Inside Fillmore city limits, building permits are issued by city staff in the Building & Safety Department at City Hall, 250 Central Avenue, while plan check and inspections are provided under contract by Bureau Veritas. Applications, document uploads and permit tracking run through the city’s GovWell portal. Fees come from Schedule A of Resolution 12-3357: a building permit is priced on project valuation, and plan check adds 75% of that fee for the first two submittals.
What requires a building permit in Fillmore?
The department asks owners to contact Building & Safety before starting any construction. Its fee schedule shows the work it permits: new buildings, additions and remodels priced by valuation, plus demolitions, re-roofs (with a separate pre-roofing inspection), swimming pools and spas, solar electric and solar water heating systems, fire sprinklers, illuminated signs, temporary tents, and electrical, plumbing and mechanical work. Its project handouts cover patio covers, decks, block walls, fences, panel upgrades, furnaces, water heaters, graywater systems and pool barriers, and it publishes a separate checklist and permit form for electric vehicle chargers.
Permit needed
- New homes, additions, garage work and remodels
- Patio covers, decks, block walls and accessory buildings over the exempt size
- Re-roofing, pools, spas and solar systems
- Electrical panels, EV chargers, furnaces and water heaters
- Demolition of a building
Exempt accessory structures (city handout)
- Detached sheds, playhouses and greenhouses for storage, not for living
- Up to 120 square feet in total, by the 2003 handout
- At least 6 feet from other buildings and 3 feet from side and rear lines
- No electrical, plumbing or mechanical connections
- Never in the required front yard
The accessory-structure handout dates from 2003 and counts the 120 square feet as a total for all exempt structures on the lot; a structure that misses any of its conditions falls back under the zoning ordinance and the building code. Staff can say whether a newer rule applies before you build.
What Fillmore decides and what the state holds
The city sets its own building fees, zoning code, ADU rules, design standards for murals and signs, business license tiers and encroachment rules, and its staff decide who may receive a permit: only owner-builders and licensed contractors, and never a buyer who does not yet own the property unless the current owner consents in writing. Contractor licensing belongs to the state.
Fillmore building department: who handles permitting
City staff issue building permits for private work inside Fillmore, and the city’s contract firm, Bureau Veritas, reviews the plans and performs the inspections. Building & Safety and the Planning Department share City Hall, and every building permit needs Planning’s administrative clearance first. Land outside the city limits is unincorporated Ventura County, permitted by the county’s Building and Safety Division.
Short on time to read all of this?
Get a free quote →| Detail | Information |
|---|---|
| Office | Building & Safety Department, City Hall, 250 Central Avenue, Fillmore, CA 93015 |
| Counter hours | Monday to Thursday, 8 a.m. to 4 p.m.; closed alternate Fridays |
| Building & Safety phone | 805-616-2912 |
| Inspection requests | 805-524-1500, ext. 112 (voicemail, checked daily) |
| Inspection hours | Tuesday to Thursday, 8:30 a.m. to noon |
| Planning Department | 805-946-1862, ext. 114 |
| Finance (business licenses) | 805-524-1500 |
| Portal | City of Fillmore GovWell portal for applications, uploads and permit tracking |
Fillmore permit types
A single permit covers one trade or a simple building job; a combination permit puts building, electrical, plumbing and mechanical work on one form and charges a smaller fee for each added trade. Several jobs carry flat fees, while the rest are priced from the project valuation.
Residential permits
- New homes, additions and remodels are valued from the city’s Standard Valuation Table, which the Building Official may adjust each year, and need an administrative clearance with a site plan before the building permit.
- Accessory dwelling units are approved ministerially in every residential zone and on mixed-use and multi-family lots. An ADU may be up to 1,200 square feet and 16 feet tall and must match the main house’s architecture; a junior ADU of up to 500 square feet sits inside the house or an accessory building. The ADU administrative clearance comes first, then construction plans and the building permit.
- Pools and spas have flat permit fees plus a pre-inspection, and the city’s handouts set barrier, fencing and equipment bonding rules.
- Solar and EV chargers use flat fees for solar and a dedicated checklist and form for chargers.
Building or remodeling a home here? Alliance handles residential permit expediting, so the crew isn't waiting on the counter.
Commercial permits
Commercial buildings and tenant spaces follow the same valuation table, with sprinkler systems and illuminated signs priced from it too. Major construction needs sign-off from the City Engineer, Public Works and the Fire Department on the administrative clearance, and commercial kitchens follow the city’s hood system and hood certification handouts. A new business also needs a city business license reviewed by both Planning and Building & Safety.
For tenant improvements and new commercial builds, Alliance handles commercial permit applications through issuance. More on this: commercial building permits explained.
Not sure this scope needs a permit?
Get a free quote →What comes before the building permit
- Administrative clearance. This form travels with the building permit application, and no permit is issued without its endorsements. It asks for a title report no more than a year old, and the site plan must show grades, structures, fences and walls, yards, parking, drainage and lighting.
- Discretionary approvals. Projects that need a public hearing go to the Community Development Director, Planning Commission or City Council; each resubmittal of an incomplete application adds at least 30 days of staff review.
- Zoning and hazard maps. The city’s GIS viewer shows zoning, parcel numbers and Fire Hazard zones for every parcel in the city.
- Street work. Work in the public right of way needs a city encroachment permit, which requires proof of a state contractor’s license, a city business license, liability insurance and, for utility work or closures, traffic control plans.
Fillmore building permit fees
The fee schedule linked from the Building & Safety page is Schedule A, adopted by Resolution 12-3357 on June 26, 2012 and effective July 1, 2012; it is the newest building fee schedule the city posts. Valuation includes all finish work, roofing, electrical, plumbing, heating, fire-extinguishing systems and permanent equipment, and the Building Official sets it. Fees are rounded to the nearest dollar.
| Item | Fee |
|---|---|
| Permit issuance, single permit | $24 |
| Combination permit, each added trade | $15 |
| Minimum permit fee | $48 |
| Valuation $2,001 to $25,000 | $69.25 plus $14.00 per $1,000 over $2,000 |
| Valuation $25,001 to $50,000 | $391.75 plus $10.10 per $1,000 over $25,000 |
| Valuation $50,001 to $100,000 | $643.75 plus $7.00 per $1,000 over $50,000 |
| Valuation $100,001 to $500,000 | $993.75 plus $5.60 per $1,000 over $100,000 |
| Plan check | 75% of the building permit fee (first two submittals) |
| Plan review after the second submittal or for revisions | $137.50 per hour |
| Swimming pool / spa | $345 / $230, plus a $55 pre-inspection |
| Solar electric / solar water heating | $130 / $75 |
| Demolition | $80 |
| Pre-roofing inspection | $31 |
| Title 24 enforcement fee (work that must meet Title 24) | 10% of the building permit fee |
| Reinspection / occupancy inspection | $80 each |
| After-hours inspection | $85 per hour, two-hour minimum |
| Temporary certificate of occupancy | $120 |
Rather talk it over?
Call 1-855-478-4290 →Worked example: a $20,000 remodel sits in the $2,001 to $25,000 band, so the permit fee is $69.25 plus 18 × $14.00, or $321.25, rounded to $321. Plan check adds 75%, or $241 after rounding, and a single permit carries the $24 issuance fee, for $586; where the work must meet Title 24, the schedule’s Title 24 enforcement fee of 10% of the permit fee adds $32, for $618, before trade fees and state charges. The schedule’s bands do not join exactly at $25,000 ($391.25 at the top of one band, $391.75 at the start of the next) or at $50,000 ($644.25 and $643.75), so a job near those lines should be priced by staff.
Standard plans used at more than five sites pay half the plan check fee after the first approval, and plans returned because they are incomplete pay an added plan check fee of half the original. Because the posted schedule is from 2012, confirm the current amount at the counter before budgeting a large project.
Trade permits and who may pull them in Fillmore
Electrical, plumbing and mechanical work is permitted through Building & Safety, either on its own trade permit with the $24 issuance fee or as an added trade on a combination permit at $15. Unit fees for fixtures, appliances, services and wiring are listed in Schedule A, and rough inspections for each trade can be done together by a combination inspector or separately on complex jobs.
The city’s notice is short: permits go only to owner-builders and licensed contractors. Contractors also need a Fillmore business license; a business based outside the city pays the Tier V rate of $95 plus $15 and the $4 state fee, $114 a year, plus a one-time $25 application fee, and licenses run from July 1 to June 30.
An owner thinking of pulling the permit should read the city’s Owner/Builder Advisement first. It explains that an owner who works alone carries the job personally, an owner who hires licensed subcontractors acts as the general contractor, and an owner who pays an unlicensed person can become that worker’s employer, responsible for payroll taxes and workers’ compensation insurance. The advisement still prints a $500 job value; state law now requires a contractor’s license for work of $1,000 or more.
Rather not deal with the building department?
Get a free quote →How to apply for a Fillmore building permit
Use the city GIS viewer for zoning and Fire Hazard zone, and call Planning if an ADU, sign or discretionary approval is involved.
Fill in the clearance form, attach a title report less than a year old and draw the site plan to the city’s plan requirements.
Use the Standard Valuation Sheet and the project handouts for your job; owner-builders read the advisement and contractors line up a city business license.
File through the GovWell portal or at the City Hall counter, Monday to Thursday, and pay plan check.
Bureau Veritas reviews the plans; plan check covers two submittals, and later rounds are billed hourly.
Pay the permit and issuance fees, then post the inspection record card on site with the approved plans.
Review, corrections and what causes delay
The city publishes no plan review times for building permits. The plan check fee pays for two submittals; a third review, plan revisions and incomplete plans are billed at $137.50 an hour, and plans returned as incomplete owe an added half of the original plan check fee. For planning approvals, the city says delays usually come from incomplete submittals and changes to the project description, and each resubmittal adds at least 30 days of review. Missing endorsements on the administrative clearance also hold the building permit, since none is issued without them.
Fillmore building inspections
To book an inspection, call 805-524-1500, ext. 112 and leave a message with the job address, permit number and inspection type; the line is checked daily. The department’s inspection FAQ also lists a 24-hour voicemail at 805-524-7125 and asks for requests by 5 p.m. on the business day before. The Building & Safety page gives inspection hours of Tuesday to Thursday, 8:30 a.m. to noon. A morning or afternoon visit can be requested but not guaranteed, and the inspector will not enter an empty property without prior authorization.
The city’s home inspection handout lists the usual sequence: under-slab plumbing, foundation, slab, under-floor framing, sub-floor nailing, exterior shear and roof nailing, rough electrical, plumbing, mechanical and framing (with a tub and shower pan test), lath, insulation, interior shear, water and sewer, gas test and final. Keep the inspection record card and approved plans on site, have tests done before the inspector arrives, and provide a ladder where needed. A failed inspection costs $80 to repeat.
The house may not be occupied, and utility meters are not released, until the final inspection passes. Work in the street, such as curbs, gutters and driveway approaches, is inspected separately by Public Works.
Want this handled start to finish?
Get a free quote →California building code in Fillmore
Building & Safety regulates construction under the state building codes and the city’s municipal code; the zoning articles and zoning map are posted on the city’s Zoning & Standards page, and the Building Official can say which local changes apply to a project. FEMA’s Community Status Book lists the City of Fillmore (community 060415) as participating in the National Flood Insurance Program, with flood maps effective April 11, 2024.
California builds on one statewide code, Title 24, whose 2025 edition took effect on 1 January 2026; the editions in effect when the application is submitted apply, and cities and counties may adopt local amendments only with findings filed with the state (new residential amendments are largely frozen until June 2031). Title 24 and local amendments
Fillmore permit search and official resources
Permits filed through GovWell can be tracked there. For older permits and plans, ask Building & Safety at 805-616-2912; the fee schedule charges $1.10 per sheet for document imaging up to 8½ by 14 inches and $1.50 for larger sheets. Planning applications and ADU forms are on the Applications & Checklists page.
- Fillmore Building & Safety
- GovWell planning and permitting portal
- Fee Schedule A, Resolution 12-3357
- Inspection requests
- Typical home inspections handout
- Building & Safety project handouts
- Exempt accessory structures handout
- Owner/Builder Advisement
- Administrative clearance application
- Accessory dwelling units
- Planning permit process summary
- Planning applications and checklists
- Zoning code and map
- City GIS viewer
- Business license
- Encroachment permit packet
- FEMA Community Status Book, California
Inspections are where schedules slip.
Get a free quote →Fillmore building permit FAQs
Who reviews plans and inspects work in Fillmore?
Bureau Veritas, under contract to the city; city staff issue the permits.
How much is a building permit in Fillmore?
It is based on valuation; a $20,000 job costs about $586 with plan check and the issuance fee, or $618 with the 10% Title 24 enforcement fee, under the 2012 schedule, before trade fees.
Do I need a permit for a shed?
Not for a detached storage shed within the city’s exempt limits (120 square feet in total, no utilities, set back 3 feet and 6 feet from other buildings, out of the front yard).
How do I schedule an inspection?
Leave a message at 805-524-1500, ext. 112; inspections run Tuesday to Thursday mornings.
Can a buyer pull a permit before closing?
Only with the current owner’s written consent; otherwise permits go to owner-builders and licensed contractors.
What is needed before an ADU permit?
An ADU administrative clearance from Planning, then construction plans and a building permit; ADUs are approved ministerially.
Do contractors need a Fillmore business license?
Yes. Out-of-city businesses pay $114 a year plus a one-time $25 application fee.
Simplify Fillmore permitting with Alliance Permitting
Alliance Permitting is a permit documentation and submission company in California. We prepare your paperwork, file it correctly and coordinate with the permitting authority through issuance. We are not a contractor and we do not perform licensed plan review or inspections; that work stays with your licensed team and the jurisdiction.
Ready to break ground in Fillmore sooner?
Let Alliance prepare, file, and track your Fillmore permits while your crew stays on the job.
More California permitting guides
Ventura County
Read guide →Moorpark
Read guide →Oxnard
Read guide →Folsom Building Permit Guide
Read guide →Fontana Building Permit Guide
Read guide →Fortuna Building Permit Guide
Read guide →This guide is provided by Alliance Permitting for general information about Fillmore permitting. Requirements, fees, and procedures change; confirm details with the permitting authority before relying on them.