On unincorporated land in Nevada County, building, electrical, plumbing, mechanical and grading permits come from the Nevada County Building Department, part of the Community Development Agency at 950 Maidu Avenue, Suite 170, Nevada City (530-265-1222, option 1), where George Schureck is the Director of Building. The county also does the building work for the City of Nevada City under contract. Applications, payments and inspection requests run through the county’s Citizen Access portal, and under the schedule in force since September 1, 2026, plan review and inspection are billed against a $191.20 hourly rate.
What requires a building permit in unincorporated Nevada County?
The county’s rule is short: anything not on its list of exempt work needs a permit. New houses, additions, garages and barns over the exemption, remodels, reroofs, decks, retaining walls over 4 feet, pools, solar, generators, grading and driveways all appear in the building fee schedule as permit work, and electrical, plumbing and mechanical work carries its own permit fee.
Permit needed
- New dwellings, factory-built homes and tiny homes on wheels set as dwellings
- Additions, remodels and conversions
- Reroofs, except repairs to less than 25% of the roof in a calendar year
- Decks over the exemption, patio covers and gazebos over 200 square feet
- Fences over 7 feet and block walls over 4 feet
- Pools and spas, solar systems, generators and propane tanks
- Grading, driveways and ponds
Exempt (county list)
- One one-story detached accessory building up to 200 square feet per parcel, with no electrical, plumbing or mechanical work and not for living in
- Other one-story detached accessory buildings up to 120 square feet
- Fences up to 7 feet and retaining walls up to 4 feet without a surcharge
- Detached decks up to 200 square feet and 30 inches above grade that do not serve a required exit door
- Sidewalks, driveways and finish work such as painting, tile and cabinets
The 200-square-foot allowance comes from section L-V 2.4 of the county code, and it is lost once utilities are added to the building; the structure must still meet setbacks.
What the county decides and what the state holds
Nevada County sets its own fees, exemption list, snow and wind design values and local amendments. Its 2025 code notes put the whole county in seismic design category D, take ground snow loads from the ASCE Hazard Tool (with an alternate-methods application allowed above 4,000 feet), set special wind speeds of 110 to 130 mph above 4,000 feet and east of Kingvale, and require backup power disconnect switches on the outside of the main building, within 3 feet of each other and signed. The state licenses contractors.
Nevada County building department: who handles permitting
The county Building Department covers every parcel outside city and town limits. Inside the three incorporated places the answer depends on the place:
| Place | Building permits |
|---|---|
| Unincorporated county | Nevada County Building Department |
| Nevada City | City planning approval first (317 Broad Street, 530-265-2496), then the Nevada County Building Department under the city’s contract |
| Grass Valley | City of Grass Valley Building Department, 530-274-4350 |
| Truckee | Town of Truckee Building & Safety, 530-582-7821 |
Short on time to read all of this?
Get a free quote →To check whether an address is unincorporated, look it up in the county’s My Neighborhood map, which also shows zoning, snow load and permit history.
| Office | Contact |
|---|---|
| Building Department | 950 Maidu Avenue, Suite 170, Nevada City, CA 95959 (bottom floor of the Eric Rood Administration Center); 530-265-1222, option 1; BuildingDept@nevadacountyca.gov; Director of Building George Schureck |
| Hours | Lobby 8 a.m. to 5 p.m. weekdays; the Building Department takes new projects 8 a.m. to 4 p.m., while the agency’s general pages list 8 a.m. to 3:30 p.m., so arrive early or book an appointment |
| Planning | 530-265-1222, option 2; planning@nevadacountyca.gov |
| Environmental Health (septic, wells) | Same building; 530-265-1222, option 3 |
| Public Works (encroachments) | 950 Maidu Avenue; 530-265-1411; Public.Works@nevadacountyca.gov |
Nevada County permit types
Most applications start in Citizen Access, where an account lets you file, upload plans, pay and track every review. Paper submittals still take three full plan sets, three site plans and two sets of truss and engineering calculations where they apply, and plan check fees are due when the plans are filed.
Residential permits
- New houses. A new dwelling also needs two sets of the septic design and site plan where a septic system serves it, and fire and school district fees are paid to those districts before issuance; each district returns a certificate of compliance.
- Owner-built rural homes. In qualifying rural zones the county’s Title 25 program for limited-density owner-built dwellings lets owners skip some requirements such as solar, sprinklers or engineered drawings while meeting basic health and safety rules; a restrictive covenant must be recorded before the permit issues, and parcels in community regions or rural centers do not qualify.
- Housing master plans. Pre-designed house and ADU plans shared by Nevada, Placer and Sierra counties, Truckee, Grass Valley and Nevada City cost $1,500 per use, paid to the design consultant before you apply; the county says they may be used without updates to the 2025 code.
- ADUs. ADUs are approved ministerially in the RA, R1, R2, AE, AG, FR and TPZ zones under county code section 12.03.191.
- Unpermitted work. The after-the-fact process starts with a meeting at the agency counter, a records search and dating the construction to set the code edition; plan check may call for a foundation scan, an engineer’s structural letter and trade contractor letters.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial projects use the commercial plan submittal checklist, and the Over-the-Counter Wednesday program offers plan review by appointment for non-structural tenant improvements under 1,500 square feet in retail or business occupancies. Commercial additions, new buildings, projects with hazardous materials and changes of use go through full plan review, which can involve Planning, Environmental Health, Code Compliance, Cannabis and Public Works.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning and zoning. Planning confirms zoning and setbacks and handles use permits and administrative development permits.
- Septic and wells. Environmental Health permits wells, septic systems and on-site soils evaluations (perk and mantle tests) through Citizen Access.
- Encroachments. Driveway, utility and construction work on a county-maintained road needs a Public Works encroachment permit, with $1 million in general liability cover naming the county; expect 7 to 10 business days.
- Fire districts. Each fire district sets its own development fees, paid before issuance.
Nevada County permit costs and fees
The county adopts a new fee schedule each fiscal year; the FY 2026-27 schedule took effect on September 1, 2026, with an hourly rate of $191.20. New buildings are priced by a base amount plus a rate per square foot that covers electrical, plumbing, mechanical, energy and access review; smaller jobs are priced in inspection units of $191.20.
| Item | Fee |
|---|---|
| Permit processing, over-the-counter / other permits | $95.60 / $191.20 |
| Site-built residence: inspection | $1,600.34 plus $0.13 per sq ft |
| Site-built residence: plan review | $1,005.71 plus $0.03 per sq ft |
| Residential addition (inspection and review) | $1,629.00 plus $0.27 per sq ft |
| Remodel or conversion (inspection and review) | $818.30 plus $0.31 per sq ft |
| Garage, shop, barn or shed (inspection and review) | $1,602.25 plus $0.12 per sq ft |
| Reroof / demolition / deck / fence over 7 ft | $382.40 each |
| Pool: vinyl / gunite / pre-made shell | $860.40 / $764.80 / $669.20 |
| Plumbing, mechanical or electrical permit (two visits) | $382.40 |
| Reinspection or extra site visit | $191.20 |
| Expedited plan review | $382.40 |
| Time extension or renewal | $95.60 |
| Grading plan review up to 1,000 / over 1,000 cubic yards | $478.00 / $764.80 |
| Grading bond, up to 500 / 501–1,500 cubic yards | $500 / $2,000 |
Rather talk it over?
Call 1-855-478-4290 →Worked example: a 2,000-square-foot site-built house pays $1,600.34 plus 2,000 × $0.13, or $1,860.34, for inspection and $1,005.71 plus 2,000 × $0.03, or $1,065.71, for plan review, plus the $191.20 processing fee: $3,117.25 before state charges. Plan review covers the first check and one recheck; further rechecks and progress or repeat inspections are billed at the hourly rate. The state seismic fee adds $0.13 per $1,000 of value on residential work, plus $1 and $4 state surcharges.
Impact fees are larger than the permit itself. The county’s estimate for western Nevada County, updated on October 5, 2026, puts a 1,800-square-foot house with a 500-square-foot garage at $24,822.70, including $5,998 in traffic impact fees, $9,684 in Nevada Joint Union High School District fees ($5.38 per square foot of living space), about $2,300 in fire district fees and up to $2,700 in park fees. In the east the Tahoe Truckee Unified School District charges $3.69 per square foot and the Truckee Donner Recreation and Park District sets its own fee. Neither estimate includes PG&E, Nevada Irrigation District, Public Works or septic and well charges. County-controlled impact fees can be deferred under the Development Impact Fee Deferral Program, but must be paid before final inspection.
Trade permits and who may pull them
The Building Department issues electrical, plumbing and mechanical permits alongside building permits; for a new building the square-foot fee already includes that review, and stand-alone trade jobs are priced at two inspection visits ($382.40).
Licensed contractors, or owner-builders working on their own property, may take out permits. The county publishes an owner-builder packet with the construction permit application, notice and property owner forms, and anyone else filing for the owner needs the agent authorization letter. A contractor search in Citizen Access shows contractors on file with the county.
Roofing contractors can apply to the county’s Platinum Roofing Program; the two-hour application review costs $382.40.
How to apply for a Nevada County building permit
Look up the parcel in My Neighborhood. In Nevada City, get city planning approval first; in Grass Valley or Truckee, apply to the city or town instead.
Ask Planning for zoning and setbacks, Environmental Health about septic and well capacity, and Public Works about road access.
Use the residential or commercial submittal checklist, the county general notes sheet and the snow, wind and seismic values for the site.
Upload plans as one combined plan file and one support-document file, or bring paper sets, and pay plan check fees at filing.
Upload a full revised set with a written response to each comment and a short note of what changed.
Bring fire and school district certificates of compliance, pay the balance and print the approved plans for the site.
Rather not deal with the Nevada County building department?
Get a free quote →Review, corrections and what causes delay
The county reviews new residences in about four weeks and most other projects in 10 days to four weeks. You get notices when routing starts, when every review is done and when the permit is ready, but not in between, so check Citizen Access for comments. Each resubmittal must carry the latest version of every document, including sheets that did not change, and digitally locked PDFs should be swapped for stamped but unlocked copies. Small qualifying jobs can be reviewed at Over-the-Counter Wednesday appointments, booked at least two days ahead; decks, patio covers, kitchen and bath remodels, additions and outbuildings under 600 square feet, residential ground-mount and commercial solar and residential pools qualify.
Inspections in Nevada County
Book inspections in Citizen Access; no account is needed. Requests made by midnight are scheduled for the next working day, and by 8 a.m. on the day the portal shows a two-hour arrival window. An adult must be on site with the approved plans and a secured ladder, work must stay uncovered until inspected, and cancellations must be phoned in by 8 a.m.
In the unincorporated east, from Yuba Gap to the state line, including Kingvale, Soda Springs and Floriston, inspections are done on Mondays and Thursdays and must be booked online at least two days ahead. Qualifying inspections can also be done by video through the county’s virtual inspection service.
A permit expires 180 days after issuance or after the last passed inspection, so keep inspections moving or file the extension and renewal request ($95.60). Before the final, have Environmental Health sign off the septic system and Public Works final any encroachment; new homes also turn in the CalGreen operation and maintenance manual and the construction waste form. When the final passes, the inspector signs the yellow permit card and issues the certificate of occupancy.
California building code in Nevada County
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Nevada County’s local amendments to the 2025 codes took effect on January 1, 2026 in its land use and development code, and every project submitted from that date is designed to the 2025 edition. The county also publishes its climatic and geographic design criteria and a 2025 general notes sheet for plans.
Nevada County building permit FAQs
Does Nevada County issue building permits inside cities?
Only in Nevada City, which contracts with the county for building services after the city’s own planning approval. Grass Valley and Truckee issue their own permits.
How big a shed can I build without a permit?
One one-story building up to 200 square feet per parcel, with no utilities and not for living in, plus any number of 120-square-foot sheds; all must meet setbacks.
How much is a building permit for a new house?
For a 2,000-square-foot site-built house the county’s inspection and plan review fees come to about $2,926 plus $191.20 processing, and the county’s western-county estimates, which add impact, school and fire fees, run from about $17,000 for a 749-square-foot house to $33,300 for a 3,000-square-foot house, each with a 500-square-foot garage.
Want this handled start to finish?
Get a free quote →How long does plan review take?
About four weeks for a new residence and 10 days to four weeks for most other projects.
When are inspections done in the eastern county?
On Mondays and Thursdays, booked online at least two days ahead.
Can I defer impact fees?
Yes for county-controlled impact fees, through the deferral program filed with your permit application; deferred fees are due before final inspection.
Who handles septic systems and wells?
Nevada County Environmental Health, at the same Maidu Avenue office, through Citizen Access.
Nevada County permit search and official resources
Citizen Access shows permit status, staff notes and inspection results around the clock, and the My Neighborhood map shows permit history by parcel. For older records, file a public records request with the agency.
Inspections are where schedules slip.
Get a free quote →- Nevada County Building Department
- Citizen Access permit portal
- My Neighborhood parcel map
- Work exempt from permits
- 2025 building codes and design criteria
- Apply for a building permit
- Plan review and digital resubmittals
- Permit issuance
- Inspection scheduling
- Final inspection
- Over-the-Counter Wednesday program
- After-the-fact permit process
- Title 25 owner-built rural dwellings
- Housing master plans
- Fee schedules
- FY 2026-27 building fees
- FY 2026-27 plan review and inspection rates
- Fee estimate, new residence, western county
- Fee estimate, new residence, eastern county
- Building document library
- Building Department FAQ
- Planning Department
- Accessory dwelling units
- Environmental Health
- Public Works permits
- Encroachment permits
- City of Nevada City forms and building permit note
- City of Grass Valley Building Department
- Town of Truckee Building & Safety
- FEMA Community Status Book, California
Unincorporated Nevada County takes part in the National Flood Insurance Program; its current flood maps date from February 3, 2010.
Simplify Nevada County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Nevada County sooner?
Let Alliance prepare, file, and track your Nevada County permits while your crew stays on the job.
More California permitting guides
Truckee
Read guide →Grass Valley
Read guide →Placer County
Read guide →Newark Building Permit Guide
Read guide →Newman Building Permit Guide
Read guide →Newport Beach Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Nevada County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.