In La Palma, building permits are issued by the city’s Building and Safety Division in the Community Development Department at City Hall, 7822 Walker Street (714-690-3340). The city contracts its building and safety services, including plan check, to Bureau Veritas North America, Inc. Permits are applied for and issued on the city’s OpenGov portal, and inspections run Monday to Thursday mornings. Fees follow Resolution No. 2024-20, a valuation table plus percentage plan check charges; a 300 sq ft patio cover is valued at $4,500 and carries a $170.70 permit fee.
What requires a building permit in La Palma?
The Building and Safety Division says almost all improvement plans need plan check before a permit is issued. Its fee schedule and handouts show the work it permits: new buildings and additions, tenant improvements, patio covers and enclosures, block walls and retaining walls, re-roofs, swimming pools and spas, pool demolition, building demolition and relocation, signs, and electrical, plumbing and mechanical work. Solar photovoltaic systems take both a building and an electrical permit.
Residential work with city handouts
- Attached and detached patio covers
- Block walls, including walls on a shared property line (with a common wall agreement)
- Electrical panel change-outs, load calculations and EV equipment
- Window and door replacement
- Pools and spas (barrier form and conditions of approval) and pool demolition
- Smoke and carbon monoxide alarms on permitted work
Commercial work
- Tenant improvements, with three full plan sets including electrical, mechanical and plumbing
- Grease interceptors (city standard detail)
- EV charging stations under the city’s EV Charging Ordinance 2023-02
- Disability access upgrades, with an ADA hardship exception form
- A Certificate of Compliance and Occupancy before a new business license
For a small job where it is unclear whether a permit is needed, the division’s 7:30 to 8:30 a.m. inquiry hour, email to building@lapalmaca.gov or a call to 714-690-3340 is the quickest way to ask.
What La Palma decides and what the state holds
The city adopted the 2025 California codes with local amendments in Ordinance 2025-02 (building codes) and Ordinance 2025-03 (fire code), now codified in Article III of Chapter 10 of the Municipal Code. Ordinance 2025-02 also adopts the International Property Maintenance Code and the Uniform Code for the Abatement of Dangerous Buildings. Its findings on local climate, geology and topography were adopted by resolution (No. 2025-43) on October 7, 2025, the day the ordinance was introduced at a public hearing, and the City Council adopted Ordinance 2025-02 on November 4, 2025. Contractor licenses come from the state; the city requires a local business license.
Short on time to read all of this?
Get a free quote →La Palma building department: who handles permitting
The city’s Building and Safety Division issues permits for all property inside La Palma. It handles pre-construction consultation, plan check, inspections, stop-work and correction notices, water quality best management practices on construction sites and certificates of occupancy. The city contracts these building and safety services to Bureau Veritas North America, Inc.; the permits themselves are city permits issued through the city’s portal and counter. Fire review is done by the Orange County Fire Authority and food facility review by the Orange County Health Care Agency, each with its own plan check fee.
| Detail | Information |
|---|---|
| Office | Building and Safety Division, Community Development Department, City Hall, 7822 Walker Street, La Palma, CA 90623 |
| Phone / email | 714-690-3340; building@lapalmaca.gov |
| Counter hours | Monday to Thursday: walk-in 7:30 a.m. to noon, by appointment 1:00 to 6:30 p.m.; closed Fridays |
| Code questions | 7:30 to 8:30 a.m., Monday to Thursday, or by email or phone |
| Planning Division | 714-690-3336 |
| Business licenses | 714-690-3342 |
| Contract building services | Bureau Veritas North America, Inc. |
La Palma permit types
Building and safety permitting and inspections run on the city’s OpenGov portal, and Planning applications are filed there as well. The fee schedule shows the record types the division issues: building, electrical, plumbing and mechanical permits, demolition and relocation permits, sign permits and grading permits.
Residential permits
The division publishes residential plan submittal requirements, a site plan guide, design limitations and handouts for common projects. Pool and spa permits come with conditions of approval: the pool contractor draws a site plan showing stockpiles for dirt and Gunite or Shotcrete, truck parking and the excavation access route, and a $1,173.22 swimming pool bond is held as a deposit. Owners who act as their own builder complete the city’s property owner’s package before a permit is issued.
Building or remodeling a home here? Alliance handles residential permit applications, so the crew isn't waiting on the counter.
Commercial permits
Tenant improvements need three complete plan sets with a vicinity map, a site plan showing and counting parking, building data, occupancy and construction type, the accessible path of travel from the sidewalk or parking, floor plans, wall and door details and electrical, mechanical and plumbing plans; energy forms are required for new lighting or when more than half of the lighting changes. Every non-residential business needs a building permit application and Certificate of Compliance and Occupancy to confirm zoning and building compliance, and qualifying food businesses also need a fats, oils and grease permit, before the city issues the business license. Restaurants need a county health permit, which uses a combined AQMD and fire authority form.
Not sure this scope needs a permit?
Get a free quote →For tenant improvements and new commercial builds, Alliance handles commercial building permits through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning. The Planning Division processes conditional use permits ($3,022), precise plans, residential and commercial remodels, signs, temporary uses and design review, and takes projects to the Development Committee and City Council.
- Water quality. Priority projects file a Water Quality Management Plan and smaller ones a non-priority project water quality plan; landscapes follow the state water-efficient landscape rules.
- Fire and health. Plans needing Orange County Fire Authority or Health Care Agency review are submitted directly to those agencies.
- School fees. Residential additions over 500 sq ft, new homes and new commercial or industrial space pay school fees first and return the certificate of payment to the Building Department.
La Palma permit fees
The fee schedule linked from the Building and Safety page is Resolution No. 2024-20, adopted by the City Council on June 4, 2024 and effective July 1, 2024 (Exhibit B, Schedule No. 1, the 2024-25 Building and Safety Fee Schedule). Building permit fees come from a valuation table, with value based on current ICC building valuation data or the bid. For common projects the schedule fixes the value per unit, and plan check is a percentage of the permit fee.
| Item | Fee |
|---|---|
| Value $2,001 to $25,000 | $106.23 plus $21.49 per $1,000 over $2,000 |
| Value $25,001 to $50,000 | $600.42 plus $15.50 per $1,000 over $25,000 |
| Value $50,001 to $100,000 | $987.86 plus $10.74 per $1,000 over $50,000 |
| Value $100,001 to $500,000 | $1,524.68 plus $8.60 per $1,000 over $100,000 |
| Building plan check / energy plan check | 65% / 20% of the total permit fee |
| General Plan maintenance fee | 5% of the permit fee |
| Permit issuance fee (building, electrical or plumbing) | $36.12 each |
| Set valuations | Tenant improvements $32 per sq ft; patio cover $15 per sq ft; patio enclosure $18 per sq ft; pool or spa $50 per sq ft; re-roof $120 per square |
| Block wall (6 ft or less) / over 6 ft or retaining wall | Valued at $32 / $60 per linear foot |
| Building demolition permit | $353.68 |
| Re-inspection / special inspection | $62.60 / $266.08 |
| Temporary certificate of occupancy | $101.74 |
| Construction and demolition recycling deposit | $186.00 (at least 65% recycled) |
Rather talk it over?
Call 1-855-478-4290 →Trade items include $231.77 for a 200-amp electrical service, $0.29 per sq ft of new residential electrical, $43.95 per plumbing fixture or trap, $36.12 for a water heater and vent, $159.67 for a building sewer and $70.43 plus $3.22 per fixture for a house repipe or gas piping system; plumbing plan check is also 65% of the permit fee. Grading fees follow the tables of the 1998 Uniform Building Code, and geotechnical, water quality and stormwater plan reviews are billed at $110 an hour against a $1,500 minimum deposit.
Worked example: a 300 sq ft patio cover is valued at $15 per sq ft, or $4,500. That falls in the $2,001 to $25,000 band: $106.23 plus three $1,000 steps (the $2,500 above $2,000 counts as three, since a fraction counts as a full step) at $21.49, for a permit fee of $170.70, plus the $36.12 issuance fee and the percentage plan check, energy and General Plan charges.
Trade permits and who may pull them in La Palma
Electrical, plumbing and mechanical permits are issued by Building and Safety on the same portal, each with its own $36.12 issuance fee, and a solar installation needs both a building and an electrical permit. Smaller trade jobs such as a panel change-out follow the division’s handouts; larger ones go through plan check with the building permit.
- Contractors need a La Palma business license even when their office is outside the city. The city applies its contractor category to holders of a state A or B general license and of C-2 to C-61, ASB or HAZ specialty licenses, and contractors apply for it on OpenGov.
- Owner-builders must read, initial and sign the city’s owner-builder acknowledgment before the permit is issued. An agent cannot sign that notice for the owner without the city’s prior approval.
- Agents filing Planning applications for an owner use the city’s property owner certification and agent authorization form.
Rather not deal with the building department?
Get a free quote →The owner-builder package also warns that an owner who engages workers other than licensed contractors may be considered an employer under state and federal law, with payroll tax, workers’ compensation and other duties that come with it.
How to apply for a La Palma building permit
Ask Planning (714-690-3336) whether the project needs a planning approval, and read the design limitations handout.
Use the residential or tenant improvement submittal list; plan check starts with three plan sets and the plan check fee.
Create an account, choose the record type and upload the plans and forms, or get help at the City Hall counter.
Where needed, submit separate plan sets and fees to the Orange County Fire Authority or Health Care Agency.
The contract plan reviewers return comments; revise and resubmit until approved.
Pay permit fees, school fees and any deposits, and file the owner-builder package if you are your own builder.
The permit is issued digitally on the portal.
Review, corrections and what causes delay
Plan check cannot start until the plan sets and plan check fee are in, and a project that also needs fire or health approval waits on those agencies’ own reviews. School fee certificates must be returned to the Building Department before issuance, and businesses moving into a space cannot get a business license until the Certificate of Compliance and Occupancy is complete.
Inspections in La Palma
Building inspections are done Monday to Thursday, 8:30 a.m. to noon; the city is closed on Fridays. Schedule on the OpenGov portal, generally with 24 hours’ notice. If you call 714-690-3340 before 8:30 a.m., the division may be able to fit in a same-day inspection. Depending on the inspection, the owner or contractor may need to be present.
A re-inspection costs $62.60 and a special inspection $266.08. Pool jobs follow the conditions of approval for staging materials and access, and the pool barrier form covers the required safety barrier. The division issues certificates of occupancy at the end of the job; a temporary certificate is $101.74.
California building code in La Palma
La Palma enforces the 2025 California Building Standards Code, including the 2025 California Fire Code, as amended by Ordinances 2025-02 and 2025-03. Some older handouts, such as the tenant improvement checklist, still print earlier code years in their plan notes. FEMA’s Community Status Book lists La Palma (community 060225) as participating in the National Flood Insurance Program, with no special flood hazard area mapped in the city.
Want this handled start to finish?
Get a free quote →California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
La Palma building permit FAQ
Who issues building permits in La Palma?
The city’s Building and Safety Division at City Hall, 7822 Walker Street. Plan check and inspection services are provided under contract by Bureau Veritas North America, Inc.
Can I apply online?
Yes. Building permits and inspections run on the city’s OpenGov portal, and permits are issued digitally. Staff help at the City Hall counter Monday to Thursday.
How much does a permit cost in La Palma?
It depends on value. Under Resolution 2024-20 a $4,500 project, such as a 300 sq ft patio cover, has a $170.70 permit fee before the $36.12 issuance fee and percentage plan check charges.
Is City Hall open on Fridays?
No. The counter is open Monday to Thursday, with walk-ins from 7:30 a.m. to noon and appointments in the afternoon, and inspections are not done on Fridays.
Do contractors need a La Palma business license?
Yes. Contractors with offices outside the city still need a La Palma business license to work in the city.
Which school district do I pay?
The city’s school fee map sends sites north of Houston Avenue to the Fullerton Union High School District (the name the map uses) and sites south of Houston Avenue to the Anaheim Union High School District.
Is La Palma in a flood zone?
FEMA lists the city as a participating community with no special flood hazard area mapped.
La Palma permit search and official resources
Permit records, plan reviews and inspection results are kept on the city’s OpenGov portal, where applicants follow their own records. For older permits or plans, contact the Building and Safety Division at 714-690-3340 or building@lapalmaca.gov.
Inspections are where schedules slip.
Get a free quote →- La Palma Building and Safety Division
- Permits and inspections
- OpenGov permit portal
- Fee schedule, Resolution 2024-20 (PDF)
- Ordinance 2025-02, building codes (PDF)
- Ordinance 2025-03, fire code (PDF)
- Planning Division
- Business licenses
- School fees map (PDF)
- Owner-builder package (PDF)
- Tenant improvement checklist (PDF)
- Pool and spa permit conditions (PDF)
- Solar energy information
- Community Development Department
Simplify La Palma permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in La Palma sooner?
Let Alliance prepare, file, and track your La Palma permits while your crew stays on the job.
More California permitting guides
Orange County
Read guide →Laguna Hills
Read guide →Laguna Niguel
Read guide →La Puente Building Permit Guide
Read guide →La Quinta Building Permit Guide
Read guide →La Verne Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about La Palma permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.