building, Planning, Fire, Police and Public Works review the plans; revise and resubmit if comments require it.
Show proof of school fee payment, pay the remaining fees, online through eTRAKiT if you prefer, and start work.
Review, corrections and what causes delay
The City’s process chart estimates about two to three weeks for building plan review, about one to two months when Planning review or an administrative entitlement is involved, and about two to three months when the Planning Commission or City Council must approve. Comments from outside agencies such as Tehama County or Caltrans can require revised plans. Under Chapter 5, an application expires if no permit is issued within 180 days, and a permit expires if the work is not finished and given final approval within 180 days of issuance, unless the Community Development Director extends it on a written request before it lapses.
Inspections in Red Bluff
Leave inspection requests on the Building Department’s 24-hour line, (530) 527-2605 ext. 3069, at least one day ahead. Messages are collected once each workday at 7:00 a.m., and the line is not answered during the day. Inspections by the commenting departments can occur at grading, foundation, framing, interior and exterior finish and landscaping stages. A building inspector or the Community Development Director issues the building final or certificate of occupancy once every department has approved the work. Each reinspection costs $180.
Work in the public right-of-way is inspected by Public Works: give 48 hours’ notice for concrete form and water or sewer line inspections and 24 hours for the final, on ext. 3055 or 3052 between 9:00 a.m. and 2:00 p.m. on weekdays. The City makes taps into its sewer lines, with no taps after 2:00 p.m. Monday to Thursday or on Fridays. Encroachment permits expire one year after issuance, and work in the right-of-way is guaranteed for one year after final inspection.
Want this handled start to finish?
Get a free quote →Building code in Red Bluff
Red Bluff’s local construction rules are in Chapter 5 of the City Code, with flood damage prevention in Chapter 26. Flood insurance: FEMA lists the City of Red Bluff as a participating community in the National Flood Insurance Program, with a current flood map dated September 29, 2011.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Frequently asked questions
Who issues building permits in Red Bluff?
The City’s Community Development Department, through its Building Division at 555 Washington Street (530-527-2605). Outside the city limits, Tehama County Building & Safety issues permits.
How much is a building permit in Red Bluff?
It depends on valuation. A $100,000 project is $2,365, and a $150,000 project is $3,031.50 under the fee schedule in effect since July 1, 2024. Plan check is included, and 60% is paid as a deposit at submittal.
Can I apply online?
Yes. The City accepts submittals and fee payments through eTRAKiT; contractors use their state license number as the user name when setting up an account.
How do I schedule a building inspection?
Leave a message on the 24-hour line, (530) 527-2605 ext. 3069, at least a day ahead. Messages are collected at 7:00 a.m. each workday.
How long is a Red Bluff permit valid?
Under Chapter 5, the work must be finished and given final approval within 180 days of issuance unless the Community Development Director grants an extension requested in writing. Applications without a permit expire after 180 days.
Do contractors need a Red Bluff business license?
Yes. Every business transacting in the city limits needs a current City business license, renewed each January 1 through the Finance Department (ext. 3010).
Where do I pay school fees?
At the Red Bluff School District offices. The Building Division needs proof of payment before it issues the permit.
Red Bluff permit search and official resources
Permit holders link their permits to their eTRAKiT account to see fees due and pay online; the Community Development Department answers questions about older permits on a property.
Inspections are where schedules slip.
Get a free quote →- Red Bluff Community Development Department
- Building permits and eTRAKiT instructions
- eTRAKiT permit portal
- Forms and applications
- Building permit application (PDF)
- Owner-builder form (PDF)
- Building permit process details and time line (PDF)
- Schedule of Fees and Charges, July 1, 2024 (PDF)
- Chapter 5: application and permit expiration
- Encroachment permit application (PDF)
- Environmental Health approval verification (PDF)
- Business licenses
- Tehama County Building & Safety (unincorporated areas)
Simplify Red Bluff permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Red Bluff sooner?
Let Alliance prepare, file, and track your Red Bluff permits while your crew stays on the job.
More California permitting guides
Tehama County
Read guide →Shasta County
Read guide →Butte County
Read guide →Redding Building Permit Guide
Read guide →Redlands Building Permit Guide
Read guide →Redondo Beach Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Red Bluff permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.