Building permits in the City of Hawaiian Gardens come from the Building and Safety Division of the Community Development Department at City Hall, 21815 Pioneer Boulevard (562-420-2641). The division’s office is open Monday, Tuesday and Thursday from 8 a.m. to noon and 4 to 5 p.m., inspections run 1 to 4 p.m. on those days, and appointments are booked through Buildingtech@hgcity.org. Permit fees are the Los Angeles County building, electrical, plumbing and mechanical fees multiplied by 1.30, and many re-roofs, water heaters, A/C change-outs and similar jobs are express permits with no plan check.
What requires a building permit in Hawaiian Gardens?
The Building and Safety Division enforces the California Building Code for all construction in the city. Its rule is broad: no building or structure may be built, enlarged, altered, repaired, moved, improved, converted or demolished without first getting a building permit, and each building or structure needs its own permit. The single Building Permit Application covers building, mechanical, electrical, plumbing and grading approvals. The city’s express-permit bulletin (B-005, effective January 5, 2015) lists the work that is permitted without a plan check:
Express: building
- Re-roofs and re-stucco
- New or replacement exterior siding on residential walls 5 feet or more from property lines
- Masonry walls built to bulletin B-002 and retaining walls built to bulletin B-003, with a site plan
- Attached patio covers 5 feet or more from property lines at houses, with a site plan
- Change of owner or contractor on a permit
Express: trades
- Replacing or adding plumbing fixtures and replacing water heaters
- Sewer caps, sewer connections and sewer repairs
- Low-pressure gas piping with up to 10 outlets and earthquake valves
- Replacing A/C units of the same size and type, or adding A/C of 5 tons or less
- Non-engineered wiring under 600 volts and up to 400 amps in existing homes, offices and shops, including EV charging at single-family homes
Prefabricated fireplaces appear on the express list, but the bulletin adds that they still need a separate building plan check and permit. New homes, residential additions and alterations, new commercial buildings and tenant improvements have their own submittal lists for plan check. The division posts no list of work that is exempt from permits, so ask at the counter before starting small work.
What Hawaiian Gardens decides and what the state holds
The city sets its fee formula (the county’s current fee times 1.30), its express-permit list, its construction and demolition recycling rules with an exclusive hauler, its business license tax, a streamlined process for EV chargers adopted by Ordinance No. 2023-612 on August 8, 2023, and planning review through plot plan, design and discretionary applications. The building code itself is the state’s, and contractors hold state licenses.
Hawaiian Gardens building department: who handles permitting
The City of Hawaiian Gardens issues building permits inside city limits through its own Building and Safety Division, part of the Community Development Department. The department reviews development proposals, issues building permits, inspects new construction and enforces the municipal code; the division itself provides plan review, permits and field inspections. Fire prevention for the city comes from the Los Angeles County Fire Department, whose Cerritos fire prevention office serves Hawaiian Gardens.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building and Safety Division, City Hall, 21815 Pioneer Boulevard, Hawaiian Gardens, CA 90716 |
| Division office hours | Monday, Tuesday and Thursday, 8 a.m. to noon and 4 to 5 p.m. |
| Inspection hours | Monday, Tuesday and Thursday, 1 to 4 p.m. |
| Community Development counter | 8 a.m. to 5 p.m., 562-420-2641 |
| Inspections and over-the-counter plan checks | 562-420-2641, ext. 224 |
| Appointments and solar submittals | Buildingtech@hgcity.org |
| County fire prevention | Cerritos office, 19030 Pioneer Blvd., Cerritos; 562-860-8014 |
Hawaiian Gardens permit types
One Building Permit Application is used for building, electrical, plumbing, mechanical and grading work, and the division supports it with a set of numbered bulletins: construction bulletins B-001 to B-027, accessibility bulletins A-001 to A-10, a photovoltaic bulletin (E-002) and a fire separation distance bulletin (F-001).
Residential permits
- Additions and alterations follow the residential alteration and addition submittal list (B-009); new homes follow B-006. Bulletins cover setbacks (B-22), a sample site plan (B-021) and ceiling joist span tables (B-026).
- Patio covers, carports and walls: bulletins B-001 (attached patio cover or carport), B-002 (masonry walls) and B-003 (retaining walls 4 feet high or less) give standard details; work built to them is an express permit. A Block Wall Neighbor Agreement form is posted for walls on a shared line.
- Re-roofs, windows, water heaters and HVAC: bulletins B-015 (residential re-roofing), B-014 (wood shakes and shingles), B-025 (window change-outs), B-024 (water heaters) and B-023 (residential HVAC).
- Pools: bulletin B-016 covers backfilling a swimming pool; pool wiring is an express electrical permit.
- Rooftop solar: projects can use SolarAPP+ (automated review, then email the SolarAPP+ permit, checklist and single-line drawing to Buildingtech@hgcity.org) or the city’s streamlined process for systems no larger than 10 kilowatts AC on a single-family home or duplex, with the full package emailed and a $407.57 payment before processing. Los Angeles County Fire must final PV and battery storage systems before they are used (323-890-4125).
- EV chargers: the residential and non-residential EV checklist is submitted with the Building Permit Application under the streamlined process of Ordinance No. 2023-612.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Not sure this scope needs a permit?
Get a free quote →Commercial permits
New commercial or industrial buildings follow submittal list B-008, and tenant improvements follow B-010. A change of use with no construction is covered by B-011, and occupancy groups by B-012. Accessibility bulletins show the required details for parking, ramps, doors, restrooms, elevators and signage, with an unreasonable-hardship worksheet (A-001). Special inspectors check in with the job assignment form B-027. Newly constructed buildings, and tenant improvements over 1,000 square feet, must document proper disposal of universal waste such as fluorescent tubes, batteries and mercury thermostats.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
What comes before the building permit
- Planning review: the Development Application covers plot plan review, landscape review and design review; the Discretionary Application covers conditional use permits, variances, minor exceptions and minor use permits; the Land Use Application covers zone changes, specific plans and general plan amendments.
- Subdivisions: lot line adjustments, parcel maps and tract maps use the Subdivision Application.
- Signs: all new commercial signs need a Sign Permit Application, reviewed formally or at the counter.
- Temporary uses: the Temporary Use Permit Application covers encroachments, storage containers, outdoor sales and similar short-term uses.
- Waste plan: the construction and demolition recycling checklist starts with completing the C&D Waste Management Plan forms and submitting them to the Building Department.
Planning and building applications are filed with the Community Development Department during counter hours, with the fees and plans the application lists.
Hawaiian Gardens building permit fees
Hawaiian Gardens does not publish its own building fee tables. Its rule is that fees depend on the size and complexity of the project and are calculated from the Los Angeles County current fee multiplied by 1.30: Title 26 of the county code for building permits, Title 27 for electrical, Title 28 for plumbing and Title 29 for mechanical. The city page gives no adoption date for the factor. Los Angeles County Public Works posts its current fees for unincorporated areas, effective July 1, 2026, on its plan check and permit fee page; the rows below apply the city’s factor to some of those figures. The division calculates the final amount for each project.
Rather talk it over?
Call 1-855-478-4290 →| Item | County fee 2026-27 | Times 1.30 |
|---|---|---|
| Permit issuance fee (building, electrical or plumbing permit) | $41.35 | $53.76 |
| Inspection of a building demolition | $244.88 | $318.34 |
| Inspection of pool, spa or hot tub barriers | $137.95 | $179.34 |
| Inspection with no set fee, or outside normal hours, per hour | $147.02 | $191.13 |
| Certificate of occupancy / temporary certificate | $151.50 / $227.54 | $196.95 / $295.80 |
| Minimum plan check fee for a standard plan | $225.59 | $293.27 |
| Electrical, new single- or two-family home, per sq ft | $0.23 | $0.299 |
| Electrical, new private in-ground pool at a home | $121.52 | $157.98 |
| Plumbing fixture, or water heater and vent, each | $24.47 | $31.81 |
The building permit fee itself follows the county’s valuation table, which adds the issuance fee to every permit and sets a combined permit for a one- or two-family home with an attached garage at 1.6 times the building permit fee. The county also charges a plan maintenance fee of 2% of the building permit fee. Ask the division whether the factor applies to every line, including plan check and issuance, before budgeting.
| Item | Fee |
|---|---|
| Streamlined residential rooftop solar (10 kW AC or less), paid before processing | $407.57 |
| Contractor business license tax | $120 per year (includes all) |
| Business license application fee | Set by city resolution, not shown in the fee summary |
Solar processing fees are paid online or in person at the Community Development Department.
Trade permits and who may pull them in Hawaiian Gardens
Electrical, plumbing and mechanical permits are issued by the same division on the same application, priced from county Titles 27, 28 and 29 times 1.30. Most routine trade work is an express permit with no plan check: fixture and water heater replacement, sewer connections and repairs, low-pressure gas piping, HVAC systems under 500,000 Btu/h, exhaust fans up to 2,000 cfm and non-engineered wiring up to 400 amps in existing buildings.
Bulletin B-004 lists what is needed when the permit is issued. A contractor shows the original current State of California contractor’s license (or a notarized authorization naming an agent, plus identification), fills out the Workers’ Compensation Declaration and holds a current City of Hawaiian Gardens business license. An owner-builder initials each statement on the Owner’s Acknowledgment and Verification of Information form and fills out the Owner-Builder Declaration and the Workers’ Compensation Declaration. Someone acting for the owner needs those forms plus an Authorization of Agent, all with the owner’s notarized signature, and may be asked for identification.
Rather not deal with the building department?
Get a free quote →The contractor business license tax is $120 a year. Since October 6, 2025 the city’s business licenses run through HdL Companies: apply or renew online, or mail the application to the processing center at 8839 N. Cedar Ave. #212, Fresno, CA 93720. Support is at hawaiiangardens@hdlgov.com or 562-392-8084.
How to apply for a Hawaiian Gardens building permit
Ask the Community Development counter whether the project needs plot plan, design or discretionary review, and file that application first.
Use the submittal list for the job (B-006, B-008, B-009 or B-010) or the standard detail for a patio cover, wall or re-roof.
Complete the Building Permit Application and, for demolition or construction waste, the C&D Waste Management Plan form.
Bring plans to the division during office hours; book an over-the-counter check for minor plans through ext. 224 or Buildingtech@hgcity.org.
Contractors bring the state license, workers’ compensation declaration and city business license; owner-builders sign the owner forms.
Pay the county-based fees and receive the permit before work starts.
Call 562-420-2641, ext. 224, at least 24 hours before each inspection.
Review, corrections and what causes delay
Minor plan checks can be done over the counter by appointment; larger projects go through full plan check. Because the division’s office is open only Monday, Tuesday and Thursday, and only in the morning and late afternoon, submittals and pick-ups need to fit those windows. Using a hauler other than Waste Resources for construction debris counts as illegal hauling and can put the permit in jeopardy, so keep every hauling and disposal ticket for the close-out.
Hawaiian Gardens building inspections
Inspections take place on Monday, Tuesday and Thursday between 1 and 4 p.m. Request each one at least 24 hours in advance by calling 562-420-2641, ext. 224. Inspections are not done in a set order or at a set time unless arranged in advance with the building inspector, so plan to have the site open for the whole afternoon window. The division posts a When to Call for Inspections bulletin (B-018), and a separate bulletin (B-019) explains how to obtain permits to clear code enforcement orders.
At the end of a project with construction or demolition waste, submit the Post-Project Form with all hauling and disposal tickets to the Building Department. Solar and battery storage systems also need a Los Angeles County Fire Department final inspection before use. Under the county schedule the city follows, a certificate of occupancy is $151.50 and a temporary certificate $227.54 before the 1.30 factor.
Want this handled start to finish?
Get a free quote →California building code in Hawaiian Gardens
The Building and Safety Division enforces the California Building Code together with the fire, mechanical, plumbing, green building and electrical codes. Its local rules on this page come from its own bulletins and ordinances: the express-permit list, the EV charging ordinance and the construction waste program run through the city’s exclusive hauler. The municipal code’s chapter adopting the state codes is not posted on the division page. FEMA’s Community Status Book lists the City of Hawaiian Gardens (community 065032) as participating in the National Flood Insurance Program, with no Special Flood Hazard Area mapped on its current maps.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Hawaiian Gardens permit search and official resources
For an existing permit, plans or inspection history, contact the Building and Safety Division at 562-420-2641, ext. 224, or Buildingtech@hgcity.org. Buyers and sellers can file a Presale Inspection Request with Community Development for a pre-sale inspection report on a residential or commercial property.
- Hawaiian Gardens Building and Safety Division
- Community Development Department
- Permits and applications
- Building Permit Application
- Express permits, no plan check required (B-005)
- Insurance and license requirements (B-004)
- Build an ADU or JADU
- Business license
- Business license fee summary
- Los Angeles County Public Works plan check and permit fees
- Los Angeles County Fire Department, Fire Prevention
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Hawaiian Gardens building permit FAQs
Who issues building permits in Hawaiian Gardens?
The city’s own Building and Safety Division in the Community Development Department at City Hall, 21815 Pioneer Boulevard.
How are Hawaiian Gardens permit fees set?
The city takes the Los Angeles County current fee for the work (Titles 26 to 29 of the county code) and multiplies it by 1.30.
Do I need plan check for a re-roof or water heater?
No plan check, but you still need a permit. Re-roofs, water heaters, fixture replacements and same-size A/C change-outs are express permits.
When are inspections?
Monday, Tuesday and Thursday from 1 to 4 p.m. Call ext. 224 at least 24 hours ahead.
What does a contractor need to pull a permit?
The original state contractor’s license or a notarized authorization, a workers’ compensation declaration and a city business license, which costs $120 a year.
Can I haul my own construction debris?
Only in certain cases approved by the Building Department. Otherwise Waste Resources, the city’s exclusive hauler, must be used.
How do I get a solar permit?
Use SolarAPP+ or the city’s streamlined process for systems up to 10 kW AC on houses and duplexes, which costs $407.57, then pass the county fire final.
Can a homeowner pull the permit?
Yes, as an owner-builder, after signing the owner acknowledgment, owner-builder and workers’ compensation forms.
Simplify Hawaiian Gardens permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Hawaiian Gardens sooner?
Let Alliance prepare, file, and track your Hawaiian Gardens permits while your crew stays on the job.
More California permitting guides
Los Angeles County
Read guide →Hermosa Beach
Read guide →Huntington Park
Read guide →Hawthorne Building Permit Guide
Read guide →Hayward Building Permit Guide
Read guide →Healdsburg Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Hawaiian Gardens permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.