In Malibu, building permits come from the City’s Building Safety Division, part of the Community Development Department at City Hall, 23825 Stuart Ranch Road (310-456-2489). Every project starts with Planning: the entire city lies in the California coastal zone, so work needs Planning approval, a coastal development permit or an exemption under the Local Coastal Program before Building Safety plan check. Applications, fees and inspection requests run through the Malibu Development Portal, and the FY 2026-27 fee schedule, in effect since September 11, 2026, charges $2.48 per square foot for plan check and $2.51 per square foot for the permit on new residential construction.
What requires a building permit in Malibu?
Building Safety issues building, mechanical, electrical, plumbing, pool and spa, and excavation permits, and the City’s building checklists cover new single-family homes, residential additions and remodels, accessory structures, pools and spas, retaining walls, grading and drainage, commercial buildings and tenant improvements. Cosmetic upgrades such as floor tile, paint and window coverings need no permit.
Permit needed
- New homes, additions and remodels (fees scale with the share of the house affected)
- Decks, balconies, patio covers, cabanas and carports
- Re-roofs, re-stucco and window or door change-outs
- Pools, spas and post-fire pool repairs
- Retaining walls, masonry walls and grading
- Generators, battery systems, solar and EV chargers
- Septic (onsite wastewater) work, reviewed by the City’s Environmental Health staff
Listed as exempt
- Floor tile, paint and window coverings
- One-story sheds or playhouses up to 120 sq ft and 12 ft high
- Fences up to 6 ft that are not pool barriers
- Retaining walls up to 4 ft from footing to top, with no surcharge
- Water tanks on grade up to 5,000 gallons
The exempt list comes from a City handout headed “2014 County of Los Angeles Building Code with Amendments”, so treat it as a guide and confirm with Building Safety. It also warns that work exempt from a building permit may still need Planning or other agency approval, which in Malibu often means a coastal development permit exemption.
What Malibu decides and what the state holds
Malibu controls zoning and coastal permitting under its Local Coastal Program, which the California Coastal Commission certified in 2002 and which overrides the General Plan and Zoning Code where they conflict. The City also sets its own fees, runs its own septic program, and its Building Safety page points applicants to the Los Angeles County codes. Construction standards are the state’s Title 24 codes, and contractor licenses come from the state. The City lists its design factors as Climate Zone 6, 94 mph wind with exposure C or D, 2.0 inches of rain per hour, Seismic Design Category D or higher, and a Very High Fire Hazard Severity Zone; a City news item from August 2026 notes that all of Malibu is in that zone.
Short on time to read all of this?
Get a free quote →Malibu building department: who handles permitting
The City of Malibu issues all building permits within its limits through the Building Safety Division; the Community Development Director, Yolanda Bundy, heads the department. Planning, Environmental Health (septic), Geology and Coastal Engineering, and Public Works each review and stamp plans, while the applicant takes plans to outside agencies: the Los Angeles County Fire Department, Los Angeles County Waterworks District 29 and, for commercial projects, the County Health Department.
| Detail | Information |
|---|---|
| Office | Building Safety Division, Malibu City Hall, 23825 Stuart Ranch Road, Malibu, CA 90265-4861 |
| Phone and email | 310-456-2489 (Building Safety ext. 259); Mbuilding@malibucity.org |
| Counter hours | Monday to Friday, 8 a.m. to 4 p.m.; closed Wednesdays 12 to 1:30 p.m.; appointments for other times |
| Online | Malibu Development Portal (applications, fees, corrections, inspections) |
| Planning | MPlanning@malibucity.org; 310-456-2489 ext. 485 |
| Environmental Health (septic) | ext. 390; walk-ins Tuesday and Thursday, 9 a.m. to 12 p.m. |
| LA County Fire plan check | 26600 Agoura Road, Calabasas; 818-880-0341 |
Malibu permit types and what comes first
Malibu issues no combination permits: building, mechanical, plumbing and electrical work each get their own permit. A registered account is needed for the portal, except that a guest may apply for a Rapid Permit, which covers seismic gas shut-off valves and water heater replacements. The City also publishes streamlined permit forms for generators, HVAC, tenant improvements and window and door change-outs.
Residential permits
New homes, additions, remodels, accessory structures, pools and retaining walls each have a Building Plan Check Submittal Checklist. Owners building their own projects sign the City’s Owner/Builder Acknowledgement, and the forms list includes neighbor notification and response forms, a structural observation report and a pool installation certificate. Roof-mounted solar needs no Planning review, while ground-mounted solar does.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial projects and tenant improvements use their own checklists, and the City posts its disability-access notice for commercial permit applicants in seven languages. Express Tenant Improvement plan check appointments are held at City Hall on Wednesdays only and are cancelled if the applicant is more than 10 minutes late or missing documents. Commercial projects also go to the County Health Department.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Planning and coastal review. Planning reviews the project first and issues the “green stamp”; depending on scope this is an over-the-counter permit, an administrative plan review, or a coastal development permit decided by the Planning Director or the Planning Commission, with appeals to the City Council and, in some cases, the Coastal Commission.
- Geology and coastal engineering. Geotechnical and coastal engineering reports are reviewed under the City’s guidelines, including wave uprush reports.
- Septic. Where the property uses an onsite wastewater (septic) system, Environmental Health checks whether an existing system can take the new flows or reviews a new one.
- Fire, water and right of way. LA County Fire and Waterworks District 29 clearances, a City encroachment permit for work in the public right of way, and a Caltrans permit for work along Pacific Coast Highway.
- Flood zones. Public Works reviews work in a FEMA flood zone; some projects must elevate above the base flood elevation and file an Elevation Certificate.
Malibu permit fees
Malibu’s Schedule of Fees for fiscal year 2026-27 was adopted by the City Council on July 13, 2026 and took effect on September 11, 2026, raising most fees by 2.9%. Building fees are set per square foot for new work, as a share of the new-construction fee for remodels, and as flat plan check and permit amounts for itemized work.
| Item | Fee |
|---|---|
| New residential construction and additions | Plan check $2.48 per sq ft; permit $2.51 per sq ft (2-hour minimum) |
| Residential remodels | 40% to 60% of the new-residential fee, depending on whether the work is minor or major and structural or not |
| Non-residential / tenant improvement under 5,000 sq ft | $1.06 + $1.90 per sq ft / $0.50 + $0.76 per sq ft |
| Re-roof under 30 squares and under 5.9 lb per square | $548 permit |
| Residential pool under 800 sq ft (with MEP) | Plan check $561; permit $1,096 |
| Grading, 1–50 cubic yards | Plan check $254; permit $1,096 |
| Electrical, new single- or two-family home | $0.31 per sq ft |
| Hourly building plan check | $254 per hour |
| Technology enhancement | 5.12% of the building permit fee |
| General Plan maintenance | 0.18% of valuation |
| Art in Public Places in-lieu contribution | 1% (impact fee) |
| School processing fee (Santa Monica-Malibu Unified) | $69 |
| Work without a permit / temporary certificate of occupancy | $548 / $548 |
| Permit time extension | $411 |
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Over-the-counter permit, Level I / Level II | $447 / $637 |
| Administrative plan review, minor | $3,527 |
| Coastal development permit: accessory structures, second units, additions | $13,244 |
| Coastal development permit: new single-family home | $22,211 |
| De minimis waiver (septic or driveway) | $6,416 |
| Rebuild Development Permit | $3,527 |
| Final Planning approval (“red stamp”) | $541 |
| Geology review, single-family home (standard / complex) | $4,113 / $6,023 |
| Coastal engineering, standard project review | $1,876 |
| Septic (OWTS) review, complex: planning / building phase | $3,085 / $2,203 |
Example from the schedule. For a new 2,500-square-foot house, building plan check is 2,500 × $2.48 = $6,200 and the building permit is 2,500 × $2.51 = $6,275, plus the 5.12% technology fee on the permit ($321.28), for $12,796.28 before the 0.18% General Plan fee on valuation, the per-square-foot electrical fee, plumbing and mechanical items, state surcharges, and Planning, geology, septic and coastal review.
Trade permits and who may pull them
Electrical, plumbing and mechanical permits are separate permits applied for in the same portal, priced from itemized tables (for example $69 per water heater, $137 for a gas system of up to five outlets, $274 for a split system, and $69 per set of 20 outlets or fixtures). Mechanical, electrical and plumbing plan check is billed at $254 an hour where plans are needed, and the City publishes MEP requirement sheets for residential and non-residential projects.
Permits may be obtained by the property owner or a licensed contractor; an agent may pull them with a notarized letter of authorization from either. Owner-builders complete the City’s acknowledgement form, and contractors need the state license for their trade. Once fees are paid, the permit is created and sent by DocuSign to the contractor named on the application. On business licenses, the City has adopted the Los Angeles County Code, so licensable businesses apply to the County Business License Office (213-974-2011).
Rather not deal with the building department?
Get a free quote →CALGreen and the City require construction and demolition projects to recycle or reuse at least 65% of their waste, with a recycling report and haul tickets at the end, and only haulers on the City’s 2026-27 permitted hauler list may serve Malibu jobs.
How to apply for a building permit in Malibu
Create an account; Planning staff first decide whether the project is exempt from Planning review.
Submit the Planning application, upload the documents on the checklist staff provide, pay the fees and work with the assigned case planner until the project receives its green stamp.
Under the Building Safety tile choose New Application, put “plan check” in the project description and upload the plans and reports on the matching City checklist.
A permit technician checks the upload; pay plan check fees online or at City Hall and follow department reviews under Review Projects.
Take the plans to LA County Fire, Waterworks District 29 and, for commercial work, County Health while City departments review.
Use Plan Check Resubmittal and send everything only once all departments’ corrections are addressed.
Building Safety stamps first and Planning last; then submit a Permit Application for each trade and pay the permit fees.
Review, corrections and what causes delay
The City asks applicants not to resubmit until every department’s corrections have been addressed, outside-agency approvals are the applicant’s job, and coastal development permits decided by the Planning Commission need a public hearing. Planning charges $2,086 for each coastal development permit resubmittal after the third, and building plan check bills a third review at $254 an hour. An unused plan check or permit expires; the City sells extensions ($274 for a plan check application, $411 for a permit), and issued permits expire 365 days after issuance or after 365 days without work.
Inspections in Malibu
Every permitted project needs City inspections. Request them through the online inspection request form or the Schedule Inspection tile in the portal, giving the site address, permit number, type of inspection, date, contact name and phone number; a confirmation arrives by email and an estimated arrival time is emailed on the day. If no email has arrived by 9 a.m., call 310-456-2489. Inspectors must be given access to the property between 8 a.m. and 5 p.m., and they hold counter hours from 7:30 to 8:30 a.m. on weekdays.
Construction is allowed from 7 a.m. to 7 p.m. on weekdays and 8 a.m. to 5 p.m. on Saturdays, never on Sundays or City holidays. Before final sign-off and a certificate of occupancy, the City’s Final Sign Off Checklist lists the department and agency approvals to collect, and septic systems get their own inspection and, afterward, an operating permit from Environmental Health.
Want this handled start to finish?
Get a free quote →Building code in Malibu
Malibu’s Building Safety pages link to the Los Angeles County codes and its septic program applies County Title 28 (plumbing) along with Malibu Municipal Code Chapters 15.40 to 15.44. FEMA lists Malibu as a participating community in the National Flood Insurance Program, with the revised coastal flood maps that took effect on April 21, 2021.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Frequently asked questions
Who issues building permits in Malibu?
The City’s Building Safety Division in the Community Development Department, at City Hall, 23825 Stuart Ranch Road. Los Angeles County Fire, Waterworks District 29 and, for commercial work, County Health review plans separately.
Do I need a coastal development permit?
All of Malibu is in the coastal zone, so development needs a coastal development permit unless Planning finds it exempt. Planning reviews the project before any building plan check.
How much does a building permit cost in Malibu?
For new residential space, $2.48 per square foot for plan check and $2.51 per square foot for the permit, plus a 5.12% technology fee and other charges under the FY 2026-27 schedule effective September 11, 2026.
Can a homeowner pull a permit?
Yes. The owner or a licensed contractor may obtain permits, and an agent may do so with a notarized authorization letter. Owner-builders sign the City’s acknowledgement form.
Does Malibu issue combination permits?
No. Building, mechanical, plumbing and electrical work each need a separate permit.
Do I need a permit to paint or retile?
No. Floor tile, paint and window coverings are cosmetic work that the City says needs no permit.
Who handles septic systems?
The City’s own Environmental Health staff review onsite wastewater systems and issue operating permits; start an OWTS plan check by emailing them.
When do permits expire?
Within 365 days after issuance, or if work stops for 365 days. A permit time extension costs $411.
Malibu permit search and official resources
Past building permits, geology reports and septic approvals can be searched in the City’s OnBase public records system, and current projects in the Development Portal. Planning also holds Los Angeles County Assessor building records, released to the owner with identification or to an agent with a notarized letter.
Inspections are where schedules slip.
Get a free quote →- Building Safety Division
- Development Portal instructions
- Building applications, checklists and forms
- FY 2026-27 Schedule of Fees (PDF)
- City fee schedule page
- Work exempt from building permits (PDF)
- Building inspections
- Planning and the development process
- Local Coastal Program
- Environmental Health and septic systems
- Public Works encroachment permits
- Floodplain management
- Public records and OnBase
- California Building Standards Commission
Simplify Malibu permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Malibu sooner?
Let Alliance prepare, file, and track your Malibu permits while your crew stays on the job.
More California permitting guides
Los Angeles County
Read guide →Maywood
Read guide →Montebello
Read guide →Manhattan Beach Building Permit Guide
Read guide →Manteca Building Permit Guide
Read guide →Marin County Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Malibu permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.