Foster City’s Building Division, in the Community Development Department at City Hall, 610 Foster City Boulevard, issues building permits for the city (permit center 650-286-3231). A permit is needed for any interior or exterior change beyond cosmetic work such as painting or carpet, including replacements. Apply in eTRAKiT or in person; simple jobs can be issued the same day at Tuesday and Thursday over-the-counter appointments. Fees follow the FY 2026–27 Master Fee and Service Charges Schedule, with first plan check at 70% of the building permit fee.
What requires a building permit in Foster City?
Foster City’s rule is broad: a building permit is required for all interior and exterior changes except cosmetic ones such as carpeting or painting, and it applies whether the work is new construction or a replacement.
Over-the-counter permits
- Kitchen and bathroom remodels with no structural work
- Reroofs, insulation, drywall, stucco and siding
- Like-for-like window and garage door replacement
- Pool demolition
- Voluntary foundation upgrade to the standard Plan Set A
- Subpanels, service upgrades and lighting
- Furnace, air conditioner, heat pump and water heater replacement
- Water pipe, building drain and sewer line replacement
Permits with plan review
- New homes and multi-family buildings
- Additions to single-family homes
- Remodels with structural changes
- New detached ADUs
- Rooftop solar
- Commercial new construction and tenant improvements, including lab and biomedical spaces
- Monument signs
The city’s posted design criteria matter for structural plans: Seismic Design Category E, a basic wind speed of 95 mph, exposure C and D, and an allowable soil bearing value of 1,200 pounds per square foot. A design that relies on more than 1,200 psf needs a soils or geology report; the city also has a soils report waiver request form for smaller projects. Homes in a homeowners association may need an HOA approval letter with the application.
What Foster City decides and what the state holds
Foster City adopts the 2025 California codes with its own amendments in Title 15 of the Municipal Code (Chapter 15.02 and following), sets its fees each year, runs architectural review under its zoning code (Title 17) and its ADU rules in Chapter 17.78. The city’s Adopted Codes page also explains the state freeze on new residential code amendments from October 1, 2025 to June 1, 2031 and notes that the 2025 codes in effect since January 1, 2026 are not affected by it. Contractor licensing is the state’s.
Foster City building department: who handles permitting
The Building Division checks that every permitted project complies with the California codes and the Foster City Municipal Code. Its Chief Building Official is Chuck Venook. The San Mateo Consolidated Fire Department reviews battery storage systems and books commercial fire inspections ((650) 522-7940). Planning handles zoning, architectural review and ADU standards.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building Division, Community Development, 610 Foster City Boulevard, Foster City, CA 94404 |
| Permit center | 650-286-3231, cddpermit@fostercity.org |
| General building questions | 650-286-3227, building@fostercity.org |
| Counter hours | Monday to Friday 8 a.m. to noon and 1 to 5 p.m.; from December 4, 2026, Monday to Thursday 8 to noon and 1 to 5, Friday 8 to noon |
| Over-the-counter appointments | Tuesdays and Thursdays, 9 to 11:30 a.m. (not on holidays) |
| Online | eTRAKiT permit portal |
Foster City permit types
Every permit starts with the city’s building application, filed in eTRAKiT or at the counter. The forms page adds the owner-builder acknowledgement, the authorization for an agent to act for the owner, a separate re-roof application, the special inspection and testing agreement and project checklists (kitchen and bath templates, window and door schedules, EV chargers, panel upgrades, tankless water heaters, furnace replacement and siding).
Residential permits
- Over-the-counter jobs. Book an appointment for Tuesday or Thursday morning and bring the completed application with the documents listed for that job: for example, floor plans for a kitchen remodel, the re-roof application with an aerial map for a partial re-roof, the PG&E application number and panel details for a service upgrade, or the energy compliance form and specifications for a furnace or heat pump. Applications filed online instead are processed in one to two business days.
- Flat-fee permits. Kitchen remodels, single bathrooms, re-roofs, window and door replacements, residential EV chargers, pool demolition, battery storage and moving a furnace or water heater have set fees.
- Plan-reviewed work. Additions, structural remodels and new homes go through plan review on the timelines below.
- ADUs. ADUs are allowed in every residential district (R-1, R-2, R-T, R-3 and R-4) and in homes in the C-2 and C-M districts. On a single-family lot the options in Section 17.78.060.A include one junior ADU of up to 500 square feet, one ADU of up to 850 square feet, or a junior ADU plus a conversion ADU. The Building Division has its own ADU checklist, and the city lists pre-reviewed ADU plans.
Building or remodeling a home here? Alliance handles residential permit filing, so the crew isn't waiting on the counter.
Commercial permits
Commercial new construction, office tenant improvements and lab or biomedical tenant improvements are plan-reviewed, with a tenant improvement checklist and a commercial list of work requiring a permit. The forms page includes the C.3 and C.6 stormwater development review checklist and a screening assessment for PCBs in priority building materials. A temporary certificate of occupancy has its own inspection checklist.
For tenant improvements and new commercial builds, Alliance handles commercial permit expediting through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Architectural review. Many exterior changes go through Planning’s architectural review: administrative minor review for windows, decks, fences, front-yard paving, skylights and accessory structures; administrative major review for additions to homes that are not on the waterfront or additions under 400 square feet; and Planning Commission review for larger projects. Residential additions on waterfront lots may need a use permit from the Planning Commission or City Council.
- Preliminary review and variances. Planning offers staff or Commission preliminary project review, and handles variance requests.
- School fees. Where developer fees apply, the Building Division completes a certification for the San Mateo–Foster City School District and San Mateo Union High School District; you email it to developerfees@smuhsd.org and pay the high school district by check, by appointment only.
Foster City permit costs and fees
Fees come from the Master Fee and Service Charges Schedule for Fiscal Year 2026–27, which the city adjusts each year using the state Department of General Services building cost index. The building permit fee is set from valuation; first plan check costs 70% of it, the second check is included, and third and later checks are billed at actual cost.
| Item | Fee |
|---|---|
| Valuation $1–$500 | $68.38 |
| Valuation $501–$2,000 | $68.38 plus $8.61 per $100 |
| Valuation $2,001–$25,000 | $203.98 plus $41.11 per $1,000 |
| Valuation $25,001–$50,000 | $1,155.63 plus $28.61 per $1,000 |
| Valuation $50,001–$100,000 | $1,876.92 plus $20.32 per $1,000 |
| Valuation $100,001–$500,000 | $2,850.19 plus $15.98 per $1,000 |
| Valuation $500,001–$1,000,000 | $9,446.46 plus $13.77 per $1,000 |
| Over $1,000,000 | $16,430.94 plus $8.15 per $1,000 |
| First plan check / second / third and later | 70% of building fee / included / actual cost |
| Express plan check | Extra 50% of plan check (not for ADUs, JADUs, solar or EV chargers) |
| General Plan and code maintenance | 0.50% of value above $500 (ADUs exempt) |
| Technology fee | $5.57 plus $0.92 per $1,000 of valuation |
| Permit processing fee | $62.56 |
| Plumbing, mechanical or electrical by valuation | $15.17 per $1,000 each |
| Permit extension | $165.80 |
Worked example: a home addition valued at $200,000 falls in the $100,001–$500,000 band, so the building fee is $2,850.19 plus 100 × $15.98, or $4,448.19. First plan check adds 70% ($3,113.73), the maintenance fee 0.50% of $199,500 ($997.50) and the technology fee $5.57 plus 200 × $0.92 ($189.57), about $8,749 before trade, state and processing fees. The valuation bands do not join exactly at their edges, so use the band your valuation falls in.
Rather talk it over?
Call 1-855-478-4290 →| Item | Fee |
|---|---|
| Kitchen remodel | $510.33 |
| Single bathroom remodel | $408.85 |
| Re-roof / windows / doors including garage doors | $503.91 each |
| Residential EV charger | $503.91 |
| Pool demolition | $756.39 |
| Furnace or water heater relocation | $770.93 |
| Battery energy storage (fire review extra) | $450 |
| Rooftop solar | Exempt from building permit fees |
Penalties, deposits and planning fees
Work started without a permit costs a $399.65 processing fee on a house if the permit is applied for within 10 days, plus 100% of the permit fee at 11–30 days and 200% after 30 days; other buildings start at $800.36. A construction and demolition recycling deposit of $50 per estimated ton of debris is collected (minimum $1,000, capped at $10,000 for residential and $30,000 for commercial projects), plus a C&D application fee of $169.21 for roofs or $474.24 otherwise. Planning work is billed against deposits: $750 for minor architectural review, $2,000 for major administrative review or a variance, and $5,000 for Planning Commission architectural review or a use permit.
Trade permits and who may pull them
The Building Division issues plumbing, mechanical and electrical permits, either as part of a building permit or on their own. Trade work is charged by item (plumbing issuance is $119.59, then per fixture or device) or by valuation at $15.17 per $1,000. Many common trade jobs, such as subpanels, service upgrades, lighting, furnaces, air conditioners, heat pumps, water heaters and sewer line replacement, qualify for over-the-counter issuance.
- Business license. Anyone doing business in Foster City, contractors included, must hold a Foster City business license, issued through the city’s HdL portal ((650) 331-2802).
- Owner-builders sign the city’s owner-builder acknowledgement form; an owner who uses someone else to apply signs the authorization to act as an agent.
- Batteries. San Mateo Consolidated Fire reviews battery storage systems; its review and inspection are not included in the city’s $450 battery permit fee.
Rather not deal with the Foster City building department?
Get a free quote →How to apply for a Foster City building permit
Exterior changes, additions and ADUs may need architectural review or a use permit; schedule a Planning counter appointment if you are unsure.
Compare your project with the over-the-counter list and book a Tuesday or Thursday appointment, bringing the application and listed documents. Ask your HOA for an approval letter if the property is in one.
Upload the building application and a complete plan set, with structural calculations, energy forms and a soils report or waiver where needed.
Review times count from the day plan review fees are paid.
The second plan check is included; later rounds are billed at actual cost. Revisions and deferred submittals use the city’s revision form.
Pay any school district developer fees, the recycling deposit and the remaining permit fees, then schedule the pre-construction inspection before any work begins.
Review, corrections and what causes delay
The city’s approximate review times, in working days after fees are paid, are: residential new construction 20 days (15 for the second cycle), single-family additions 15 (10), remodels 10 (5), new detached ADUs 20 (15), rooftop solar 5 (3), stand-alone trade work 5 (3), commercial new construction 25 (20) and office or lab tenant improvements 20 (10). Express plan review is offered case by case with the Building Official’s prior approval, by appointment only, with all fees paid up front and a complete plan set; the city then tries to finish review the day you submit. The city notes that actual times depend on each project and how complete the submittal is.
Inspections in Foster City
Inspections run Monday to Friday, 8 a.m. to noon and 1 to 4 p.m., and are scheduled in eTRAKiT with at least 24 hours’ notice. The city now requires a pre-construction inspection before construction or demolition starts, booked once the permit is issued. On inspection day, check eTRAKiT after 8:30 a.m. for your one-hour window; the city may not be able to give you the time you asked for. Results appear in eTRAKiT, and questions go to 650-286-3227.
- Commercial fire inspections are booked with San Mateo Consolidated Fire at (650) 522-7940.
- Re-inspections are billed at actual cost, and after-hours inspections at overtime cost with a four-hour minimum.
- Smoke and carbon monoxide alarms. The city posts an alarm handout and a self-certification form.
- Re-roofs have their own inspection checklist, and reroofing a home with existing solar has its own handout.
- Extensions. An issued permit can be extended on request before it expires ($165.80).
Local details in Foster City
- Flood zones. Foster City participates in the National Flood Insurance Program; its current flood map is dated April 5, 2019.
- Improvement district. The fee schedule is issued jointly for the City of Foster City and the Estero Municipal Improvement District.
Want this handled start to finish?
Get a free quote →California building code in Foster City
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Foster City’s Adopted Codes page lists each 2025 California code it enforces with a link to the matching local amendment chapter, and gives climate zone 3 and risk category II for design.
Foster City building permit FAQs
Who issues building permits in Foster City?
The city’s Building Division at City Hall, 610 Foster City Boulevard (permit center 650-286-3231). The Chief Building Official is Chuck Venook.
Do I need a permit to replace a water heater or windows?
Yes. Foster City requires a permit for any interior or exterior change, including replacements, unless it is cosmetic like painting or carpet. Both jobs qualify for over-the-counter issuance, and window replacement is a $503.91 flat fee.
Can I get a permit the same day?
Qualifying jobs can be issued at over-the-counter appointments on Tuesdays and Thursdays from 9 to 11:30 a.m. Online applications for the same jobs take one to two business days.
How much does a building permit cost?
Under the FY 2026–27 schedule a $200,000 addition has a building fee of $4,448.19 and first plan check of $3,113.73, about $8,749 with the maintenance and technology fees. Kitchen remodels are a flat $510.33 and rooftop solar pays no building permit fee.
How long is plan review?
Roughly 15 working days for a single-family addition, 10 for a remodel and 20 for a new house or detached ADU on the first cycle, counted from payment of plan review fees.
Do contractors need a Foster City business license?
Yes. Everyone doing business in Foster City needs a city business license, available through the HdL portal.
What is the pre-construction inspection?
A required first inspection, scheduled in eTRAKiT after the permit is issued and before any construction or demolition begins.
Who handles fire inspections?
San Mateo Consolidated Fire. Commercial fire inspections are booked directly at (650) 522-7940.
Foster City permit search and official resources
Look up a permit, its scheduled inspections and results in eTRAKiT. A request for an author’s release of plans costs a $42.93 base fee under the fee schedule.
Inspections are where schedules slip.
Get a free quote →- Foster City Building Division
- Building permits and over-the-counter appointments
- Over-the-counter permit guide
- Plan review turnaround times
- Building inspections
- eTRAKiT permit portal
- Adopted codes and design criteria
- Building forms and handouts
- School district impact fee certification
- Master Fees and Service Charges Schedule page
- Master Fee and Service Charges Schedule FY 2026–27
- Accessory dwelling units
- Planning Division
- Business license FAQ
- 2025 California Title 24 building standards
- FEMA Community Status Book, California
Simplify Foster City permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Foster City sooner?
Let Alliance prepare, file, and track your Foster City permits while your crew stays on the job.
More California permitting guides
San Mateo County
Read guide →Half Moon Bay
Read guide →Hillsborough
Read guide →Fountain Valley Building Permit Guide
Read guide →Fremont Building Permit Guide
Read guide →Fresno Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Foster City permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.