In the City of Newman, the Building Department at City Hall, 938 Fresno Street, issues building permits and inspects construction; Stanislaus County permits only the unincorporated land around the city. Applications are emailed or brought to the second-floor counter, which is open Monday through Thursday from 8:30 a.m. to noon. Under the fee schedule effective February 1, 2025, a new one-story house is charged by the square foot and plan check adds 65% of the permit fee; over-the-counter jobs such as water heaters and HVAC change-outs start at $118.
What requires a building permit in Newman?
The Building Department publishes a list of common projects that need a permit and warns that work done without a permit years ago may need one today. If you are unsure, call 209-862-3725, option 8, before starting.
Permit required
- Patio covers, attached or detached
- Sheds and other detached structures over 120 square feet
- Swimming pools and house additions
- Re-roofing
- HVAC units and water heaters, new or replacement
- Water softeners (non-salt conditioning units only)
- Plumbing work other than minor repairs or clearing stoppages
- All electrical work except replacing a receptacle or fixture
- Solar systems
No building permit
- Replacing a receptacle or light fixture
- Minor plumbing repairs and clearing stoppages
- Retrofit windows where no building paper is exposed and no framing changes
Two local rules catch homeowners out. Since January 1, 2023, a self-regenerating water softener that discharges into the city sewer may not be replaced with another one; only non-salt water conditioning units may be installed, under Newman City Code 11.06.060. And small accessory structures under 120 square feet with no electrical, mechanical or plumbing work still need a $60 zoning permit, as do fences under 6 feet.
What Newman decides and what the state holds
Newman sets its own zoning standards (setbacks, lot coverage, fence heights, accessory structure limits in City Code 5.23 and 5.25), its building permit fee schedule and its business license. Its design criteria sheet, written for the 2022 code cycle, lists a 90 mph wind speed with exposure C, seismic design category D0, a 1,500 psf soil bearing value unless a soils report justifies more, and no snow load.
Newman building department: who handles permitting
The City of Newman Building Department reviews plans, issues building, electrical, plumbing and mechanical permits and inspects work inside city limits. The Community Development (Planning) Department must approve accessory structures, ADUs and other projects before the Building Department will review them. The Finance Department takes permit payments and issues business licenses. Unincorporated land outside the city is permitted by Stanislaus County.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Building Department | City Hall, 2nd floor, 938 Fresno Street, Newman, CA 95360 |
| Phone and email | 209-862-3725, option 8; buildingdepartment@cityofnewman.gov |
| Counter hours | Monday to Thursday, 8:30 a.m. to noon; closed Fridays |
| Payments | In person by card or check, or a check mailed to P.O. Box 787, Newman, CA 95360, with the invoice; no phone payments |
| Business licenses | Finance Department, City Hall, 938 Fresno Street |
| Instant solar permits | Symbium portal for residential solar and batteries |
The city notes that its inspectors do not work only in Newman, which is why it cannot promise exact inspection times.
Newman permit types
Application forms are posted on the Building Department’s E-Docs page: residential and commercial building permit applications, separate short forms for panel upgrades and change-outs and for re-roofs, a revisions application, the owner-builder declaration, EV charging station checklists and the streamlined solar package. Pick the form that matches the project, then email it to the address printed at the top of the form or bring it to City Hall.
Residential permits
- Solar and batteries: residential rooftop solar and battery storage can be permitted instantly through Symbium, which checks the design against state and local rules, verifies the contractor’s license and business license and issues the permit without manual review.
- Accessory structures: structures over 120 square feet need a building permit under the city’s April 2026 guide. They must be 5 feet from rear and side lines (10 feet on a corner lot’s street side), 6 feet from other buildings except detached patio covers, no taller than 12 feet, and not in the front yard or driveway; all buildings may cover no more than 40% of the lot, and a lot may have no more than two detached accessory structures.
- ADUs: Newman, Stanislaus County and eight other cities in the county offer three free detached ADU plan sets of 405, 744 and 1,192 square feet, updated for the 2025 code and plan-checked by the county’s Building Division. A permit application still needs a site plan, solar plans for every new detached ADU, sprinkler plans if the main house is sprinklered, and a flood elevation certificate in a flood zone. ADUs follow City Code 5.23.040, with 5-foot side and rear setbacks and matching architecture, and need Planning approval first.
- Garage conversions: the city’s checklist asks for three copies of plans and a floor plan, removal of the garage door with a framing detail, wall insulation of R-13 or R-19 and R-38 in the ceiling, and egress windows and smoke and carbon monoxide alarms for any new bedroom.
Not sure this scope needs a permit?
Get a free quote →Building or remodeling a home here? Alliance handles home building permits, so the crew isn't waiting on the counter.
Commercial permits
New commercial buildings are priced per square foot by occupancy, from $0.22 for the largest warehouses to $1.66 for restaurants, with electrical, plumbing and mechanical work included; tenant improvements run $0.47 to $0.91 per square foot by size ($1.18 for restaurants). Commercial alterations needing six or more inspections are charged as tenant improvements. New businesses opening inside the city also pay a one-time $75 occupancy inspection fee with their business license, and the E-Docs page posts a business license inspection checklist.
For tenant improvements and new commercial builds, Alliance handles commercial permit filing through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning approval: accessory structures, ADUs and garage conversions are approved by Planning before the Building Department reviews them.
- Fences: side and rear fences may be 7 feet high if they stay out of the front yard and meet the street-side and corner setbacks in the city’s fence rules; front-yard fences are limited to 42 inches (or 4 feet for see-through fencing with staff approval), and corner-lot sight triangles to 36 inches.
- Flood zones: the Public Works flood information page offers flood zone determinations and lists properties with elevation certificates.
Newman building permit fees
The City of Newman Building Permit Fee Schedule took effect February 1, 2025. Plan check is 65% of the building permit fee (doubled for expedited review), and staff time is billed at $145 an hour for inspections and plan check and $37 an hour for processing. The schedule notes that its figures exclude state and impact fees.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| New one-story home or duplex, up to 1,580 sq ft | $1.31 per sq ft, plus $0.33 per sq ft of garage or covered patio |
| New home, 1,581 to 3,350 sq ft | $1.24 per sq ft, plus $0.33 per sq ft of garage or patio |
| New home, 3,351 sq ft and up | $1.11 per sq ft, plus $0.33 per sq ft of garage or patio |
| Two or more stories | Additional $0.05 per sq ft of the whole building |
| Plan check | 65% of the building permit fee; expedited review doubles it |
| Residential fire sprinklers | $517 |
| Residential addition | $1.31 per sq ft, $334 minimum including plan check |
| Residential remodel or fire damage repair | $334 minimum (worksheet) |
| Re-roof: tear-off with new sheathing / without / overlay | $300 / $227 / $227 |
| Water heater, HVAC change-out, panel change-out to 200 amps, demolition | $118 each |
| New HVAC unit | $226.75 |
| Roof-mounted solar: up to 2 / 3 to 5 / 6 or more inverters | $371.75 / $516.75 / $806.75 |
| Pool / pool and spa | $879.25 / $1,169.25 minimum |
| Patio cover, or shed or garage over 120 sq ft | $299.25 minimum |
| Zoning permit: shed under 120 sq ft or fence under 6 ft | $60 |
| Re-inspection / additional plan review | $145 per hour |
| Work under a red tag | Double the calculated permit fee |
Worked example: a new 1,800-square-foot one-story house with a 400-square-foot garage falls in the 1,581 to 3,350 band: 1,800 × $1.24 = $2,232, plus 400 × $0.33 = $132, for a $2,364 permit fee. Plan check at 65% adds $1,536.60, for $3,900.60 before fire sprinklers, state fees and development impact fees.
Business licenses are separate: $79 a year for a business inside the city plus a one-time $75 occupancy inspection fee, $79 a year for an out-of-town business such as a contractor, and $54 a year plus a one-time $25 fee for a home occupation.
Trade permits and who may pull them in Newman
Electrical, plumbing and mechanical permits are issued by the Building Department. Panel upgrades and change-outs have their own short application, as do re-roofs; for new homes and commercial buildings the electrical, plumbing and mechanical work is included in the square-foot fee. Solar contractors can use Symbium for instant residential permits.
The city’s accessory structure guide spells out who may apply: the property owner with a completed owner-builder form, or a California licensed contractor with a current City of Newman business license. Every business that works in the city, including contractors based elsewhere, needs a Newman business license from the Finance Department; licenses run on a July 1 to June 30 fiscal year, and new licenses taken out between April 1 and June 30 are prorated.
Rather not deal with the building department?
Get a free quote →How to apply for a Newman building permit
Accessory structures, ADUs and garage conversions go to Community Development first.
Download the matching application from the Building E-Docs page, plus the owner-builder declaration if you are the owner doing the work.
Email the application and plans to the address on the form, or bring them to City Hall, 2nd floor, Monday through Thursday mornings.
Over-the-counter jobs receive an invoice once the application is complete; plan-check jobs take about 10 days per reviewing department.
Pay in person by card or check, or mail a check with the invoice to P.O. Box 787.
Schedule inspections by phone or email at least a day ahead.
Review, corrections and what causes delay
Permits that need plan check, such as solar, patio covers and ADUs, usually take about 10 days in each department that reviews them, and the city says the time grows when many applications come in. Changes to approved plans need a revisions application and approval by the plan reviewers. An issued permit expires 12 months after issuance unless the Building Department grants an extension, and a finaled permit is closed, so later changes need a call to the department.
Newman building inspections
Schedule an inspection by calling 209-862-3725, option 8, or by email, at least one day ahead and no more than a week in advance; if you leave a voicemail or send an email, wait for confirmation that the inspection is booked. Inspections take place Monday through Thursday in a morning window (8 a.m. to noon) or an afternoon window (1 to 5 p.m.); exact times are not given because the inspectors also work outside Newman.
Have the issued permit, the approved plans and the city’s smoke and carbon monoxide alarm handout on site for the inspector to review and sign, and make sure the inspector can get to the work. Re-inspections are billed at $145 an hour.
California building code in Newman
The Building Department enforces the state codes along with Newman’s zoning rules in City Code chapters 5.23 and 5.25, and the free regional ADU plans were updated for the 2025 code. FEMA’s Community Status Book lists the City of Newman (community 060388) as participating in the National Flood Insurance Program, with flood maps effective August 24, 2021, and as a Community Rating System class 9 community, which gives eligible policyholders a 5% discount.
Want this handled start to finish?
Get a free quote →California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Newman permit search and official resources
The city’s pages offer no online permit lookup; questions about an existing permit, an expired permit or a closed permit go to the Building Department by phone or email. Flood zone determinations and the list of properties with elevation certificates are on the Public Works flood information page.
- Newman Building Department
- Building Department FAQs
- Building E-Docs (applications and handouts)
- Building permit fee schedule (effective February 1, 2025)
- Detached accessory structure guide (April 2026)
- Garage conversion requirements
- Building design criteria
- Pre-approved ADU plans
- Instant residential solar and battery permits
- Business license
- Flood information
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Newman building permit FAQs
How do I submit a permit application in Newman?
Email it to the address printed on the application or bring it to City Hall, 2nd floor, 938 Fresno Street, Monday through Thursday from 8:30 a.m. to noon.
How long does a permit take?
Over-the-counter permits such as HVAC change-outs and re-roofs are invoiced once the application is complete; plan-check permits usually take about 10 days in each reviewing department.
Do I need a permit for a shed?
Over 120 square feet, yes, a building permit. Under 120 square feet with no electrical, mechanical or plumbing work, a $60 zoning permit.
How high can my fence be?
Up to 7 feet at the side and rear, 42 inches in the front yard, with lower limits near street corners.
Can I replace my water softener?
Only with a non-salt water conditioning unit; replacing a self-regenerating softener that discharges to the city sewer has been prohibited since January 1, 2023.
When does my permit expire?
Twelve months after it was issued; contact the Building Department if you need an extension.
Are there free ADU plans?
Yes. Detached plans of 405, 744 and 1,192 square feet are available free, though you still need Planning approval and a building permit.
Does a contractor need a Newman business license?
Yes. Contractors based outside the city pay $79 a year.
Simplify Newman permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Newman sooner?
Let Alliance prepare, file, and track your Newman permits while your crew stays on the job.
More California permitting guides
Stanislaus County
Read guide →Patterson
Read guide →Riverbank
Read guide →Newport Beach Building Permit Guide
Read guide →Norco Building Permit Guide
Read guide →Norwalk Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Newman permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.