All of Mariposa County is unincorporated, so building permits everywhere in the county come from the Mariposa County Building Department, part of Development Services at the Government Center, 5100 Bullion Street, Mariposa ((209) 966-3934). Applications for building, planning, septic and well permits are filed in the county’s online Permit Center, and a parcel with an open code violation cannot get a permit except to fix that violation. Fees come from the Board-approved 2026 schedule; plan check for a single-family home takes about 7–10 working days.
What requires a building permit in Mariposa County?
The county enforces the 2025 California codes with its own amendments, and its “Do I Need a Permit?” handout lists the work that is exempt. Anything else, from new homes and remodels to conversions, changes of occupancy, manufactured home installation and grading, needs a permit.
No building permit
- One-story detached accessory buildings up to 120 sq ft with no water or power (they may still be regulated by the Wildland-Urban Interface Code)
- Fences up to 7 feet
- Retaining walls up to 4 feet from the bottom of the footing, with no surcharge
- Sidewalks and driveways
- Water tanks on grade up to 5,000 gallons
- Decks up to 200 sq ft and 30 inches above grade, not attached and not serving the exit door
- Painting, tiling, carpet, cabinets and countertops
Needs a permit
- Any structure supplied with water or power
- Remodels that move or add electrical, mechanical or plumbing fixtures or change the footprint or layout
- Re-roofing and re-siding
- Water heaters, HVAC, wood stoves and propane tanks
- Manufactured home installation and utilities
- Grading and solar systems
- Emergency repairs (apply by the next business day)
What the county decides and what the state holds
The Board of Supervisors adopts the county’s building fees, local amendments and land use rules. Since June 9, 2022, under Ordinance 1173 (County Code 15.10.260), the Building Department cannot accept an application, inspect or approve anything on a parcel with an existing violation unless the permit is to correct that violation. Zoning (Title 17) and subdivision rules (Title 16) form the county’s Development Code, which is being updated. Contractor licenses come from the state.
Mariposa County building department: who handles permitting
The U.S. Census lists no incorporated city or town in Mariposa County, so there is no city building department to send you elsewhere: the county Building Department is the permit office everywhere in the county, and its inspection route runs from Coulterville, Greeley Hill and Lake Don Pedro to Fish Camp, Wawona and Yosemite West. It sits in Development Services with the Planning Department and Environmental Health, all at the Government Center. Development Services is led by Director Greg Thompson.
Short on time to read all of this?
Get a free quote →| Office | Handles | Contact |
|---|---|---|
| Building Department | Building, grading and manufactured home permits; inspections | 5100 Bullion Street (PO Box 1268), Mariposa; (209) 966-3934; Mon–Fri 7 a.m.–4 p.m. |
| Planning Department | Zoning, land use, ADUs, use permits | 5100 Bullion Street; 209-966-5151; walk-in planner hours Mon–Fri 8 a.m.–noon |
| Environmental Health | Septic systems, wells, pools, food facilities | 5100 Bullion Street; 209-966-2220; Mon–Fri 8 a.m.–5 p.m. |
| Public Works | County road encroachments, special district applications | 4639 Ben Hur Road, Mariposa; 209-966-5356 |
| Caltrans | Driveways and work off a state highway | Apply at the Caltrans office |
If you are not sure whether a project needs Building, Planning or Environmental Health, Development Services takes questions at devservices@mariposacounty.org. The Permit Center map shows parcels, assessor parcel numbers and existing permits.
Mariposa County permit types
All permits are processed online. You create a Permit Center account with two-factor authentication, choose a permit or plan application, find the parcel on the map, and enter the project, parcel and contractor details. Required uploads are a complete plan set, an owner authorization form and a site plan. The portal does not auto-save, so save drafts often.
Residential permits
- New homes, additions and remodels go through plan check; the county also issues permits for conversions and changes of occupancy.
- Manufactured homes need an installation permit and a utilities permit; a foundation under an existing manufactured home has its own flat fee.
- ADUs. The county has no ADU ordinance of its own and follows state law; pre-approved ADU plan sets are available, and a junior ADU needs a recorded deed restriction before the final.
- Owner-built rural dwellings (LDRD), a proposed ordinance. The county’s Title 25 page says Mariposa County is proposing a Limited Density Owner-Built Rural Dwelling Ordinance (Chapter 15.40), which would let owners in specific zones build small homes without full compliance with the latest California Building Code; its information sheet also calls it proposed, and the posted ordinance has no number. The same page asks for LDRD applications through the portal, with a mandatory pre-application meeting, a topographic site plan, a geotechnical waiver, a grading worksheet and an owner liability form. As proposed, it covers owner-occupied rural homes outside the Mariposa, Coulterville and Midpines town planning areas, bans short-term rentals and needs at least 3,000 gallons of water storage. Ask the Building Department whether it has been adopted before you plan on it.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Commercial construction, remodels and changes of occupancy follow the same online process, with issuance fees of $176 for non-structural and $294 for structural permits. Commercial grading is $1,737, or direct cost or project valuation as the Building Official sets it, and commercial solar starts at $1,000 for systems up to 50 kW. Outside consultants used for plan check or inspection are billed at actual cost.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Code Enforcement and Planning review first. Every application is checked for unpermitted development and open code cases, then for zoning, before other agencies start their review.
- Septic and wells. Environmental Health permits new or repaired septic systems and new wells under the county septic ordinance and its Local Agency Management Program for onsite wastewater systems.
- Grading. A residential grading permit costs $499, and the county offers a $236 site review for grading questions.
- Roads, power and schools. County road encroachments are applied for at Public Works, state highway encroachments at Caltrans, and power with PG&E. School developer fees on habitable space are collected by Mariposa County Unified School District, or by Bass Lake Joint Union Elementary School District in its area.
Mariposa County permit costs and fees
Building fees are in the 2026 Board-approved fee schedule (Exhibit 1, dated November 26, 2025). A typical permit adds an issuance fee, a building permit fee and a plan check fee, each set from the project valuation tables, plus flat fees for specific work and the state fees.
| Item | Fee |
|---|---|
| Permit issuance, residential or commercial: non-structural / structural | $176 / $294 |
| Building permit fee, valuation $2,001–$25,000 | $559 plus $24.31 per $1,000 over $2,001 |
| Building permit fee, $50,001–$100,000 / $100,001–$500,000 | $1,119 plus $5.30 / $1,384 plus $0.89 per $1,000 |
| Plan check, $50,001–$100,000 / $100,001–$500,000 | $471 plus $4.71 / $707 plus $1.62 per $1,000 |
| Title 24 energy review | $294 |
| Flat-fee permits: water heater, HVAC, wood stove, propane tank, electrical blue tag | $323 |
| Re-roof or re-side / demolition | $323 each |
| Covered deck / uncovered deck | $442 / $383 |
| Manufactured home installation / utilities | $442 / $530 |
| Residential solar up to 15 kW | $450, plus $15 per kW above |
| Residential grading permit | $499 |
| Single-family fire sprinkler permit and plan check | $677 |
| Reinspection / after-hours inspection | $265 / $383 |
| Additional plan check | $176 per hour |
Rather talk it over?
Call 1-855-478-4290 →Worked example from the valuation tables: a new house valued at $200,000 pays a building permit fee of $1,384 plus 100 × $0.89, or $1,473, and plan check of $707 plus 100 × $1.62, or $869. With the $294 structural issuance fee that comes to $2,636; the $294 Title 24 energy review, trade fees and the state fees are added, and school fees are paid to the district.
Trade, septic and state fees
Electrical fees for a building run from $205 up to 500 square feet to $383 for 1,251 square feet and up, and plumbing from $205 for a half bath to $383 for three bathrooms; individual trade items such as a main service, sub-panel or water heater replacement are $205 each. Environmental Health’s fees, effective February 1, 2026, are $1,014 for a new or major septic repair permit and $608 for a new private well, each including a $131 Planning fee, with septic design plan check at $204 an hour. The state requires a $4 fee on every permit and a building standards fee of $1 per $25,000 of valuation, and the strong-motion (seismic) fee follows the state’s schedule. Fees are invoiced by email and paid in the Permit Center by e-check or card before the full review begins.
Trade permits and who may pull them
Electrical, plumbing and mechanical work is permitted by the Building Department, either as part of a building permit or as flat-fee permits for jobs such as water heaters, HVAC units, wood stoves and propane tanks. The electrical “blue tag” service inspection is made once the riser and panel are in place, and temporary construction power is inspected at the same stage.
- Applicants add contractors, architects or designers as contacts in the Permit Center, and an owner authorization form is required with every application.
- Electronic inspections are open to any licensed contractor in good standing with the Contractors State License Board who joins the county’s participation list: after a license and insurance check and a signed agreement, the contractor photographs each stage of re-roof, water heater, simple HVAC replacement and similar jobs and uploads the photos to the permit for approval. The county may still inspect within 10 business days, and contractors are removed for building without a permit, letting their license or insurance lapse, or unsafe work.
- Fire sprinklers for single-family homes are permitted and plan-checked by the county for $677, and other fire code reviews are billed at $118 an hour.
Rather not deal with the Mariposa County building department?
Get a free quote →How to apply for a Mariposa County building permit
Make sure the parcel has no open code case, because the county cannot accept an application otherwise unless it is to fix the violation.
Talk to Planning about zoning, Environmental Health about septic and wells, and Public Works or Caltrans about driveway encroachments.
Register with a personal email and two-factor authentication.
Choose the permit, find the parcel on the map, add contacts, and upload the plan set, owner authorization and site plan; sign electronically.
Fees are invoiced by email and must be paid before the full review starts.
Revision requests arrive by email and in the red attention box on your dashboard; correct and resubmit.
Review, corrections and what causes delay
Reviews run in order: completeness, payment, Code Enforcement (unpermitted development or code cases), Planning, then the other agencies, first come, first served. The county estimates about five to eight working days of plan check for signs and non-engineered minor projects and seven to ten working days for a single-family home. Unpaid invoices, open violations and the time you take to resubmit corrections all add to that; changed or re-corrected drawings are billed at $176 an hour.
Inspections in Mariposa County
Inspections are requested by phone at (209) 966-3934 between 7 a.m. and 4 p.m. on workdays, with at least 48 hours’ notice, and the approved plans must be on site. Inspectors cover the county on a weekly route:
- Tuesdays: Coulterville, Greeley Hill, Lake Don Pedro, Hornitos and Buck Meadows.
- Thursdays: Fish Camp, Wawona and Yosemite West.
- Mondays and Wednesdays: all other areas of the county.
An inspection is needed before any phase is covered by the next. For a new house the job card typically runs from under-slab electrical and plumbing and the foundation (with Ufer ground and setbacks) through bond beam, under-floor framing and insulation, roof nailing, rough framing and trades, insulation and sheetrock nailing, to the final gas test, the blue tag service and the final. Reinspections cost $265, and inspections outside normal hours $383 with a 2-hour minimum.
California building code in Mariposa County
The Board of Supervisors has adopted the 2025 California Building Standards Code with county amendments, and the county’s exemption handout notes that even permit-exempt sheds may still be regulated by the Wildland-Urban Interface Code. FEMA’s Community Status Book lists unincorporated Mariposa County (community 060634) in its section of communities not in the National Flood Insurance Program.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Want this handled start to finish?
Get a free quote →Mariposa County building permit FAQs
Who issues building permits in Mariposa County?
The county Building Department at 5100 Bullion Street, Mariposa ((209) 966-3934). The county has no incorporated cities, so it covers every community.
How much is a building permit for a new house?
On a $200,000 house the building permit fee is $1,473, plan check $869 and structural issuance $294, before the $294 energy review, trade and state fees and school fees.
Can I get a permit if my parcel has a violation?
No. Under Ordinance 1173, the county cannot accept an application, inspect or approve work on a parcel with an existing violation unless the permit is to correct it.
Do I need a permit for a small shed?
Not for a one-story detached shed up to 120 square feet with no water or power, though it may still be regulated by the Wildland-Urban Interface Code. Add water or power and it needs a permit.
How long does plan check take?
About five to eight working days for signs and non-engineered minor projects, and seven to ten working days for a single-family home, after Code Enforcement and Planning finish their reviews.
How do I schedule an inspection?
Call (209) 966-3934 between 7 a.m. and 4 p.m. on workdays, at least 48 hours ahead; your area’s inspection day depends on the weekly route.
Who handles septic systems and wells?
Mariposa County Environmental Health (209-966-2220). A new or major septic repair permit is $1,014 and a new private well permit $608, including the Planning fee.
Mariposa County permit search and official resources
Applications, permits and property records can be searched in the Permit Center, which also shows parcel maps and the day’s scheduled inspections. The Building Department posts lists of issued permits on its website, and its fee schedule lists a $7 charge for a research request.
Inspections are where schedules slip.
Get a free quote →- Mariposa County Building Department
- Development Services Permit Center
- Permit Center quick reference guide
- Do I need a permit? (2025 code)
- Building Department common questions
- Approximate fees and state fees
- 2026 Board-approved building fees
- Electronic inspections for contractors
- Title 25 owner-built rural dwelling ordinance (proposed)
- LDRD information sheet
- Planning Department
- Accessory dwelling units
- Environmental Health
- Septic systems
- Environmental Health fees, effective February 1, 2026
- Public Works
- Building Department staff directory
- 2025 California Title 24 building standards
- FEMA Community Status Book, California
Simplify Mariposa County permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Mariposa County sooner?
Let Alliance prepare, file, and track your Mariposa County permits while your crew stays on the job.
More California permitting guides
Madera County
Read guide →Merced County
Read guide →Stanislaus County
Read guide →Martinez Building Permit Guide
Read guide →Marysville Building Permit Guide
Read guide →Maywood Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Mariposa County permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.